Capital Works Schedule
As at: 31-May-2014
Forward design for bridge rehab program 10,000 50,000 5,045 10.09%
Noosa Parade Munna Point Bridge - Investigations and interim 250,000 250,000 29,352 11.74%
Total Bridges 260,000 300,000 34,397 11.47%
David Low Way, Beach Access 49 refurbishment 45,000 55,000 48,231 87.69%
Gympie Terrace and William Street Revetment wall and pathway 50,000 50,000 9,121 18.24%
Munna Point Holiday Park Bank Protection - Design 50,000 15,797 19,530 123.63%
Noosa Dog Beach SEMP Coastal monitoring 20,000 20,000 3,390 16.95%
Noosa River Mouth Groyne amd Rock Wall - Rehab 100,000 125,000 120,373 96.30%
Noosa Waters revetment walls - Stage 2a 1,300,000 1,300,000 884,979 68.08%
Total Coastal Canals and Waterways 1,565,000 1,565,797 1,085,623 69.33%
Peregian Surf Club Public Amenities - Planning & Design 15,000 15,000 202 1.35%
Total Community Facilities 15,000 15,000 202 1.35%
Purchase of Biodiversity Land 0 57,700 9,887 17.14%
Total Environmental Assets, Bushland, Tracks and Trails 0 57,700 9,887 17.14%
Noosa Nth Shore Holiday Park - Upgrade Septic treatment 90,000 49,500 37,813 76.39%
Replace Mains Power Supply Pole Noosa River CP 0 7,500 4,600 61.33%
Total Holiday Parks 90,000 57,000 42,413 74.41%
IT Major Projects 1,600,000 2,300,000 2,098,464 91.24%
Total Information Technology 1,600,000 2,300,000 2,098,464 91.24%
Cooroy Skate Park Minor Renewal 34,000 44,000 4,404 10.01%
Gympie Terrace Park Furniture Renewal program 50,000 50,000 30,886 61.77%
Joe Bazzo Park (Pomona Community House Park) BBQ Relocation 12,000 0 0 0.00%
Noosa Lions Pk - Rehab Shower Facilities 30,000 21,000 4,990 23.76%
Peregian Beach Park Plan - Finalise upgrade and removal of s 30,000 30,000 25,166 83.89%
Total Parks & Playgrounds 156,000 145,000 65,446 45.14%
Cooran State School - Charles Street Pathway improvements 30,000 60,000 60,242 100.40%
Pomona State School Station Street Pathway improvements 100,000 50,000 3,116 6.23%
Weyba Creek Boarwalk Rehab Stage 1 20,000 20,000 417 2.09%
Gibson Road (Eumindi Noosa Rd to Thomas St) - On road cycle 440,000 440,000 7,129 1.62%
Sunshine Beach State School Safety Improvements2 90,000 90,000 2,020 2.24%
Edwards Street Sunshine Beach Pathway Betterment 0 21,500 0 0.00%
Total Pathways & Enabling Facilities 680,000 681,500 72,925 10.70%
Noosa Junction Mini Bus Shelter - Panels for weather protect 25,000 25,000 24,622 98.49%
Noosa Parade Transit Hub-Stage 1 300,000 5,000 1,322 26.44%
Bus Shelter, Sunshine Beach Rd, Noosa Junction 0 5,000 4,993 99.87%
Total Public Transport Infrastructure 325,000 35,000 30,938 88.39%
Annual Sealed Road Renewal & Rehabilitation Program 500,000 500,000 47,409 9.48%
Sealed Road Pavement surveys and Investigations 60,000 60,000 1,321 2.20%
Total Sealed Roads Network 560,000 560,000 48,730 8.70%
Page 99 of 112See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.