MCU14/0056 Information Response Cover Letter
Attachments
(Attachment A) Revised Proposal Plans prepared by Verve
(Attachment B) Economic impact response prepared by Foresight Partners Pty/Ltd dated December, 2014
(Attachment C) Revision to Civil Engineering Report (Engineering Report and Stormwater Management
Plan), prepared by vT Consulting Engineers and inclusive of response from Seq water
(Attachment D) Stormwater Quantity Management Plan prepared by Storm Water Consulting Pty Ltd
(Attachment E) Earthworks Plan prepared by vT Consulting Engineers
(Attachment F) Traffic Addendum prepared by PTT
(Attachment G) Ecology addendum report Prepared by Saunders Havill Group
(Attachment H) Acoustic report prepared by MRG Environmental