Original source · versioned page text
07/1452 - Preliminary building works assessable against planning scheme [As Published]
C) Fro |
as NG@KORK Ye Checklist - Applications Involving Land /
Development & Land Use Sections
IDAS APPLICATION
REFERS,
This checklist should be used for any IDAS application. Please check each of the following items before ackepting-arr|
application at the counter.
4. APPLICATION FORMS ree
4.1. Form PartA
4.1.1. Ensure that the form is fully completed. V1
1.1.2 In the case of an MCU or Op Works below the high-water mark, owners consent is required.
1.1.2.1 If there are multiple owners, the consent of each owner is required.
1.1.2.2 If the owner of the land is a company, either ACN No. or Company Seal required.
1.2. Form1 Part B-O Supporting Information
1.1.2 Ensure that for each box checked on Form A, the relevant additional Forms B-O are attached. [4]
1.1.2.1. Ensure that each of Forms B-O which are attached are fully completed. [A
2. REFERRAL INFORMATION. - * :
2.1. Ensure that items 1-23 have been checked and/or completed with regard to referrals. 7]
3.” ENVIRONMENTALLY RELEVANT ACTIVITIES |
3.1. Ensure that Part G is completed if EPA referral is required.
3.2. Where EPA is delegated to Council (see * in ERA checklist), ensure that the correct application
fee is paid and recorded on the application.
4. " FORM 2.- REQUEST TO CHANGE APPROVAL -— . *
4.1. Ensure that items 1-28 have been checked and/or completed including information regarding
applicant details and owners consent.
‘5. PLANS?) ep.
5.1 Ensure that at feast 6 sets of the Plan of Development (5 for Reconfiguration and Operational
Works) accompanies the application. In addition ensure that each set is complete.
5.2 Ensure that 1 of the copies of the Plan of Development is in an A3 or A4 format and is
unbound.
6: ‘SUPPORTING INFORMATION 77 ke
6.1 Ensure that at least 6 copies of any report accompanies the application (5 for Reconfiguration
and Operational Works). {f the application is accompanied by a covering letter, ensure that it is
capable of reproduction.
6.2 In the case of reports, ensure that 1 of the copies is in an A3 or A4 format and is unbound.
7. SORBET Sea TTT eB
7.4 Ensure that the application fee, as ; determined from the ‘Council’ Ss adopted scale of fees, L/L
accompanies the application or has been paid.
7.2. Ensure that the fee which has been paid is recorded on the application form. /
Y
Receiving Officer fs Date .. 73 ffs
Having completed this form and accepted th application, please deliver both to the following IDAS Application Receiving
trays:-
« Ifthe application is for a Material Change of Use exclusively -AOP1’s desk in the Land Use Section.
« fthe application is for an Material Change of Use & Reconfiguration - AOP1’s desk in the Land Use Section.
« {fthe application is for Operational Works (for parking, access, sewerage or drainage) exclusively - AOD2 in the
Land Development Section.
¢ inall other circumstances — AOP1's desk in the Land Use Section.
Please DO NOT leave the application at the counter and DO NOT deliver the application to Records.
SEP 1 g:\ant\forms\application checklist.doc
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 22 pages
Page 2
COASTAL EX Gns CERTIFICATIONS NOOSA SHIRE COUNCIL (LAND USE) Po Box 141 Tewantin Q 4565 Date: 20 July, 2007 The Development Permit “Preliminary Building Works” for: G Property at: 12 LAKE COOROIBAH RD, LAKE COOROIBAH Lot 3 RP 136234 Our Ref Number: 27239 Please find attached Code application for a Preliminary Building Approval for a proposed garage to be located in an Environmental Protection area. The proposal is for a 81m? garage, the vegetation to be remved is to be minimal & will comply with the code section 13.9(s2.1) maximum of 10m clearing of vegetation around the building. Yours Faithfully Michael Bowcock (Private Building Certifier A23659) attached: e FormA e =6FormE « —IDAS checklist e Fee $650.00 51 Cogill Road, Buderim Q. 4556 PO Box 890, Buderim Q. 4556 Telephone: 07 5476 9988 Facsimile: 07 5476 9987 Mobile: 0414 954 390 ra
Page 3
INTEGRATED PLANNING ACT-1997 : oo . _ Part A, Version 2.4, 29 May 2006
“The completion of all applicable questions on Part Ai 5 Mandatory | for all, applications. Part A must be accompanied by. ie completed IDAS Assessment Checklist if
required, and by one,(1) or more, other completed: Of the:-Form-as.required it ‘parts:of the: Form refer to
Any information fequested:in the form may be provided in an'attachment to the application, For further information about conipleting the following details, refer to Guide 1
Description’ of land . whe :Streetiaddress: (nciuaing house number, street Adame, suiburb/locality name & postcode) (it applicable)
Al land the subject oft tha application, mustbe | 1
identified; However adescripton-of the fandis not °° (2a CA Ke Comes C1 BAH 2H EWA NT! N.
if
ErvvanesiRo mobile of tiporary 2. - of water body: or watercourse, within which: the:devvelopment is proposed: (if applicable) !
° o on-plan description eg Lott23 on RP 4567y1- GPS coordinate
RP Bb23y. |
4,. TI .
fos z hey land’ on which'the development i is. proposed; ‘or
Advice for completing: Q3:~ Most land can be:
identified by 2 lot on plan description: These details
can be obtained from title documents.or ‘ova the
local goverriment. .
However, if the land ¢ on \ which the iGiolopment iss.
proposed does got have a lot on plan description (i.e,
the davelopmentis propased in a waler body or oe OC (ii) the tand adjoining the water body or watercourse, within which the development is
watercourse) provide ~ . . . «| proposed; or :
the lot description fa oe
0 atontgiieeneee - rhe -tooO (ii: the water body. or watercourse. -
(1) GPS coordinates where there is:no:
atjiningradjacent land in Mceton Bayh . {5.° Shop / tenancy number: 6. Storey/level: - - 7. Total area of land: (m? or ha}:
J L i J
j Bay, Woocoo etc) ff applicable)
J
Local Goverment Act 1993. » Port’ authority: fo for’ the strategic port land‘or ‘strategic port land tidal area on whiicti the ,”
Afvice forccimsieiing G9- Ca'zppliesi# |
developments on salegc portland ora svatege. development is proposed:’ (eg. Port.of Brisbane, Port of Townsville) (if applicable)
pot land dat area, For more etal refer to Guide 11» Q —_— : ‘|
Proposal details -./ - elt 10: Existing use of the.land: (eg. vacant, single house, shop etc)”
f there is insufficient room’ available, detaits may be ACMAN
oe: in an attachment to the application, . ——. v Tv LAC N i)
‘ . : 11. Proposed use of the land: eg. 6 unit apartment building, 30 Jot residential subdivision; ERA for aquaculture in
ponds with a total area of 7 ha for which wastes are released into waters etc).
[ Newl GARAGE. |
Other applicable parts of Form 4 12. Other parts of Form 1 completed as part of this application: (eg. Part D, Part J, etc)
Part A must afways be ied by oth . v “Qe “
completed parts of Form 1. For information about KAR B e+ pre evnestcrte tp
when a part of Form 1 may apply refer to Guide 1.
a Od
Applicant details 13. Applicant's name; 15. Contact Co
Cleary identify who is making the application. The
applicant need ot be the owner of the land.
When signing and todging this apafication 14. can number: 16. \ sis oma ESSE a
The applicant is responsible for ensuring the
information provided is correct. The assessment
Manager, any referral agency & the Chief Executive .
20 _bittion
(where applicable) will rely on this information when | 17. Postal address:
19. Date:
assessing and deciding the application, FO
fs = a contact person i
must be shown. 18.
Page 4
Part A, Version 2.4, 29 May 2006
.. Land owner's consent to the making of this application Pe
involve a prescribed State resource,
Section 3, 1{10){a}{it) of the TPA prescribes that an
without evidence of the resource entitlement.
Advice for completing Q21 & 22
Refer toschedule'10 of the Integrated Planning
Regulation’ '1998'that prescribes the. nature of evidence
required by the State.in ‘support of the lodging of this
development:application.
for completing 023
The information in'(i) - (v) is mandatory if evidence is .
required: under, 022 (ii) or (iit) above: ‘
The official: stamp of.the: Department of Natural
Resources, Mines and Water is mandatory where the
application invotves any water or riverine quarry °
material under. the Water Act 2000, :
Section 3. 215A) allows the.resour
lime the
Assessment triggers
This checklist does got apply if the application requires
the completion of Parts A and B of the Form onty. It
must be completed for afl other applications,
: lo9 This: application i is accompanied by evidence: (tick aéplicabe box)
than involving
QO (i) of the allocation of, or entitlement to, the.resource ~ attach evidence'and go to Q23{vi)
C1 (ii). the chief executive of the department administering the. resource is satisfied. the
. development i is. consistent with: an allocation of, or entitlement to, the resource - go
to Q23
C1 (ili}.the chief executive:of the department administering: the resource is satisfied the
development application may proceed in: the absence of an: vallocation of, or
” entitlement'to, the resource - go t0 023
23. Evidence of the resource entillement:
(i) - Resource entitlement / authority details (vil) Official stamp of the department
a > — applicable). 2
(i) Name of SSescieoet _
iti) * Position of delegated ‘officer
iV}iSignaluré of delegated officer -
(v) ‘Date’
(vi) _ date of evidence a . ‘
24. Is the IDAS Assessment Checklist completed and attached to this application?
CO Yes
NO - the assessment manager may refuse to accept this application on the
grounds that the application has not been properly made
Plans / drawings / reports
An application should be accompanied by details to
support the proposal & enable the assessment
manager, referral agencies and any person viewing
the application during public scrutiny or public
notification to understand the scope of lhe proposal
and any potential impact.
25. Plans/drawings/reports accompanying this application:
Plan / Drawing / Report Number
PLEASE NOTE: The assessment manager may refuse to accept an application that, ai the time of lod
and any other relevant part of Forn1,
OFFICE USE ONLY (applicable to assessment manager's)
igement, fails to provide all applicable information required by Part A
DATE TRecennic asricen’s | ‘ BEFERENCE Tt [ 1
[F FEE (S) bbe | _RECEIVED _ | 23h lo7 | NAMEIS LS Getto | wumsenss | CTLupsz |
Notification of Engagement of Private Certifier (Optional format) Y
To. Council, | have been engaged as the private certifier for the building work referred to in this application.
Dale ofengagement: / { Accreditation Number: __. __._ __, Name:
Signature:
Page 5
INTEGRATED PLANNING ACT 1997
RO OTe durne veal (ol
Operational &/or building work
assessable against a local government’s planning scheme
Part E, Version 2.1, 18 June 2007
E
a1
., Completion ofall question on Part E is mandatory for all applications involving the assessment of operational work and/of. iuilditig work assessable .:
Nature ofthe works | ne
The ‘types of work that are aSsessable against
a planning scheme are determined by the
scheme for a paiticular focal a goverment and
will vary across the State.
To determine the types of work that are
assessable under a particular planning
schemie, contact the relevant local
govemment.
‘The information in Q2 Is necessary for
statistical and planning purposes. ..
jainst a local govermment's planning schenie (including detailed engineering plans and other Dléns, detailed enginesning plans for subdivisional Works and conceptual
"design lens forengineering & building work when the ‘application does, pot involve ‘asséssment ofa material change, of use of premises at the same time):
Mo i eation 8 seeking approval at fick one (i) or both applicable}
Build’
ing work assessable agaist a planning Scheme - provieé details ote ospects outing’
work (6.9. building height greater than 8.5m; building work on high Jandslip tisk area)"
(J Operational Work assessable against a : planning ‘scheme # ! provide | delails of the faluire of the \.
operational work (6,9. roadworks; landscaping; drainage works, stomnvate water infristrucure; sewerage
infrastructure; earthworks; clearing vegetation’ signage). *
2.” Is the application for operational Work involving the creation of new lots? 4 : Mar Sp a
- fn Dyes - = specly mbar ciew bso be red btn ‘
3. ee ve the constriction of a canal thatis ssi wn reconfiguring a lot?
0: YES eo oe ce
A development peimit authorises *
development to occur, while. a preliminary
approval |s a step In the approval process
and: ‘does ctauthorise se development to occur,
Portable. Long Service: ‘Leave levy a
- applicable)
Prior to is issuing a development pemit ior the
‘works, the assessment manager is required
by: Jaw to “sight an approved form, issued by
Qléave, which signifies thatthe PLSL levy
has been pald,
For further information refer to
hitp/Aww.gleave aid .qov.au
eee is for: (tick one (1) or both i epplicibile)
Preliminary approval provide details of the ype of work 69. roadwork, stormwater, water and Sewerage
. Infrastructure, ete
° Fifee0 onmes a ZEW IRENA IA HOTEL ST PW
Oo Development permit: rovrde detals of the ype of (6g. rondo, stomwater, water and se sewe fe
vinffastructure, ete . i a
[ I
5." ‘wet subsequent toa previous’ ‘development pert or. prelinary eporval
, NO oO YES - ~ provide details. of ail previous onprovae .
ge Dais approval lapses ar i
/ f
tf
‘6... Is payment of a Portable Long Service Leave, (Pist) levy erlebl to the ropa
(2) YES - complete a7
LAKio - 07,84 9d0 ot apply
7. Has the PLSL levy been paid?
es complete 8
O ~ the applicable tevy must be ped béfore a dovopen permit can be given for the works
8 Howmuchwaspaid? a Soe a,
9. Whats the receipt number of the payment? , “ ,
| _ ————
Page 6
INTEGRATED PLANNING ACT 1997 (DAS Assessment Checklist, Version 20, 2 April 2007
Form 1 Development Application idas
IDAS Assessment
Checklist
(Formerly the “Referrals Checklist’)
IMPORTANT NOTE FOR ALL APPLICANTS:
1. This checklist was formerly referred to as the “Referrats Checklist’. Some of the ‘Guides’ to using the IDAS Application Forms continue to refer to this document as the
“Referrals Checklist’. The name of this checklist was changed from 25 July 2005 to more accurately describe its function.
2. Under the IPA and IDAS framework, an application may require assessment by the local Council and/or certain Queenstand State entities (e.g. Environmental Protection
Agency, Dept. of Natural Resources and Water, Queensland Heritage Council etc.).
3. This checklist is provided to assist applicants to determine when an application requires assessment by a Queensland State entity and may also assist the applicant to
determine the assessment manager' for the application.
4. Therefore, the completion of alt questions in section 1 of this checklist is mandatory for all applications (other than those requiring the completion of Parts A & 8 only).
5. tis the responsibility of the applicant to accurately complete this checklist.
6. Section 2 is mandatory only if the proposed development is focated in any part of a wild river area declared under the Wild Rivers Act 2005.
7. Depending on the nature of the application, an applicable State entity may be either the assessment manager or an {DAS referral agency for the application.
8
The assessment manager for the application will rely on the information provided in this checklist (as well as any material lodged in support of the application) to identity
any applicable referral agencies for the application in the Acknowledgement Notice. The assessment manager will also rely on this information when identifying if the
application triggers referral coordination2.
9. To assist you in answering the following questions a series of guides are available free from the IPA website www. ipa.qid.gov.au. Guide 25 explains the role of the IDAS
Assessment Checklist in the IDAS application process, and its relationship to the Form 1 development application.
10. Any other parts of Form 1 that this checklist requires to be completed are available from the Council or the applicable State entity, or can be downloaded tree from
www. ipa.qid.gov.au.
11. Section 3 provides advice about the referrals that can be required for applications for building work assessable against the Building Regulation 2006.
SECTION 1 - STATE ASSESSMENT (completion mandatory)
Note: The following state assessment triggers apply to development other than for bultding work assessable against the Building Regulation 2008.
Environmentally relevant activity 1. The application involves: (tick applicable box/es)
For more information refer to Guide 4. C1 (i) an environmentally retevant activity (ERA) for which a code for environmental compliance
Unless you answered “none of the above" to Qt, has not been made - complete Part G of Form 1
the application requires assessment by tha —
administering authority?. oO (ii), a mobile or temporary ERA for which a code of environmental compliance has not been
If an entity, other than the administering made - complete Part G of Form 1
authority, is the assessment manager for the (iii) none of the above
application, the administering authority is a
concurrence agency for the application in relation
to this matter.
Note: An application invalving ERA 19 and/or 20
will also require completion of Part Kr of Form 1
for approval where an allocation under the Water,
Act 2000 is required.
Continued overleaf
PLEASE NOTE: The assessment manager may refuse to accept an application, which, at the time of lodgement, fails to provide the
completed IDAS Assessment Checklist (if applicable}.
OFFICE USE ONLY (applicable fo assessment manager)
DATE RECEIVED REFERENCE NUMBER/S
1 The assessment manager is responsible for assessing and deciding an IDAS application. The assessment manager for an application is prescribed in schedule BA of the IPA.
2 For additional information refer to Guide 6 ‘Does my application trigger the referral coordination process?’
3 The ‘administering authority’ may be either the Environmental Protection Agency, the relevant focal goverment {for a devolved ERA} or the Queenstand Department of Primary Industries and
Fisheries (for a delegated ERA).
Page 1
Page 7
INTEGRATED PLANNING ACT 1997
State-controlled road matters
For more information refer to Guide 3.
Unless you answered “none of the above" to Q2,
the application triggers referral to the Department
of Main Roads (DMR) as a referral agency.
in certain circumstances DMR will be an advice
agency, while in other circumstances DMR will
be a concurrence agency.
Schedule 2 of the IP Regulation will assist you to
determine where OMR is an advice or
concurrence agency for the application.
2.
IDAS Assessment Checklist, Version 20, 2 April 2007
The application involves: (tick applicable box/es)
C1 (i) development on land contiguous? to a State controlled road and for -
(J (a) material change of use assessable against the planning scheme;
LD (b) reconfiguring a fot unless -
e the total number of lots is not increased; and
« the total number of lots abutting the State-controlled road is not increased;
C1 (c) operational work (not associated with a material change of use assessable against the
planning scheme or reconfiguring a lot mentioned in (b) ebove)-
+ associated with access to a State-controlled road; or
¢ for filling or excavation; or
« involving the redirection or intensification of site stormwater from the land, through a
pipe with a cross-sectional area greater than 625 cm? that directs stormwater to a
State-controfled road.
{C1 (ii) development on tand not contiguous to a State-controlled road and -
(J (a) material change of use —
« assessable against the local government's planning scheme; and
« mentioned in schedule 5 of the iP Regulation and exceeding the thresholds set by
that schedule;
CO (b) reconfiguring a lot for a purpose mentioned in schedule 5 of the IP regulation
and exceeding the thresholds set by that schedule;
C1 (c) operational! work (not associated with a material change of use assessable against the
planning scheme or reconfiguring @ lot mentioned in (b) above}-
* assessable against the local government's planning scheme; and
* mentioned in schedule 5 of the !P Regulation and exceeding the thresholds set by
that schedule.
x (iii) none of the above
Clearing vegetation 3. The application involves: (tick applicable box/es)
For more information refer to Guide 12. (1 (i) material change of use -
tear ean ee eerie te (a) assessable against the planning scheme;
aaa o ut er (b) on alot containing -
tan agency other than NRW is the assessment * acategory 1, 2 or 3 area shown on a property map of assessable vegetation; or
manager for the application, NRW Is a ; « if there is no property map of assessable vegetation for the lot - remnant vegetation;
benaurrence agency fr tre application In relation (c)_ where the existing use of the land is a rural or environmental use; and
Ifyou licked 034) or (i), your application requires (d) where the size of the land is 2 hectares or larger - complete Part J of Form 1
teferral to NRW for assessment regardless of oO (ii) reconfiguring alot~
whether vegetation clearing is proposed or not. we
(a) on alot containing a category 1, 2 or 3 area shown on a property map of
assessable vegetation or, if there is no property map of assessable vegetation for
the lot, remnant vegetation;
(b) where the size of the lot before the reconfiguration is 2 hectares or larger;
(c) where 2 or more lots are created; and
(d) where the size of any {ot created is 25 hectares or smaller - complete Pert J of Form 1
O (ili) operational work -
{a) for the clearing of native vegetation where the vegetation clearing is made
assessable under Schedule 8 of the IPA; and
(b) not associated with a material change of use assessable against the planning
scheme mentioned in (i) or reconfiguring a lot mentioned in (ii) - complete Part J of
Form 4
M (iv) none of the above.
Strategic port land 4. The application involves:
For more information refer to Guide 11.
If you ticked (i) - the relevant Port Authority is the
assessment manager for the application.
If you ticked (ii) Queensland Transport is a
concurrence agency for the application.
C1 (i) development on strategic port land as defined in the Transport Infrastructure Act 1994 (TI
Act) - complete Part ! of Form 4
O (i) a material change of use that is inconsistent with the land use plan approved under the
TI Act for the strategic port land - complete Part { of Form 1
y (iii) none of the above
4 Land contiguous to a State-controlled road is defined in schedule 14 of the iP Regulation to mean land - if part of the land is within 100m of the State-controlted road; or that is part of a future State-
controlled road.
Page 2
Page 8
INTEGRATED PLANNING ACT 1997
Acid sulfate soils 5.
For more information refer to Guide 10.
Unless you answered "none of the above” to 05,
the application requires assessment by
Department of Natural Resources and Water
(RW).
[fan agency other than NRW is the assessment
manager for the application, NRW is an advice
agency for the application in relation to this
matter.
Major hazard facilities or possible 6.
major hazard facilities
For more information refer to Guide 17.
(fyou answered “YES” to Q6, the application
requires assessment by the Department of
Ememency Services (DES).
If an agency other than DES is the assessment
manager for the application, DES is a
concurrence agency for the application in
elation to this matter.
IDAS Assessment Checklist, Version 20, 2 April 2007
The application involves development on land situated in an identified’ local government area
and where the surface of the land is: (tick appficable box)
(1 (i) below 20m AHD® and the development will involve the excavation of 1000m3or more of
soil or sediment at or below 5m AHD, or
O (ii) at or below 5m AHD and the development will involve filling the site with 1000m? or more
of material
M (iii) none of the above
Does the application involve a material change of use for a major hazard facility or possible
major hazard facility as defined under the Dangerous Goods Safety Management Act 2001?
BNO
YES - complete Part L of Form 1
Water related development under the | 7.
Water Act 2000
For mare information about items (a) — (f), refer
to Guide 15. For more information about item
(g), refer to Guide 14 Does my application
involve assessment of a referable dam?
Unless you answered "none of the above" to Q7,
the application requires assessment by the
Department of Natural Resources and Water
{NRW).
If an agency other than NRW is the assessment
manager for the application, NRW is a
concurrence agency for the application in
elation to this matter.
The application involves:
C1 (i) operational work, for taking or interfering with water under the Water Act 2000, that is:
{lick applicable box/es)
(a) in awatercourse, lake or spring, (eg. a pump, gravity diversion, stream re-direction, weir or
dam) - complete Part K2, Ks, Ks, Ke, or Ko of Form 1 whichever is applicable,
CJ (b) for an artesian bore anywhere in the State, no matter what the use - complete Part
Ky of Form 1;
(1 (c) for a subartesian bore, in dectared subartesian area’, or in a certain area
Removal of quarry material from a 8.
watercourse
For more information refer to Guide 16.
(fyou answered "YES" to 8, the application
requires assessment by the Department of
Natural Resources and Water (NRW).
Ifan agency other than NRW is the assessment
manager for the application, NRW is a
concurrence agency for the application in
relation to this matter.
Note: Part G of Form 1 is required to be
completed as the activity of removing quarry
material from a watercourse is also an
Environmentally Relevant Activity (ERA).
covered by a water resource plan, for use for purposes other than stock and/or
domestic use - complete Part K; of Form 1;
and/or domestic purposes - complete Part K: of Form 1;
(1 (e) for taking overland flow water in certain areas covered by a water resource plan
{J (f)_ for interfering with overland flow water in a drainage and embankment area -
complete Part Kio of Form 1
of a referable dam by more than 10% - complete Part Ks of Form 1; or
® (ii) none of the above.
requiring an allocation notice under the Water Act 2000?
NO
(2 (@) fora subartesian bore, in certain declared subartesian areas, for use for stock
— complete Part Ks of Form 1;
(J (g) for constructing a referable dam? or works that will increase the storage capacity
Does the application involve development for the removal of quarry material from a watercourse®
(J YES - complete Parts Ky and G of Form 1
5. The identified ocal government areas are: Aurukun, Bowen, Brisbane, Broadsound, Bundaberg, Burdekin, Burke, Bumett, Caboolture, Caims, Calliope, Caloundra, Cardwell, Carpentaria, Cook,
Cooloola, Dounglas, Fitzroy, Gladstone, Gold Coast, Hervey Bay, Hinchinbrocke, tsis, Johnstone, Livingstone, Logan, Mackay, Maroochy, Maryborough, Mirium Vale, Mornington, Noosa, Pine Rivers,
Redaiiffe, Redland, Rockhampton, Sarina, Thuringowa, Tiaro, Torres, Townsville, Whitsunday.
Australian Height Datum (AHO).
Referable dam is defined under the Wafer Act 2000.
Watercourse is defined in sch 10 of the IPA.
COD
‘The declared ground water areas are listed in Guide 13 Development in a declared catchment area,
Page 3
Page 9
INTEGRATED PLANNING ACT 1997
Operational work that is tidal work or
work in coastal management district
For more information refer to Guide 18. For
more Information about prescribed tidal work in
local government tidal areas refer to Guide 24.
Uniess you answered “none of the above” to Q9,
the application requires assessment by the
Environmental Protection Agency (EPA).
If an agency other than EPA Is the assessment
manager for the application, EPA is a
concurrence agency for the application in
elation to this matter.
Local govemment is the assessment manager
for all prescribed tidal work.
DW
oii
Diiiy
Ww)
IDAS Assessment Checklist, Version 20, 2 Aprii 2007
9. The application involves operational work that is: ( tick the applicable boxes)
tidal work"? as defined under the Coastal Protection and Management Act 1995 (the
Coastal Act) that is not prescribed tidal work - complete Part M of Form 1; or
tidal work that is prescribed tidal work" other than in a canal'2 -compiete Part P of Form 1;
or
carried out within a coastal management district under the Coastal Act and for - complete
Part M of Form 1 if any box/es (a) to (i) below are licked.
(1 {a) constructing or installing works in a watercourse between MHWS and HAT (ie.
other than those works in tidal water) where the development has been determined not
to be assessable against the Water Act 2000 ;
constructing a canal intended to be connected to tidal waters;
constructing an artificial waterway;
reclaiming land under tidal water;
disposing of dredge spoil or other solid waste material in tidal water;
interfering with quarry material on State coastal land above high-water mark;
draining or allowing drainage or flow of water or other matter across State
coastal land above high-water mark;
temoving or interfering with coastal dunes on land, other than State coastal land,
that is in an erosion prone area and above high-water mark;
constructing a bank or bund wall to establish a ponded pasture on land, other
than State coastal land, above high-water mark; or
none of the above.
J b)
Oe
Od)
Oe)
Of
O@)
Ch)
Ov
Operational work below high water
mark
For more information refer to Guide 18. For
more information about prescribed tidal work in
local government tidal areas refer to Guide 24.
Unless you answered “none of the above" to
Q10, the application triggers referral to
Queensland Transport (QT) (Maritime Safety
Qld) as a concurrence agency.
Local goverment is the assessment manager
for ail prescribed dat work,
Miiv)
10, The application involves operational work that is: (tick the applicable box/es)
( (i) tidal work’ as defined under the Coastal Protection and Management Act 1995 (the
Coastal Act) that is not prescribed tidal work - complete Part M of Form 1; Or
C1 (ii) tidal work that is prescribed tidal work"4 - complete Part P of Form 1; OF
C1 (iii) carried out within a coastal management district’ under the Coastal Act and for -
Oe)
0 (b)
O(c)
disposing of dredge spoil or other solid waste material in tidal water - complete Part
M of Form 1;
reclaiming land under tidal water - complete Part M of Form 1; OF
constructing a canal, if the canal is associated with reconfiguring a lot - complete
Part M of Form 1;
none of the above.
Coastal management
For more information refer to Guide 18.
Unless you answered "none of the above" to
Q11, the application requires assessment by the
Environmental Protection Agency (EPA).
If an agency other than EPA is the assessment
manager for the application, EPA is a
concurrence agency for the application in
elation to this matter.
10 Tidal work is defined in sch 10 of the (PA.
Oi
Oi
Diy
Ow
$d)
11, The application involves: (tick the applicable box/es)
a material change of use assessable under a planning scheme involving operational
work carried out completely or partly in a coastal management district
a material change of use assessable under a planning scheme involving building
work, carried out completely or partly in a coastal management district that is -
« the construction of a new premises with a GFA'S of at least 1000m2
« the enlargement of the GFA of existing premises by more than 1000m?2
reconfiguring a lot assessable under schedule 8 of the IPA where the land is situated
completely or partly in a coastal management district
reconfiguring a lot'’ assessable under schedule 8 of the {PA and in connection with
the construction of a canal - complete Part M of Form 1
none of the above
41 Prescribed tidal work is defined in the Coastal Protection and Management Regulation 2003 and includes certain tidal works completely or partly within a local government tidal area.
12 Canal means canal as defined under the Coastal Protection and Management Act 1995
13 Tidal work is defined in sch 10 of the IPA.
14 Prescribed tidal work Is defined in the Coastal Protection and Management Regutation 2003 and includes certain tidal works completely or partly within a local government tidal area.
15 Coastal management district is defined in sch 10 of the IPA and means a coastal management district under the Coastal Protection and Management Act 1995, other than an area declared as a
coastal management district under section 47(2) of that Act
16 GFA is defined in sch 14 of the IPA to mean the gross floor area. For a definition of how to calculated GFA, go to the planning scheme against which the application is being assessed.
17 Under s117 of the Coastal Protection and Management Act 1995, an application for reconfiguration, where the reconfiguration is associated with the construction of an artificial waterway, must be
accompanied by the appfication for the operational works to construct the artificial waterway.
Page 4
Page 10
INTEGRATED PLANNING ACT 1997
Development within the limits of a
port
For mote information refer to Guide 18. For
information about prescribed tidal work refer to
Guide 24.
Ifyou answered "YES" to Q12, the application
triggers referral to the Port Authority.
The Port Authority is a concurrence agency if the
development is -
within 200m of a shipping channel or an entry
and exit shipping corridor for the part
within 1000m of a swing basin, a commercial
shipping wharf, a mooring, anchorage or spoil|
grounds;
within 1000m of a planned port facility
identified in a land use plan approved under
the Transport infrastructure Act 1994,
in all other situation the Port Authority is an
advice agency.
Marinas
For more Information refer to Guide 18, For
information about whether a marina is prescribed
tidal work refer to Guide 24. The locat
goverment is the assessment manager for all
prescribed tidal work.
\f you answered "YES" to Q13, the application
tiggers referral to Queensland Fire and Rescue
Service as an advice agency.
IDAS Assessment Checklist, Version 20, 2 April 2007
12, Does the application involve development below high water mark’ and within the limits of a port
under the Transport infrastructure Act 1994?
NO
(11 YES - complete Part M of Form 1, or Part P of Form 4 if the work Is prescribed tidal work
13. Does the application involve operational work that is tidal work for a marina‘? with more than 6
vessel berths?
[No
(DYES -comptete Part M of Form 1, or Part P of Form 1 if the tidal work is prescribed tidal work
Tidal works in strategic port land tidal
areas
For more information refer to Guide 18.
Unless you answered "NO" to 014, the relevant
Port Authority is the assessment manager for the
application and the Environmental Protection
Agency (EPA) and Queensland Transport (QT)
are concurrence agencies for the application.
Heritage
For further information refer to Guide 19.
\f you answered "YES" to Q15, the application
triggers referral to the land Hi
Council as concurrence agency for the
application,
Unless you answered “none of the above" to
Q15(b), the application involves referral to the
Environmental Protection Agency as an advice
agency for the application
Does the application involve tidal works within a strategic port land tidal area2°?
NO
YES - complete Part M of Form 1
15. Does the application involve development in a heritage registered place as defined under the
Queensland Heritage Act 1992?
0
YES - complete Part C of Form 1
15(b)The application involves: (tick applicable boxes)
{1 () a material change of use assessable against the planning scheme and the lot shares a
common boundary with a protected area or registered place under the Queensland
Heritage Act 1992;
(ii) reconfiguring a tot if the lot shares a common boundary with a protected area or
registered place under the Queensiand Heritage Act 1992;
none of the above.
vi (iii)
Declared catchment areas
For more information, including a list of the
declared catchment areas within Queensland,
refer to Guide 13.
Unless you answered “none of the above" to
Q16, the application requires assessment by the
Department of Natural Resources and Water
(NRW).
If an agency other than NRW is the assessment
manager for the application, NRW is a
concurrence agency for the application in
relation to this matter.
16. The application is in an area declared to be a catchment area under the Water Act 2000 and
involves: (tick the applicable box/es)
(1 (i) reconfiguring a fot if any lot resulting from the reconfiguration is less than 16 hectares;
C1) (ii) development assessable against the planning scheme involving the establishment or
expansion of a waste water disposal system, other than a disposal system for carrying
out an environmentally relevant activity under the Environmental Protection Act 1994;
none of the above
Q (il
18 High water mark is defined in the Coastal Protection and Management Act 1995 and means the ordinary high water mark at spring tide.
19 Marina is defined in the Transport Operations (Maritime Pollution) Regutalion 1995,
20 Strategic port Sand tidal areas are the areas generally 50 metres seaward of high water mark adjacent to strategic port land,
Page 5
Page 11
INTEGRATED PLANNING ACT 1997
IDAS Assessment Checklist, Version 20, 2 April 2007
Contaminated land 17. The application involves: (tick the applicable box/es)
Applications involving material change of use (A (i)_ recenfiguring a fot for which all of part of the premises are —
al hA dialed a tot may tigger iis (a) premises mentioned in the IPA, schedule 8, part 1, table 2-—
For more information refer to Guide 5. * item 5, including the exemption otherwise provided for by paragraph (d);
Unless you answered “none af the above" to « item 6, including the exemption otherwise provided for by paragraph (e); or
Q17, the apptication requires assessment by the « item 7, including the exemption otherwise provided for a mining activity or petroleum
Environmental Protection Agency (EPA). If an activity; or
agency other than EPA is the assessment ,
manager for the application, EPA will be a (b) in an area for which an area management advice has been given for unexploded
concurrence agency for the application in ordnance - complete Part N of Form 1
elation to this matter.
C1 (il) a materiat change of use —
(a) made assessable under the IPA, schedule 8, part 1, table 2, items 5 to 7; or
(b) assessable against the planning scheme and if all or part of the premises is in an area
for which an area management advice has been given for unexploded ordnance -
complete Part N of Form 1
A (iii) none of the above
Electricity infrastructure 18. The application involves: (tick the applicable box/es)
Fo more information refer to schedule ofthe IP (1 (i) reconfiguring a lot where any part of the lot is —
Ue yu answered ‘none of the above" to « subject to an easement in favour of a distribution entity or transmission entity under the
18, the application triggers referral to the Electricity Act 1994 and the easement is for a transmission grid or supply network under
lency to which the easement is granted in that Act; or
favour of as advice agency. « situated within 100m of a substation site;
( (ii) a material change of use, assessable against a planning scheme and not associated
with reconfiguring a lot if -
« any part of the premises is subject to an easement in favour of a distribution entity or
transmission entity under the Electricity Act 1994 and the easement is for a transmission
grid or supply network under that Act; and
¢ any structure or work that is the natural and ordinary consequence of the use is, or will be,
located wholly or partly in the easement;
OO (ii) a material change of use, assessable against a planning scheme and not associated
with reconfiguring a lot if any part of the premises is situated within 100m of a substation
site;
Ci (iv) operational work that is filling or excavation assessable against the planning scheme,
not associated with reconfiguring a lot, if -
« any part of the premises is subject to an easement in favour of a distribution entity or
transmission entity under the Electricity Act 1994 and the work is located wholly or partly in
the easement;
» the work is located wholly or partly within 10m of a substation site;
A {v) none of the above.
Land designated for community 19. Does the application involve development assessable against the planning scheme and on land
infrastructure
Applications involving development on land
designated for community infrastructure may
trigger this referral.
For more information refer to schedule 2 of the
IP Regulation.
If you answered “YES” to Q19, the application
requires assessment by the chief executive of
the department administering the Act authorising
the development for the designated purpose.
If an agency other than the designator is the
assessment manager for the application, the
designating agency will be a concurrence
agency for the application in relation to this
matter,
designated for community infrastructure?
{i) intended to be supplied by a public sector entity; and
(ii) on land not owned by or on behalf of the State; and
(iii) other than development —
(a) for the designated purpose; or
(b) carried out by, or on behalf of, the designator.
NO
Ol yes
Page 6
Page 12
INTEGRATED PLANNING ACT 1997
SEQ Regional Plan
For more information refer to schedule 2 of the
IP Regulation.
Refer to Chapter 2, part 5A and schedule 10 of
the Integrated Planning Act 1997, and schedule
2 of the Regulatory Provisions for retevant
definitions.
Uniess you answered "none af the above” to
Q20, the application requires assessment by the
Office of Urban Management (OUM).
Fisheries matters
For more information refer to schedule 2of the IP
Regulation.
Unless you answered “none of the above" to
Q21, the application requires assessment by the
Department of Primary Industries and Fisheries
{DPI&F).
Ifan agency other than OPI&F is the assessment
manager for the application, OPI&F is a
concurrence agency for the application in
relation to items (i) ~ (Iv) and an advice agency
in relation to item (v).
IDAS Assessment Checklist, Version 20, 2 April 2007
20. The application involves (tick applicable box/es) -
(1 (i) amaterial change of use of premises -
(a) in a Major Development Area in the Urban Footprint for -
OO (i) anurban activity -
(1 inan area included in a structure plan where the IPA, section 3.1.6
applies;
(11 inan area not included in a structure plan where -
« the IPA, section 3.1.6 applies to the application for the material change
of use; or
the premises exceeds 10,000m2; or
« the gross floor area (GFA) on the premises will exceed 10,000m2: or
« impact assessment is required under the relevant planning scheme
0 (ii) intensive animal husbandry, or
O (ii) residential development involving a rural residential purpose
(b) in the Regional Landscape and Rural Production Area for -
O (i) anurban activity and not specified in section 2.4(2); or
C1 (ii) residential development involving a rural residential purpose and not
specified in section 2.6(2)
(c) in the Rural Living Area for an urban activity and not specified in section 2.8(2);
(d) in the Investigation Area for -
CD (i) anurban activity and not specified in section 2.10(2);
© (ii) residential development involving a rural residential purpose and not
specified in section 2.12(2); or
C1 (ii) intensive animal husbandry
Osi) reconfiguring a lot-
On land in a Major Development Area in the Urban Footprint that is:
(a) not included in a structure plan; and
(b) not specified in section 3.1(2).
A (iii) none of the above
21. The application involves: (tick the applicable box/es}
CO (i) anassessable material change of use for aquaculture - complete Part O; of Form 1;
LO (li) assessable operational work that is the construction or raising of a waterway barrier -
comptete Part Os of Form 1;
Di
assessable operational work completely or partly within a declared fish habitat area.
complete Part Oz of Form 1;
0 (iw)
Ow)
plant - complete Part O2 of Form 1;
development assessable under the IPA, schedule 8, part 1, on land that adjoins a
declared fish habitat area;
none of the above.
assessable operational work that is the removal, destruction or damage of a marine
wi)
Page 7
Page 13
INTEGRATED PLANNING ACT 1997
Integration of land use and public
transport
For more information refer to Guide 23, schedule
8A of the IPA, & schedule 2 of the IP Regulation.
Unless you answered “none of the above”, the
application triggers referral to QT as a
concurrence agency.
IDAS Assessment Checklist, Version 20, 2 April 2007
22. The application involves: (tick the applicable box/es)—
(J (i) a material change of use assessable against the planning scheme for a purpose
mentioned in schedule 13C of the IP Regulation and exceeding the thresholds set by that
schedule.
C1 (i) reconfiguring a tot—
(J (a) onland that is completely or partly within a public transport corridor, and the
total number of lots increases;
(1 (b) on land that is completely or partly within a future public transport corridor or
an airport's public safety area;
O(c) _ onland that is within 400m of a public passenger transport facility or a future
public passenger transport facility, and the total site area is 5000m2 or greater,
[J (d) for a residential purpose within the 25 ANEF contour for an airport;
Cl(e) _ fora residential purpose resulting in 100 or more allotments.
LC (iii) operational work assessable against the planning scheme, but not associated with a
material change of use mentioned in (i) above or reconfiguring a lot mentioned in (ii)
above, on land that—
(1 (a) is completely or partly within a public transport corridor or a future public
transport corridor;
{1 {b) _ will resutt in work that encroaches into an airport's operational airspace.
[Xl (iv) none of the above.
Railway safety and efficiency 23. The application involves: (tick the applicable box/es)—
For more information refer to Guide 23, schedule i) a material change of use assessable against the planning scheme for a purpose
BA ofthe IPA & schedule 2 ofthe IP Rlesulaion OM mentioned in schedule 13D of the IP Regulation and encending the desholgs set by that
Unless you answered “none of the above”, the
application triggers referral to QT as a schedule.
conourrence agency. CL (ii) reconfiguring a tot—
C1 (a) on land that is completely or partly within a future public transport corridor,
future railway land or a railway tunnel easement;
(D (b) on land that is within 400m of a Citytrain passenger railway station or a future
Citytrain passenger railway station, and the total site area is 5000m2 or
greater;
CJ (c) on land that abuts rail corridor land, commercial corridor land or future railway
land, and the total number of lots increases;
(1 (d) — on tand that abuts rail corridor land, commercial corridor land or future railway
land and an easement abutting the corridor or future railway land is created;
C1 (e) on land that is completely or partly within 100m of, and abutting an approach
to, a railway level crossing, and the total number of lots increases;
C1 (f) for a residential purpose resulting in 100 or more allotments.
C1 (ili) operational work assessable against the planning scheme, but not associated with a
material change of use mentioned in (i) above or reconfiguring a lot mentioned in (ii)
above, involving extracting, excavating or filling greater than 50m3, on land that—
(a) _ is completely or partly within rai! corridor land or commercial corridor land, and
the work is not for rail transport infrastructure or other rail infrastructure;
(1 (b) is completely or partly within future railway land, or a railway tunnel easement;
{1 (c) abuts rail corridor land, commercial corridor land or future railway land, and
the work is within 25m of the railway boundary.
&X] (iv) none of the above.
Moonie to Brisbane pipeline 24. The application involves the easement for the construction or operation of the Moonie to
For more information refer to schedute 2of the IP
Regulation.
Unless you answered “none of the above”, the
application tiggers referral to the holder of
pipeline licence No 1 issued under the Pefrofeum
Act 1923, currently Santos QNT Pty Ltd, for
advice.
Brisbane strategic pipeline, and involves: (tick the applicable box/es)—
CO (i) a material change of use assessable against the planning scheme and not associated
with reconfiguring a lot, and any structure or work will be located wholly or partly in the
easement.
( (ii) reconfiguring a lot
C1 (ili) operational work assessable against the planning scheme, that is filling, excavation,
compaction, drilling, boring or piling not associated with a reconfiguring a lot, and the
work is located wholly or partly in the easement.
wv (iv) none of the above.
Page 8
Page 14
INTEGRATED PLANNING ACT 1997 Koala habitat area For more information, refer to Guide 26 and schedule 2 of the IP Regulation. Unless you answered "none of the above”, the application requires referral to the Environmental Protection Agency as 2 concurrence agency. Wild river area Far more information, refer to Guide 27 Ifyou answered YES to Q26, you must also complete section 2 of this checklist. This will enable you to determine if your application can proceed in a wild river area and which referral agency will assess your application against the Wild Rivers Code, or if the proposed development is “prohibited” in a wild river area. Nota: Development can be ‘prohibited’ in a wild river area because the application cannot be accepted by the assessment manager. Preliminary Approval Ifyou answered YES to Q27, the application triggers referral to the Department of Local IDAS Assessment Checklist, Version 20, 2 April 2007 25. The application involves: (tick the applicable box/es)— ( (i) a material change of use of premises in a koala conservation area or koala sustainability area made assessable under a planning scheme, that is not for a domestic activity and will result in — LJ (a) clearing of native vegetation over an area greater than 2500m?; (J (b) anew building and any reasonably associated structure with a total footprint greater than 1000m2; C1 (c) an extension to an existing building and any reasonably associated structure if the extension has a total footprint greater than 1000m2, Oo (d) extracting gravel, rock or sand from an area greater than 5000m2; (1 e) excavating or filling an area greater than 5000m?; (1 (f) additional traffic in a koala conservation area or koala sustainability area, between 6p.m. on a day and 6a.m. on the following day. (1 (ii) reconfiguring a Jot in a koala conservation area or koala sustainability area that will result in - (1 (a) an increased number of lots; [1 (b) clearing of native vegetation over an area greater than 2500m2. CL (ili) operational work in a koala conservation area or koala sustainability area made assessable under Schedule 8, Part 1, Table 4, items 1A to 1G (not associated with reconfiguring a lot mentioned in (ii) above) that will result in the clearing of native vegetation over an area greater than 2500m2. CO (iv) operational work in a koala conservation area or koala sustainability area made assessable under a planning scheme (not associated with a material change of use mentioned in (i) or reconfiguring a lot mentioned in (ii) above) that is not for a domestic activity and will result in - LJ (a) clearing of native vegetation over an area greater than 2500m?; (1 (b) extracting gravel, rock or sand from an area greater than 5000m?; O(c) excavating or filling an area greater than 5000m?. isi (v) none of the above. 26. Does the application involve development in a wild river area declared under the Wild Rivers Act 2005? Ave YES 27. Does the application involve a development for which preliminary approval is sought under Section 3.1.6 of the Integrated Planning Act 1997? Govemment, Planning, Sport and Recreation as A NO an advice agency. | YES Wetlands Comestic activity means the construction of use of a single residence on a lot and any reasonably associated building or structure. Examples of a building or structure that could be reasonably associated with a single residence include: caretaker's residence, granny Rat, duilding or structure used for a home business. Note: Wetland is defined in the Integrated Planning Regulation 1998. Unless you answered "none of the above” to Q26, the application involves referral to the Environmental Protection Agency as an advice agency for the application. 28. The application involves: (tick the applicable boxes) - (1 () — amateria! change of use, other than for a domestic activity, assessable against the planning scheme that is in or within 100m of a wetland; (ii) reconfiguring a lot - In or within 100m of a wetland that will result in CO (a) more than 10 lots being created; or LJ (b) lots less than 5 hectares; A (iii) none of the above Page 9
Page 15
INTEGRATED PLANNING ACT 1997 Conservation Estate Urban purposes is defined in the Integrated Planning Act 1997 as “purposes for which land Is used In citles or towns, including residential, Industrial, sporting, recreation and commercial purposes, but not including environmental, conservation, rural, natural or wildemess area Purposes”. Unless you answered ‘none of the above” to Q29, the application invatves referral to the Environmental Protection Agency as an advice agency for the application, IDAS Assessment Checklist, Version 20, 2 April 2007 29. The application involves: (tick the applicable box/es)— (1 (i) a material change of use for urban purposes that is in or within 100m of any of the following - CJ (a) a protected area, forest reserve, critical habitat or area of major interest under the Nature Conservation Act 1992;: ([] (b) a State forest or timber reserve under the Forestry Act 1959; C1 (c) amarine park under the Marine Parks Act 2004; (1) arecreation area under the Recreation Area Management Act 1988; C1 (e) a world heritage area listed under the World Heritage Convention; (1 (f)_ Brisbane forest park under the Brisbane Forest Park Act 1977. 0 (i) reconfiguring a lot if - (1 (@) any part of the lot is situated in, or within 100m of, any of the following — (1() aprotected area, forest reserve, critical habitat or area of major interest under the Nature Conservation Act 1992; C1 (ii) a State forest or timber reserve under the Forestry Act 1959; O (iii) amarine park under the Marine Parks Act 2004; oO (iv) arecreation area under the Recreation Area Management Act 1988; CI(v) _ aworld heritage area listed under the World Heritage Convention; Brisbane forest park under the Brisbane Forest Park Act 1977; and [1 (b) the reconfiguration involves more than 10 lots being created, or any lot tesulting from the reconfiguring is less than 5ha; A (iii) none of the above. Page 10
Page 16
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 20, 2 April 2007 SECTION 2 - ASSESSMENT IN A WILD RIVER AREA (completion ma Wild River Area It the responsibility of the applicant to determine if the development is proposed In a wild river area. Information about wild river areas including the geographical location and position of management areas in relation to properties, can be accessed by contacting the Department of Natural Resources and Water (NRW), accessing the department's website www.new.qid.gov.au or contacting the department by email on: wild [email protected] Note on Referrals Referrats for development in a wild river area (other than for agricultural activities and animal husbandry activities) are not changed from the existing referral arrangements. Notes on development assessable against the Wild Rivers Code For information regarding development in a wild river area, see the relevant wild river declaration and Guide 27, The relevant wild river declaration will provide Information regarding which types of development must be assessed against the Wild Rivers Code, and in some cases which types of development are exempt from witd river requirements. The notes on development assessable against the Wild Rivers Code in this section of the checklist provide some guidance however this may vary between wild river areas, The relevant declaration will provide the information applying to each wild river area. Applications for some new developments will not be accepted if the proposed development is in a high preservation area (HPA). Most applications for development activities which may be made including those in a preservation area (PA), must be assessed against and must comply with the Wild Rivers Code where indicated in a relevant wild river declaration. indatory if the proposed development is located in a wild river area) 1. Which wild river area is the development proposed in? The proposed development is to be located in: (tick the applicable box/es) (Ji) a high preservation area (HPA); oO ii) a preservation area (PA) ; (71 ili) a wild river floodplain management area (FMA); O iv) a wild river nominated waterway; (-] v) a designated urban area (DUA). Environmentally relevant activities (ERAs) in a designated urban area Ifyou answered YES, your application for an ERA Is exempt from any wild river requirements and provided there are no other aspects of this development that require assessment against wild rivers, you do not need to complete the femaining questions in Section 2. if you answered NO to Q2, please complete the remaining questions in Section 2. 2. Does the proposed development only involve any of the following environmentally relevant activities (ERAs) in a designated urban area (as mapped in the relevant wild river declaration)? i) An ERA 28 or ERA 14; or ii) A level 2 ERA except ERA 1, 2, 3, 4, 20, 22 or 59. i NO oO YES (ensure you have completed Part G of Form 1) Clearing native vegetation IFYES, there are a limited number of purposes for which an application to clear native vegetation may be accepted in a HPA. See. Gulde 27 for a list of relevant purposes for which an application may be made in a HPA. \FYES and you ticked Q4 box i) the application may be made and is assessable against the Wild Rivers Code. If YES and you ticked Q4 box ii) the application will not be accepted. Note: If clearing native vegetation is ina PA, there are no wild river requirements and provided there are no other aspects of this development where wild river requirements apply, do not complete the remaining questions in Section 2, 3. Is the application operational work for clearing native vegetation in a HPA? NO Oo YES (ensure you have completed Part J of Form 1) 4. If YES, is the clearing? OQ i) clearing regrowth (as defined in the Vegetation Management Act 1999) in a registered area of agriculture in a HPA (see Guide 27); or (] ii) in a HPA outside a registered area of agriculture? Page 11
Page 17
INTEGRATED PLANNING ACT 1997
Works in tidal areas, coasta!
management districts and fish habitat
areas
{fyou answered YES to QS, and ticked any
boxes in Q6), your application is required to be
assessed against and must comply with the Wild
Rivers Code.
\f you answered YES to QS and ticked box j) in
Q6, your application is required to be referred to
the EPA.
Note: if specified works are proposed in a local
goverment area, it is prescribed tidal work — the
relevant local government will be the
assessment manager with the EPA as a
concurrence agency
If you answered YES to Q5, and ticked box ti) or
iit} in Q6, your application requires referral to
DPIF.
ifyou answered NO to Q5 and ticked box i) in
Q6, the application will not be accepted.
If you answered NO to Q5, ticked box ii) in Q6
and the development is necessary to install
authorised works or infrastructure where a
development permit is not required, or if a
required permit is held, the application must be
assessed against and must comply with the Wild
Rivers Code. Appiications for purposes other
than specified works or as described above will
not be accepted.
Ifyou answered NO at Q5 and ticked box iii) in
Q6, the application may be made If the works are
ina PA. These applications must be assessed
against and must comply with the Wild Rivers
Coda. The application will not be accepted if the
development is proposed to be located in a HPA.
For more information about specified works refer
to Guide 27
Residential, commercial or industrial
development
(fyou answered YES to Q7, your application is
not subject to wild river requirements. Provided
there are no other aspects of this development
that require assessment against the relevant wild! §
river declaration or Wild Rivers Code, you do not
need to complete the remaining questions in
Section 2.
If you answered NO to Q7 and ticked either box
i) cr ii) in Q8, the assessing agency is the
relevant local government. The application must
be assessed against and must comply with the
Wild Rivers Code.
5.
IDAS Assessment Checklist, Version 20, 2 April 2007
Is the development for specified works? (see definition in the Wild Rivers Act 2005 and Guide 27-
Development in a wild river area)
A NO Clyes
The application is for one or more of the following:
[7] i) Operational works that is tidal works or works in a coastal management district (ensure you
have completed Part M and/or Part P of Form 1); OF
oO ii) Operational works for the removal, destruction or damage of marine plants (ensure you have
completed Part O2 of Form 1); OF
oO iti) Building or operational works in a fish habitat area (ensure you have completed Part O2 of Form 1).
{s the application for residential, commercial or industrial development in a designated urban
area?
ClyYes
(fl No
If NO, does the application for residential, commercial or industrial development involve:
(i) a material change of use made assessable in a local government planning scheme
(ensure you have completed Part D of Form 1); or
oO ii) operational works associated with reconfiguring a lot (ensure you have completed Part F
of Form 1).
Animal husbandry activities
Ifyou answered YES to Q9 your application
requires assessment against and must comply
with the Wild Rivers Code.
The assessing agency is NRW.
Note: Apptications for animal husbandry
activities will not be accepted if proposed in a
HPA. For more details and a definition of animat
husbandry activities see the Wild Rivers Act
2005 and refer to Guide 27.
Does the application involve a material change of use for animal husbandry activities (as defined
under the Wild Rivers Act 2005) in a PA?
J No
oO YES (ensure you have completed Part R of Form 1)
Agricultural activities
Ifyou answered YES to Q10, your application
requires assessment against and must comply
with the Wild Rivers Code.
The assessing agency is NRW.
Note: Applications for agricultural activities wilt
not be accepted if proposed in a HPA. For more
details and a definition of agricultural activities
see the Wild Rivers Act 2005 and refer to Guide
27.
The production of fodder in a PA, and pasture
improvement using low impact soil disturbance
techniques Is not an agricultural activity as
defined under the Wild Rivers Act 2005. For
more information see Guide 27.
10.
11,
Does the application involve agricultural activities (as defined under the Wild Rivers Act 2005) in
a PA?
Sno
If YES is the application for:
(1 i) a material change of use; or
Q ii) operational works.
(21 YES (ensure you have completed Part Q of Form 1)
Page 12
Page 18
INTEGRATED PLANNING ACT 1997 Works that take overland flow water The relevant wild river declaration will state works that take overland flow water are either self assessable or assessable, or are exempt from wild river requirements. (f you ticked Q13 i), your application must be assessed by NRW against the Wild Rivers Code and must comply with the code. If you ticked Q13 ii) an application is not required to be made however the works must comply with tha relevant self-assessable section of the Witd Rivers Code, otherwise the works become assessable development for which an application is required and must be assessed by NRW against the relevant part of the Wild Rivers Code and must comply with the code. If you ticked Q13 iii) your application is not subject to wild river requirements. Applications for development that is other than that stated to be assessable, self-assessable or exempt will not be accepted, 12. 13. IDAS Assessment Checklist, Version 20, 2 April 2007 Does the application involve works that take overland flow water in a HPA or an FMA? NO (21 YES (ensure you have completed Part Ks of Fonn 1) If YES, is the application for works stated in the relevant wild river declaration to be? (J i) assessable works J ii) self-assessable works LD) iti) exempt works Works that interfere with overland flow water The relevant wild river declaration will state works that interfere with overland flow water that are either self assessable, assessable or exempt from wild river requirements. If you ticked Q15 i), your application must be assessed by NRW against the Wild Rivers Code and must comply with the code, \f you ticked Q15 ii) an application is not required to be made however the works must comply with the relevant self-assessable section of the Wild Rivers Code, otherwise the works become assessable development for which an application is required and must be assessed by NRW against the relevant part of the Wild Rivers Code and must comply with the code. If you ticked Q15 iii) your application is not subject to wild river requirements, Applications for development that is other than that stated to be assessable, self-assessable or exempt will nat be accepted. 14. an the application involve works that interfere with overland flow water in a FMA? NO Oo YES (ensure you have completed Part Kio of Form 1) \f YES, is the application for works stated in the relevant wild rivers declaration to be? (1 i) assessable works (ii) self-assessable works (J iii) exempt works Waterway barrier works Applications for building or ralsing waterway barrier works in a HPA will nat be accepted. Ifyou answered YES to Q16, your application must be assessed by DPIF against the Wild Rivers Code and must comply with the code. Aquaculture (non ERA) Applications for aquaculture in a HPA will not be accepted, \fyou answered YES to Q17, your application must be assessed by DPIF against the Witd Rivers Code and must comply with the code. 16. Does the application involve building or raising waterway barrier works in a PA? BS NO oO YES (ensure you have completed Part O3 of Form 1) Does the application involve aquaculture in a PA? RfINo (1 YES (ensure you have completed Part O: of Form 1) Works that interfere with water in a watercourse Note: If the development is proposed in a HPA, applications for all works that interfere with water in a watercourse (including dams or weirs, stream realignment or stream diversion) will not be accepted. tn a PA, apptications for instream dams and weirs may be accepted in nominated waterways. If you ticked box if) in Q19, your application will not be accepted. Note: Operational works outside a HPA or nominated waterway ara not subject to wild river requirements. More information and tocations of nominated waterways is available by contact NRW, accessing the department's website wwww.nnw.ald.gov.au or contacting the department by email on: [email protected] the application involve operational works that interfere with water in a watercourse that is in nominated waterway in a PA? vo CJ YES (ensure you have completed the relevant Part K of Form 1) If YES, O i) The application is for an instream dam or weir; or oO ii) The application is for operational works that interfere with water in a watercourse, and is for development other than a dam or weir. Page 13
Page 19
INTEGRATED PLANNING ACT 1997 Environmentally relevant activities Most appfications for an ERA In a HPA will not be accepted. Appfications which may be made require referral to the EPA. The assessment of some ERAs is assessed by NRW, others have been devolved to DPIF, NRW or delegated local government (see EPA website for more information on devolved ERAs) If you answered NO to Q20 you do not need to complete Qs 21-24. Ifyou answered YES to Q20 and the development is in a PA, your application must be assessed by the administering authority?! against the Wild Rivers Code and must comply with the code, unless the proposal is for development where an application will not be accepted, of is exempt from wild river requirements (see Q2}. You will be able to determine if an application will not be accepted for the development by answering Q21 ~ Q24. if you answered NO to Q21, you do not need to complete Q22. If you answered YES to Q21 you are required to complete Q22. ifyou anawered NO to Q22, the application will not be accepted. If you answered YES to Q22, the application must be assessed by NRW against the Wild Rivers Code and must comply with the code, Ifyou answered NO to Q23 and the development Is proposed in the HPA the application will not be accepted. If you answered YES to Q23, the application must be assessed by the EPA or NRW (as prescribed in schedule 8A of the IPA) against the Wild Rivers Code and must comply with the code. Ifyou answered YES to Q24 the application will not be accepted. If you answered NO to Q24, your application must be assessed by NRW against the Wild Rivers Code and must comply with the code. Exempt ERAs in a designated urban area if the development is proposed In a designated urban area there may be no wild river fequirements. See Section 2 Q2. Nate: All applications that can be accepted must be assessed against and must comply with the Wild Rivers Code (other than exempt ERAs in a designated urban area). 20. 21. 22. 23. 24, IDAS Assessment Checklist, Version 20, 2 April 2007 Does the application involve an ERA? (Ano ts the application for an ERA 20 instream? (11 YES (ensure you have completed Part G of Form!) 9 NO LC yYes ls a quarry allocation notice held for the proposed ERA 20 instream? X NO ClYes Does the application involve any of the following in a HPA? i) a level 2 ERA 11, (and is for specified works or a residential complex) ii) an ERA 19 (dredging) iii) Low impact ERA 20 (out of stream) for specified works or a residential complex (as defined in the Wild Rivers Act 2005, and Environmental Protection Act 1994) iv) an ERA 22 (out of stream) [Ano Cl yYes Is the proposed development for ERA 20 (out of stream) and; — inaFMA; and — not low impact; and — not for a residential complex in the area, or for specified works. Fino Cyes Documentation ifyou answered NO to Q25, your application may be subject to an information request and Processing of the application may be delayed. 25, Has documentation been included with the application describing how the applicant proposes to comply with the mandatory requirements, required outcomes, and/ or performance requirements as set out in the relevant part/s of the Wild Rivers Code? LJ No CD Yes 2 The administering authority may be either the EPA, or if devolved or delegated, the local government, DPIF or NRW. Page 14
Page 20
t ~. SITE PLAN
i Ocseicament approved for: Building Works, Subject to
cemaliarice with Building Agt 1975 & Standard Building
Regulations 1993.
By COASTAL QUILDING CERTIFICATIONS P/L.
PERMIT 9.9 9 3g DATE 2.8 JUN 71007
Lot 3 NUMEE
t
§ RP 120234 {Approved by: MICHAEL BOWCOCK
' @ 202u0 dr in Poisons No: A23659° +e
(lam as 1 .
ash Old CERTIFICATIONS PAL Douf
3 y DATE 2 8 JUN 206? Proposext
@ en
het BOW!SCEK (cavage
a 74898 ees
Sout
Lake (Coceo: BAH [< OAD.
Note! The Site Plan above is not necessarily drawn to scale refer to registered plan for exact property dimensions.
SUPERIOR GARAGES CALOUNDRA PROPOSED: Panelform Garage Beir Tuyen ds sun, 2007
35 PRODUCTION AVENUE FOR: Jason Pistilli DIGGING
WARANA 4575. SITE ADDRESS: Lor: RP: Unknown
PHONE: (07) 54377022 19 Lake Cooroibah Road OBSTRUCTIONS
FAX: (07) $437 6722 Tewantin STORMWATER
: Connected Sy Client At A Later Date
. HOME : 0412103963 WORK: SITE CLEANUP
j(c) C
(c} Copyright 2007 APPROVAL BY: Private Certification Erector To Remove Rubbish (extra Charaedh
(These plans may not be reproduced in part or whole
without the expressed written consent of DANE
beepers
JOB NUMBER 16197
AUTHORITY:
s
Page 21
ee
END ELEVATION
BUILDING PLAN
PERSPECTIVE VIEW
j Ceveiopmént approved for: BulGing WOFRS. SUBpECT TT
com ai with Building Aci 1975 & Standard Building
Regulations 1993. .
{ By COASTAL BUILDING CERTIFICATIONS P/L
+ 27239 BATE 28 JUN 2007
NUMBER
—_—_Abnraditatingyy Nora 25659 .
jPERMAT
3000 ——»
on”
Rook Fat ——ae
~~ oat Fal
902q
ml
PrBoor
FLOOR PLAN
Note! The Plan above is not necessarily drawn to scale refer to production drawings for exact construction details.
NOTES: Foundations and slab:
All topsoil containing organic material together with any
loose foundation material shall be removed from the
building pad area
Slab Constructed First
Constructed by Company
Site levelled by Company (Extra’s charge to Customer)
Bocat hire and any fill required ( extra charge )
Piers through any fill payable by Customer
Site is accessable by large concrete truck
Building description:
Wir Oat 2 aM ene. eran en
Anchorage: Slab Fix
Roof Type : Nu Wave Pitch: N/A/
Slab size 9.02 x 6.08 x 2.7/
Roof Material: Zincalume Custom Orb
Wall Material: Ironstone Multiclad
Gutters & Cap: Zincalume Hi Front Quad
Main Doors: ‘Ox
1x 2100 x 2400 Sliding Glass door
1x 2050 x 770 wide
Personal Doors:
tronstone
Windows x79 ee Sina itt
Deve P fOr. Build oot
2 a
Regulations 1693.
oh COASTAL BUILDING CERTIFICATIONS P/L
Services: Power : Yes
ermensy 23g CATE 28 JUN 2007
approved by: MICHAEL BOWGGCK
' Accreditations No: A 23689
3
Water : Yes
SUPERIOR GARAGES CALOUNDRA PROPOSED:
35 PRODUCTION AVENUE
WARANA 4575
PHONE: (07) 5437 7022
FAX: (07) $437 6722
(c) Copyright 2007
These plans may not be reproduced in part or whole
without the expressed written consent of DANE
Tewantin
AUTHORITY:
FOR: Jason Pistilli
SITE ADORESS: LOT:
19 Lake Cooroibah Road
HOME : 0412103963 WORK:
APPROVAL BY: Private Certification
OATE :
15, Jun, 2007
REPRESENTATIVE :
Blair Turner
DIGGING
Unknown
OBSTRUCTIONS
Unknown
STORMWATER
Connected By Client At A Later Date
SITE CLEANUP
Erector To Remave Rubbish (extra Charged)
JOB NUMBER 16197
Panelform Garage
RP:
BEERTING
Page 22
xm 7 LAND USE SECTION FEES
aw MENLO. :
RECEIPT TYPE
SALE OF DOCUMENTS
Superseded Planning Scheme Documentation . 520
Copy of Permit/Approval Letter 110
The Noosa Plan Documentation 111
APPLICATION FEES
Material Change of Use - Code/Impact
Consistent §2T
Inconsistent 521
- Assessment under Superseded Planning Scheme 521
Modification to a Development Permit : 521
Extension of a Currency Period : 521
Operational Works - Landscaping 521
@ ig Work assessable against the Planning Scheme eso 521
PRE LODGEMENT REVIEW
Half Hour 522
One Hour §22
ADVERTISING
Purchase Advertised Applications §23
JETTIES
Jetty Application Fee 524
Jetty Bond 51
: (Category 4)
BONDS
Performance Bond : 51
(Category 9)
SIGNS
Registration Fee , ; 222
seu FEE .
Search of Land Use Section file 112
Liquor Licensing Request 113
TOTAL. $ 650
NAME: VE Postctn.: .
ADDRESS: ef- Averert Rocco t&
{? fx Te BIQSCI AK SSL
FILE NO: o7f weS2. DATE: 2-3 /AJo4
RECEIPT NO: ! 403 36 OQ Signature of TP Officer: (3 Dreeia
AUTHORITY NO: WA
17/[2007/1952/)
Page 23
CALCULATION OF FEES APPLICATION FEE TOTAL FEES MCU - CODE ASSESSMENT Details of Development Consistent 1.0 Inconsistent 3.0 FEE CALCULATION MCU - IMPACT ASSESSMENT Details of Development Consistent 1.0 Inconsistent 3.0 FEE CALCULATION OPERATIONAL WORKS Details of Development FEE CALCULATION TOTAL FEES