                      Electricity and Telecommunication Services
               27.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               28.    Certification must be submitted to Council from all relevant service providers which certifies
                      that the development has met the requirements of this Decision Notice and all applicable
                      legislation at the time of construction.
                      Earthworks and Retaining Walls
               29.    All earthworks and associated batters/anchors must be contained entirely within the subject
                      site unless written permission from the respective landowner(s) is provided to Council. All
                      earthworks must be undertaken in accordance with the provisions of Australian Standard
                      AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
                      Damage to Services and Assets
               30.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               31.    The annotated louvres of the vergolas shown on the Approved Plans, are to be fixed and
                      remain open.
               32.    Privacy screening to the external circular staircase must be always maintained.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      Building and Construction Industry (Portable Long Service Leave) Levy
               1.     The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid. QLeave contact: 1800 803 481 (free call) or (07) 3212 6855.
                      Co-ordination of Operational Works Assessment
               2.     Additional application fees apply to Operational Work applications where the different
                      aspects of the works are lodged separately. Significant savings in application fees will result
                      if all works are lodged in a single application.
                      Preparation of a Preliminary Construction Management Plan
               3.     A preliminary Construction Management Plan must be submitted with the Operational Works
                      application and must address the following:
                      a.      traffic management during all aspects of the construction phase including:
                              i.       a Traffic Management Control Plan in accordance with the Manual of Uniform
                                       Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
                                       control measures prior to construction
                              i.       maintenance of safe pedestrian access for the areas affected by the works during
                                       and after daily construction has ceased


                                                                                                          Page 5 of 8
Document Set ID: 22787295
Version: 4, Version Date: 31/01/2024
Log in to download the original file

Decision Notice - Minor Change - MCU17 0559 04 [As Published].pdf · 162 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.