24-099 RENE (58) - Fullset [B]
LOCAL AUTHORITY
1. THE LOCAL AUTHORITY IS NOOSA SHIRE REGIONAL COUNCIL.
GENERAL NOTES
1. ALL ENGINEERING DRAWINGS PRODUCED BY NAXOS ENGINEERS FOR THIS PROJECT ARE TO BE READ
AND UNDERSTOOD COLLECTIVELY . IF THERE IS A DISCREPANCY WITH THE INFORMATION PRESENTED,
NAXOS ENGINEERS ARE TO BE NOTIFIED IMMEDIATELY.
2. WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH CURRENT AUSTRALIAN AND LOCAL AUTHORITY
STANDARD DRAWINGS AND SPECIFICATIONS UNLESS NOTED OTHERWISE.
3. WORKS AND MATERIALS SHALL BE IN ACCORDANCE WITH LOCAL AUTHORITY STANDARDS, DESIGN AND
CONSTRUCTION SPECIFICATIONS AND STANDARDS DRAWINGS.
4. ALL WORKS SHALL COMPLY WITH THE WORKPLACE HEALTH & SAFETY ACT.
5. THE CONTRACTOR IS TO OBTAIN THE LOCATION OF ALL SERVICES AND PROTECT THESE SERVICES
PRIOR TO WORKING IN THEIR VICINITY. ANY DAMAGE WILL BE REPAIRED AT THE CONTRACTORS
EXPENSE.
6. THE CONTRACTOR SHALL CONTACT 1100 (DIAL BEFORE YOU DIG) AND OBTAIN ADVICE AND LOCATION
RECORDS OF THE LOCAL MUNICIPAL SERVICES, ENERGEX, AGILITY (GAS), SANTOS (OIL), ETC. PRIOR TO
COMMENCING WORKS.
7. THE CONTRACTOR SHALL CONFIRM ALL EXISTING AND PROPOSED LEVELS PRIOR TO COMMENCING
CONSTRUCTION AND SHALL REPORT ANY DISCREPANCIES TO THE ENGINEER.
8. ALL LEVELS TO AUSTRALIAN HEIGHT DATUM (AHD).
9. ALL DIMENSIONS ARE IN METRES (PLANS AND SECTIONS) AND MILLIMETRES (DETAILS) UNLESS NOTED
OTHERWISE (UNO).
10. DO NOT SCALE DRAWINGS.
11. NEW WORKS SHALL BE JOINED NEATLY TO EXISTING. THE CONTRACTOR SHALL SEEK THE PARTICULAR
REQUIREMENTS FOR SUCH WORK FROM THE ENGINEER BEFORE PROCEEDING.
12. PRIOR TO COMMENCING WORKS, THE CONTRACTOR IS TO IDENTIFY AND BE SATISFIED OF THE
CORRECT DEPTH AND ALIGNMENTS OF ALL EXISTING SERVICES HAVE BEEN LOCATED (WHETHER
INDICATED ON THE PLANS OR NOT).
13. CLASHES OR CONFLICTS TO BE NOTIFIED TO THE SUPERINTENDENT IMMEDIATELY.
14. THE CONTRACTOR IS TO PROVIDE DILAPIDATION REPORT OF EXISTING SERVICES AND STRUCTURES
PRIOR TO CONSTRUCTION.
15. ANY DAMAGE TO EXISTING INFRASTRUCTURE OR SERVICES SHALL BE REPAIRED TO ORIGINAL
CONDITION OR BETTER AT THE CONTRACTOR'S EXPENSE AND THE SERVICE PROVIDER NOTIFIED
16. THE CONTRACTOR IS TO ALLOW FOR ALL SERVICE STRUCTURES (POWER POLES, COMMUNICATIONS
PITS, VALVE BOXES ETC.) TO BE MODIFIED TO SUIT THE FINISHED SURFACE LEVEL IN ACCORDANCE
WITH THE SERVICE PROVIDES SPECIFICATIONS.
17. WHERE OVERHEAD PUBLIC UTILITY LINES AND SURFACE DRAINAGE WORKS AND/OR UNDERGROUND
PIPES, CONDUITS, OR CABLES, EXIST IN THE VICINITY OF THE WORKS, THE CONTRACTOR SHALL TAKE
CARE TO PROTECT SUCH FACILITIES FROM DAMAGE, AND IN THE CASE OF ANY DAMAGE OCCURRING
TO SUCH FACILITIES, THE MATTER SHALL BE IMMEDIATELY REPORTED TO THE RELEVANT AUTHORITY
AND TO THE SUPERINTENDENT. THE COST OF THE NECESSARY REPAIRS OR RENEWALS SHALL BE
BORNE ENTIRELY BY THE CONTRACTOR.
18. NATURAL SURFACE LEVELS ARE FROM DIGITAL TERRAIN MODEL AS SUPPLIED BY THE PROJECT
SURVEYOR.
19. THE CONTRACTOR SHALL NOT ENTER ADJACENT PROPERTIES WITHOUT PRIOR WRITTEN APPROVAL
FROM THE PROPERTY OWNER.
20. THE SITE IS TO BE LEFT NEAT AND TIDY AT THE COMPLETION OF THE WORKS. ALL RUBBISH AND DEBRIS
SHALL BE REMOVED AND DISPOSED OF IN ACCORDANCE WITH THE LOCAL AUTHORITY REQUIREMENTS
AND SATISFACTION.
21. THIS DRAWING SHALL BE READ IN CONJUNCTION WITH ALL OTHER WORKING DRAWINGS AND
SPECIFICATIONS. ALL DISCREPANCIES AND VARIATIONS SHALL BE REFERRED TO THE ENGINEER
BEFORE PROCEEDING WITH THE WORK.
INSPECTION NOTES
1. THE CONTRACTOR SHALL LIASE WITH THE ENGINEER AND/OR LOCAL AUTHORITY TO PRE-SCHEDULE
REQUIRED INSPECTIONS FOR ALL HOLD POINTS ASSOCIATED WITH ANY ASPECTS OF THE WORKS.
2. THE CONTRACTOR SHALL PROVIDE A MINIMUM OF 48 HOURS NOTICE FOR ALL INSPECTIONS TO BE
UNDERTAKEN BY THE ENGINEER. NOTIFICATION OF REQUIRED INSPECTIONS BY THE CONTRACTOR ARE
DEEMED TENTATIVE ONLY UNTIL SUCH TIME AS THE ENGINEER HAS VERIFIED THE INSPECTION DATE
AND TIME.
3. THE ENGINEER RESERVES THE RIGHT TO DEEM ANY ASPECT OF THE WORKS CONSTRUCTED
UNSATISFACTORY OR DEFECTIVE WITH A REQUEST FOR RECTIFICATION PROVIDED AS A FORMAL
WRITTEN INSTRUCTION TO THE CONTRACTOR. ALL DEFECTIVE WORKS SHALL BE RECTIFIED AT THE
CONTRACTOR'S EXPENSE INCLUSIVE OF DELAYS RESULTING FROM SUCH DEFECTS.
ISSUE FOR APPROVAL
Associated Consultant: Surveyor: RP Description: North: Client: Scale:
AMENDMENTS
E.J. GRECH & ASSOCIATES PTY LTD
No. DATE DESCRIPTION DRAWN No. DATE DESCRIPTION DRAWN
CRUC SURVEYS LOT 58 E.J. GRECH & ASSOCIATES PTY. LTD. N.T.S.
A 28.08.2024 PRELIMINARY ISSUE NP Plan Ref.: 1729_TP RP228905
APPROVAL
Project: Job No.
14.10.2024 ISSUE FOR APPROVAL JB Level Datum: Size of Land: Orig. Drg. Size
RL
2863m²
PROPOSED WAREHOUSE AND TRADE HUB DEVELOPMENT 24-099
T 1300 598 544
Approved: GREGG TYQUIN Drawn: Design: IMAGERY, CADASTRAL AND SURVEY DATA DISCLAIMER E [email protected] 58 RENE STREET Drawing No.
NP NP While every care is taken by NAXOS Engineers Pty Ltd to ensure the accuracy of the data
supplied by local authorities, dial before you dig (dbyd) records, as constructed information Level 1, Suite B
NOOSAVILLE, QLD 4566 C005
and detailed survey, we make no representations or warranties about its accuracy, reliability, 557 Gregory Terrace, Fortitude Valley Qld 4006
Checked: Supervisor: completeness or suitability for any particular purpose and disclaim all responsibility and all PO Box 224, Spring Hill QLD 4004 Title: Revision:
liability (including without limitation, liability in negligence) for all expenses, losses, damages
RPEQ. 1528 Date: 14.10.2024 GT GF (including indirect or consequential damage) and costs which may be incurred as a result of
data being inaccurate or incomplete in any way and for any reason.
NAXOSENGINEERS.COM.AU GENERAL NOTES B
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.