    Erosion and Sediment Control Inspection Report




Purpose of Meeting        Erosion and Sediment Control inspection

Project                   26 Sallwood Court, Pinbarren


Prepared By               Luke Hamilton                  Phone No    0412 739 706
Date                      15-10-2021

Present                   Kathy Ford                 Email    [email protected]

                          Luke Hamilton              Email     [email protected]

Introduction

Aussie Environmental were engaged by Kathy Ford to review the current level of erosion and
sediment control (ESC) on her property at 26 Sallwood Court, Pinbarren.

Scope and Purpose
Noosa Council as part of their Advisory e-mail requires - Action 2 “Make the site stable
and immediately contact a Certified professional in Erosion and Sediment Control
(CPESC) to put in place suitable erosion and sediment controls to prevent the runoff
of sediment from the property”

A site inspection was completed on site on 15 October 2021 by Certified Professional in Erosion
and Sediment Control (CPESC) being Luke Hamilton (Operations Manager for Aussie
Environmental).

The advice identified herein will assist the land owner in demonstrating compliance with their
General Environmental Duty.

CPESC - site observations

• The site is located on private land with some earthworks completed over the last 2 months, for:
  access to an existing dam; to clean out sediment build-up in an existing dam; remove and chip
  weed vegetation; re-profiling and provide surface protection (Geofabric and Rock) to the drainage
  line leading to the dam; and re-landscaping the property. The terrain is hilly surrounded by rural
  living property. The property is over 1 Ha, has a dwelling, drainage easement, dam and cleared
  grass areas and gardens.

• Previously most of the land was used as horse paddocks with the new owners re-landscaping,
  removing the Camphor Laurels and improving drainage protections and improving the existing
  dam’s capacity. At the time of the inspection earthworks were under a stop works order from
  Council with the dam and part of drainage line cleaned out and reprofiled, geofabbed and rocked.
  Silt fence was in place and mulch and topsoil stockpiled. Sub-soil exposure was still evident around
  and within the dam, drainage lines and along the access areas.

•     The soil on site is a medium clay texture. The slopes are less than 8% grade, however the drainage
      easement’s catchment is quite steep resulting in rapid runoff and slow permeability. Slope stability
      would be considered good; however, any exposure would generate turbid runoff.
Log in to download the original file

26 Sallwood Court Pinbarren- ESC inspection 15-10-2021 (1).pdf · 187 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 3 pages

Page 2

•   The one drainage line (partly Council drainage easement) is un-named tributary to Pinbarren
    Creek.

•   Due to the time of the year (High erosion risk based on average monthly rainfall), the large extent of
    the uphill catchment and the proximity to a waterway, any exposure of any surface would have high
    erosion risk.

•   At the time of the inspection the sediment controls (dam and silt fence) were adequate for the
    amount of exposure, however the level of erosion control is lacking and finalisation of the
    earthworks needs to continue to remedy this issue.

•   It was noted that the land-owner has a large supply of mulch on-site. This mulch is excellent for
    erosion control (covering exposed soils) and a mulch berm correctly installed (refer attached
    drawing) has a higher sediment control standard than silt fence.


CPESC – advice and corrective actions

Following is Best Practice for this sort of development with reference to the IECA Best Practice
Erosion and Sediment Control Guidelines (IECA Guidelines) document [2008, International Erosion
Control Association (Australasian Chapter)]

    Table Book 2 -G3 - Best practice site clearing and rehabilitation requirements

     Risk                                        Best Practice Requirements
     All Cases          • All reasonable and practicable steps taken to apply best practice erosion
                          control measures to completed earth works, or otherwise stabilise such
                          works, prior to anticipated rainfall-including existing unstable, undisturbed,
                          soil surfaces. under the management or control of the
                          building/construction works.

     High               • Land clearing limited to maximum 4 weeks of work.
                        • Disturbed soil surfaces stabilised with minimum 75% cover within 10 days
                          of completion of works within any area of a work site.
                        • All planned garden beds protected with a minimum 75mm layer of organic
                          Mulching, heavy Erosion Control Blanket, Rock Mulching, or the
                          equivalent.
                        • Staged construction and stabilisation of earth batters (steeper than
                          6H:1V) in maximum 3m vertical increments wherever reasonable and
                          practicable.
                        • The use of turf to form grassed surfaces given appropriate consideration.
                        • Soil stockpiles and unfinished earthworks are suitably stabilised if
                          disturbance is expected to be suspended for a period exceeding 10 days.


    Table Book 2 -G3 - Best practice channel clearing and stabilisation requirements

     Risk                                       Best Practice Requirements
     All Cases          • All reasonable and practicable steps taken to apply best practice erosion
                          control measures to completed channel works, or otherwise stabilise such
                          works, prior to an anticipated 1ncrease in stream flow.

     High               • Channel clearing limited to maximum 2 weeks of programmed work.
                        • Disturbed soil surfaces stablised with minimum 90% cover within 5 days
                          of completion of works within any constructed drainage channel or
                          waterway.
                        • Appropriate consideration given to the use of rock protection,
                          biodegradable Erosion Control Mesh or the equivalent, on all erodible
                          stream banks subject to high velocity flows.
                        • Non-completed channel works stabilised if exposed, or expected to be

Page 3

                            exposed, for a period exceeding 10 days.




     Drainage Controls.

 -   Unfortunately, with steep slopes and the large extent of uphill catchments it is very important to
     divert upslope runoff around any future soil disturbance. This cannot be achieved on this site.

 -   It appears that the channel protection has matched existing rip rap protection which would have
     been hydraulically sized to the upstream catchment, slope and expected flows.

 -   The dam spillway (which was shaped but not protected) should also match the rock protection
     upstream.


     Erosion Controls


 -   All planned garden beds protected with a minimum 75mm layer of organic Mulching.

 -   The use of turf to form grassed surfaces given appropriate consideration or hydromulching (3T/ha
     of mulch, 40kg/ha cover crop, 40kg/ha perennial grasses, 250kg/ha fertilizer, tackifier).

     Sediment Controls-
 - Site soils have a high clay content and any exposure would generate turbid runoff. Sediment
     Controls such as silt fencing or mulch bunds should be in place (which they are). Do not remove
     until there is 80% cover.

 - The dam is acting as a sediment basin/trap at present. Use Superfine Gypsum broadcasted over
     surface or preload the gypsum along the inlet channel. This will help settle the clay practical and
     improve dam clarity/water quality.



Luke Hamilton, Operations Manager
Certified Professional in Erosion and Sediment Control (CPESC No. 9205)
Aussie Environmental
Phone: 07 5315 5431
Mob: 0412 739 706
Address: 19 Central Park Drive, Yandina, QLD 4561
Postal Address: P O Box 525, Yandina, QLD 4561
Email: [email protected]

Page 4

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.