24-099 RENE (58) - Fullset [B]
DETAILS PROVIDED BY IECA (2008)
MATERIALS INSTALLATION (COMPOST-FILLED SOCKS)
ROCK: 150 TO 300mm EQUIVALENT DIAMETER, 1. REFER TO APPROVED PLANS FOR LOCATION
HARD, EROSION RESISTANT ROCK. AND INSTALLATION DETAILS. IF THERE ARE
QUESTIONS OR PROBLEMS WITH THE
SANDBAGS: GEOTEXTILE BAGS (WOVEN LOCATION OR METHOD OF INSTALLATION
SYNTHETIC, OR NON-WOVEN CONTACT THE ENGINEER OR RESPONSIBLE
BIODEGRADABLE) FILLED WITH CLEAN ON-SITE OFFICER FOR ASSISTANCE.
COARSE SAND, CLEAN AGGREGATE, OR
COMPOST. 2. PRIOR TO PLACEMENT OF THE SEDIMENT
TRAP, ENSURE THE DRAINAGE CHANNEL IS
INSTALLATION (ROCK CHECK DAM) DEEP ENOUGH TO PREVENT WATER BEING
UNSAFELY DIVERTED OUT OF THE DRAIN
1. REFER TO APPROVED PLANS FOR LOCATION
ONCE THE CHECK DAMS ARE INSTALLED.
AND INSTALLATION DETAILS. IF THERE ARE
QUESTIONS OR PROBLEMS WITH THE
3. LOCATE EACH SOCK AS DIRECTED WITHIN
LOCATION OR METHOD OF INSTALLATION
THE APPROVED PLANS, OR OTHERWISE AT
CONTACT THE ENGINEER OR RESPONSIBLE
SUCH A SPACING TO ACHIEVE THE REQUIRED
ON-SITE OFFICER FOR ASSISTANCE.
SEDIMENT TRAPPING OUTCOMES.
2. PRIOR TO PLACEMENT OF THE SEDIMENT
4. PLACE EACH SOCK TO THE LINES AND PLACEMENT OF CHECK DAM SEDIMENT TRAPS
TRAP, ENSURE THE DRAINAGE CHANNEL IS
PROFILE SHOWN IN THE APPROVED PLAN OR
DEEP ENOUGH TO PREVENT WATER BEING
AS DIRECTED BY THE SITE SUPERVISOR.
UNSAFELY DIVERTED OUT OF THE DRAIN
ONCE THE CHECK DAMS ARE INSTALLED.
5. ENSURE EACH SOCK EXTENDS UP THE
CHANNEL BANKS (WHERE PRACTICAL) TO A
3. LOCATE EACH CHECK DAM SEDIMENT TRAP
LEVEL AT LEAST 100mm ABOVE THE CREST
AS DIRECTED WITHIN THE APPROVED PLANS,
LEVEL OF THE CHECK DAM.
OR OTHERWISE AT SUCH A SPACING TO
ACHIEVE THE REQUIRED SEDIMENT TRAPPING
OUTCOMES.
REMOVAL
4. IF THE CHECK DAMS ARE ALSO BEING USED
TO CONTROL EROSION WITHIN THE DRAINAGE 1. WHEN CONSTRUCTION WORK WITHIN THE
CHANNEL, THEN LOCATE EACH SUCCESSIVE DRAINAGE AREA ABOVE THE CHECK DAMS
CHECK DAM SUCH THAT THE CREST OF THE HAS BEEN COMPLETED AND DISTURBED
IMMEDIATE DOWNSTREAM DAM IS LEVEL WITH AREAS SUFFICIENTLY STABILISED TO
THE CHANNEL INVERT AT THE IMMEDIATE RESTRAIN EROSION, THE DAMS MUST BE
UPSTREAM CHECK DAM. REMOVED, UNLESS THE SEDIMENT TRAPS ARE
TO REMAIN AS A PERMANENT FEATURE.
5. CONSTRUCT EACH CHECK DAM TO THE
DIMENSIONS AND PROFILE SHOWN WITHIN 2. REMOVE COLLECTED SEDIMENT AND
THE APPROVED PLAN. DISPOSE OF IN A SUITABLE MANNER THAT WILL
NOT CAUSE AN EROSION OR POLLUTION
6. WHERE SPECIFIED, THE CHECK DAMS MUST HAZARD.
BE CONSTRUCTED ON A SHEET OF
GEOTEXTILE FABRIC USED AS A DOWNSTREAM 3. REMOVE AND APPROPRIATELY DISPOSE OF
SPLASH PAD. ALL MATERIALS INCLUDING ANY GEOTEXTILE
FABRIC.
7. EACH CHECK DAM MUST BE EXTENDED UP
THE CHANNEL BANK (WHERE PRACTICABLE) 4. STABILISE THE DISTURBED CHANNEL WITH A
TO AN ELEVATION AT LEAST 150mm ABOVE THE LINING OF FABRIC AND ROCK, OR ESTABLISH
CREST LEVEL OF THE DAM. VEGETATION AS APPROPRIATE.
MAINTENANCE
1. INSPECT EACH CHECK DAM AND THE
DRAINAGE CHANNEL AT LEAST WEEKLY AND
AFTER RUNOFF-PRODUCING RAINFALL.
2. CORRECT ALL DAMAGE IMMEDIATELY. IF
SIGNIFICANT EROSION OCCURS BETWEEN
ANY OF THE CHECK DAMS, THEN CHECK THE
SPACING OF THE DAMS AND WHERE
NECESSARY INSTALL INTERMEDIATE CHECK
DAMS OR A SUITABLE CHANNEL LINER.
3. CHECK FOR DISPLACEMENT OF THE CHECK
DAMS.
4. CHECK FOR SOIL SCOUR AROUND THE
EROSION IS OCCURRING, CONSIDER
EXTENDING THE WIDTH OF THE CHECK DAM
TO AVOID SUCH PROBLEMS.
5. IF SEVERE SOIL EROSION OCCURS EITHER
UNDER OR AROUND THE CHECK DAMS, THEN
SEEK EXPERT ADVICE ON AN ALTERNATIVE
TREATMENT MEASURE.
6. DE-SILT SEDIMENT TRAP IF THE SEDIMENT
LEVEL EXCEEDS 1/3 THE CREST HEIGHT.
7. DISPOSE OF COLLECTED SEDIMENT IN A
SUITABLE MANNER THAT WILL NOT CAUSE AN
EROSION OR POLLUTION HAZARD.
ISSUE FOR APPROVAL
AMENDMENTS Associated Consultant: Surveyor: RP Description: North: Client: Scale:
No. DATE DESCRIPTION DRAWN No. DATE DESCRIPTION DRAWN
E.J. GRECH & ASSOCIATES PTY LTD CRUC SURVEYS LOT 58 E.J. GRECH & ASSOCIATES PTY. LTD. N.T.S.
A 28.08.2024 PRELIMINARY ISSUE NP Plan Ref.: 1729_TP RP228905
APPROVAL
Project: Job No.
B 14.10.2024 ISSUE FOR APPROVAL JB Level Datum: Size of Land: Orig. Drg. Size
RL
2863m²
PROPOSED WAREHOUSE AND TRADE HUB DEVELOPMENT 24-099
T 1300 598 544
Approved: GREGG TYQUIN Drawn: Design: IMAGERY, CADASTRAL AND SURVEY DATA DISCLAIMER E [email protected] 58 RENE STREET Drawing No.
NP NP
While every care is taken by NAXOS Engineers Pty Ltd to ensure the accuracy of the data
supplied by local authorities, dial before you dig (dbyd) records, as constructed information Level 1, Suite B
NOOSAVILLE, QLD 4566 C213
and detailed survey, we make no representations or warranties about its accuracy, reliability, 557 Gregory Terrace, Fortitude Valley Qld 4006
completeness or suitability for any particular purpose and disclaim all responsibility and all PO Box 224, Spring Hill QLD 4004 Title: Revision:
Checked: Supervisor:
liability (including without limitation, liability in negligence) for all expenses, losses, damages EROSION AND SEDIMENT CONTROL ROCK
RPEQ. 1528 Date: 14.10.2024 GT GF (including indirect or consequential damage) and costs which may be incurred as a result of NAXOSENGINEERS.COM.AU B
data being inaccurate or incomplete in any way and for any reason.
CHECK DAM DETAILS
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.