Attachment 1 - Stormwater Management Plan

of 44

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                    2. 3. P R O P O S E D D E V E L O P M E N T D R A I N A G E P A T T E R N

                        2.3.1 Stormwater Concept

            Under existing conditions, the stormwater is discharged from the property as overland
            surface flows towards Lake Doonella to the south of the sites. It is proposed that this will
            remain the lawful point of discharge for the proposed development with the design
            required to demonstrate no worsening of the peak discharges for the design storms for the
            proposed development compared to the existing state.

            Roof run-off for each unit will be collected and flow via downpipes into a 3kL slim-line
            rainwater tank. The tanks will be plumbed for internal reuse in toilets and laundry areas, with
            1.5kL of the tank allocated for reuse, and the remaining 1.5kL per tank dedicated to
            attenuating site run-off to existing conditions. To minimise pollutants entering the tank, first
            flush diverters will be installed to divert the initial capture of roof water to irrigation of the
            vegetated areas on site.

            The driveway run-off will be collected via grated trench drains that will filter through Ocean
            Protect Ocean Guard litter basket (or approved equivalent) to provide primary treatment of
            gross pollutants and larger particulates from the run-off.

            Run-off from the upstream footpath catchments will be intercepted at the driveway access
            to the site with a grated trench drain to control its flow through the site within the internal
            drainage network.

            Run-off from the rainwater tank overflows, driveway and upstream footpath areas will be
            discharged overland through turfed buffer zone providing for further treatment and
            reduction of flow rates to run-off before it leaves the site.

            The roof and allotment drainage system for the proposed site shall be designed to comply
            with:

                    1. Noosa Shire Council Planning Scheme Policy (PSP) - Engineering Design Standards
                       – Roads, drainage and earthworks;

                    2. The Queensland Urban Drainage Manual (QUDM); and

                    3. AS/NZS 3500.3:2015 - Plumbing and Drainage Part 3: Stormwater Drainage.



                        2.3.2 Stormwater Catchments

            A schematic layout plan of the proposed development and its drainage catchments as
            described in the previous sections is shown below in Figure 2.3 – Proposed Catchments
            Plan.




                                                                                                                   Page 4 of 14
P +61 7 5211 1003              A 37 Mary St, Noosaville Qld 4566            E [email protected]   recorconsulting.com
Log in to download the original file

Attachment 1 - Stormwater Management Plan.pdf · 5.2 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.