2.1.4. Mitigation Scenario
When comparing the peak flows in the existing and developed scenarios, increases in the peak discharge
are predicted at the site outlet. A detention basin is proposed to attenuate peak flows discharging from the
site to demonstrate non-worsening and meet the legal point of discharge requirements.
All modelling parameters remain consistent between the developed and mitigated scenarios, with the
addition of detention basins. The proposed basin structure details are summarised in Table 2-7 with
Concept Engineering Drawings included in Appendix A.
Table 2-7: Summary of Basin Structure Details
Sub-catchment Existing Basin Upgraded Basin
Elevation (RL) Storage (m3)
0 0 0
0.1 26 35
0.2 55 74
0.3 87 117
0.4 123 163
0.5 162 214
0.6 205 268
0.7 251 327
0.8 301 391
0.9 338 458
0.97 - 508
Pipe Outlet 1 x 450mm RCP at RL0.0m 1 x 450mm RCP at RL0.0m
Bioretention Outlet Not modelled 1 x 450mm RCP at RL-0.9m
Weir Outlet 4m wide at RL.0.60m 8m wide at RL.0.60m
Crest Level RL 0.97m RL 0.97m
Q100CC WSL RL 0.83m RL0.78m
Q100CC Freeboard 0.14m 0.19m
Peak flows from the mitigated scenario modelling are presented in Table 2-8 with a comparison against the
existing peak flows. The results show that there is non-worsening for events up the 1% AEP. The intent of
sizing the detention basin is to mitigate flows up to the 10% AEP storm event to ensure non-worsening of
discharges into the downstream flow path. In larger events, flows from the site will start to sheet flow
across the rear of the site to Cooroora Creek. As the discharge point for the site becomes inundated from
Cooroora Creek flooding in the major storm event (refer Figure 1-2), it is considered that the non-worsening
has been achieved.
Table 2-8 contains a summary of peak mitigated flows for the 1% AEP event across all storm durations. The
analysis demonstrates non-worsening has been achieved across a range of durations.
23-0167SMP01-V2 | Stormwater Management Plan | 33 Pavilion Street, Pomona Page 17
See the original