Council archive · source document
Concurrence Agency Response - DTMR - OPW11/0116.01
RE: Noosa River Spit Erosion Protection Works -
Permanent Navigational
Requirements [)
Rick a Bertram to: Andrew Brown 28/02/201212:08 PM
Cc: Peter E Kleinig, Glenn N Hale, Richard C Johnson
Hello Andrew,
As discussed in our recent telephone conversation, I have undertaken a site visit of construction works
on the Noosa Spit.
Maritime Safety Queensland’s aids to navigation requirements for the completed works are as follows.
1. There are no MSQ requirements for aids to navigation on the training wall. The wall is above the
high water mark and would be clearly visible during daylight hours. As discussed if council wishes
to install a downward facing solar street type light, MSQ would have no objection as long as the
light was shielded so as not to create a hazard to boaters.
2. MSQ will require a series of temporary buoys to be placed on the seaward side of the sunken wall.
There is to be three SLB700 type buoys placed approximately 5 metres from the wall so as to
mark the extremities and centre of the wall. The buoys are to be yellow in colour and have the
words ’OBSTRUCTION’clearly displayed on all four sides of the top mark. The is no requirement
for a light on the buoys.
MSQ is able to supply and install the buoys on your behalf and enter into an agreement for a
maintenance program if this is suitable to you. I will be able to supply a quote for these works early
next week.
It is envisaged that the buoys will only be required until the sand has backfilled the beach out to the
sunken wall. Once this has been achieved the buoys can be removed.
Thank you
Rick Bertram
AlArea Manager (Sunshine Coast) 1 Marine Operations (Brisbane)
Maritime Safety Queensland 1 Department of Transport and Main Roads
Mooloolaba Old Pilot Station 11 Parkyn Parade 1 Mooloolaba Old 4557
PO Box 1094 1 Mooloolaba Old 4557
P: (07)547784191 F: (07)54446697
M: 0419778166
E: [email protected]
W: www.msg.gld.gov.au
Tomorrow’s Queensland: strong, green, smart, healthy and fair www.toward02.gld.gov.au
-
~ Please consider the environment before printing this email
Andrew Brown IRiCk, Thanks for the response. No dramas ab... 23/02/201211 :40:21 ~M
From: Andrew Brown <[email protected]>
To: "[email protected]" <[email protected]>
Date: 23/02/2012 11:40 AM
Subject: RE: Noosa River Spit Erosion Protection Works -
Permanent Navigational Requirements
Rick,
Thanks for the response. No dramas about leaving it till Monday,
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Concurrence Agency Response - DTMR - OPW11/0116.01Related documentApplication case desk ↗
About this file
- File size
- 2.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.