Skip to the record
Beware of cheap imitations.

Original source · versioned page text

2020-07-16-sm-agenda-item-1-attachment-5-final-noosa-plan-2020-part-8-10-schedules-appendix

of 389

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (19.9 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
  Column 1            Column 2
  Activity group      Uses
  Service catchment   Service catchment means an area serviced by an infrastructure network.

  Setback             setback, for a building or structure, means the shortest distance, measured horizontally,
                      between the outermost projection of the building or structure to the vertical projection of the
                      boundary of the lot where the building or structure is.

  Site                site, of development, means the land that the development is to be carried out on.

                      Examples—
                       1. If development is to be carried out on part of a lot, the site of the development is that
                          part of the lot.
                       2. If development is to be carried out on part of 1 lot and part of an adjoining lot, the site of
                          the development is both of those parts.

  Site cover          site cover of development, means the portion of the site, expressed as a percentage, that
                      will be covered by a building or structure, measured to its outermost projection, after the
                      development is carried out, other than a building or structure, or part of a building or
                      structure, that is—
                      (a)    in a landscaped or open space area, including, for example a gazebo or shade
                             structure or;
                      (b)    a basement that is completely below ground level and used for car parking; or
                      (c)    the eaves of a building; or
                      (d)    a sun shade.

  Slope               slope means:­
                      (a)    for the purpose of reconfiguring a lot:­
                             (i)    where the proposed lot is contained wholly within a single slope category
                                    shown on a slope analysis, the slope of that category; or
                             (ii)   where a proposed lot is contained within more than one slope category shown
                                    on a slope­analysis, the predominant slope of the use area, as follows:­
                                    (A)   where the house site area or use area is contained within one slope
                                          category shown on a slope analysis, the slope of that category; or
                                    (B)   where the house site area or use area is contained within more than one
                                          slope category shown on a slope analysis, the slope is the average of all
                                          predominant slopes of the house site area or use area.

                      (b)    For the purposes of building works or material change of use, the slope of the building
                             footprint or use area is that determined as follows—
                             (i)    where the building footprint or use area has one predominant slope, that slope;
                             (ii)   where the building footprint or use area has more than one predominant slope,
                                    the average of all predominant slopes, provided that—
                                    (A)   the slope shall be determined to the nearest whole number; and
                                    (B)   where there is any question about the determination of slope, the slope
                                          shall be as determined by the Assessment Manager.

  Slope­analysis      slope­analysis means, for the purpose of reconfiguring a lot, a diagram prepared by a
                      cadastral surveyor indicating the slope of the site based on one metre contour intervals
                      using the following slope categories—
                          0­10% slope
                          >10­15% slope
                          >15­20% slope
                          >20­25% slope
                          >25­33% slope, etc

  Sloping sites       sloping sites means sites or parts of sites that exceed a gradient of 1 in 5 or 20% and


NOOSA PLAN 2020                                                                                               Page 36 of 39
Log in to download the original file

2020-07-16-sm-agenda-item-1-attachment-5-final-noosa-plan-2020-part-8-10-schedules-appendix.pdf · 19.9 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.