08/0194 - Operational Works - Transport Type 5 - Domestic Marine [As Published] · 142008.194
iN renee Checklist - Applications Involving Land
Development & Land Use Sections
{DAS APPLICATION
This checklist should be used for any IDAS application. Please check each of the following items before accepting an
application at the counter.
4. APPLICATION FORMS ~ . ‘ oe . }
1.1. Form 1 PartA
1.1.1 Ensure that the form is fully completed. J
1.1.2 In the case of an MCU or Op Works below the high-water mark, owners consent is required.
1.1.2.1 If there are muitiple owners, the consent of each owner is required.
1.1.2.2 If the owner of the land is a company, either ACN No. or Company Seal required.
1.2. Form1 Part B-O Supporting Information
1.1.2 Ensure that for each box checked on Form A, the relevant additional Forms B-O are attached.
1.1.2.1. Ensure that each of Forms B-O which are attached are fully completed. [A
2. REFERRAL INFORMATION, .
2.1. Ensure that items 1-23 have been checked and/or completed with regard to referrals.
3. ENVIRONMENTALLY RELEVANT ACTIVITIES,
3.1. Ensure that Part G is completed if EPA referral is required.
3.2 Where EPA is delegated to Council (see * in ERA checklist), ensure that the correct application |
fee is paid and recorded on the application. A
4. FORM2-REQUEST TO CHANGE APPROVAL. — 7 |
4.1 Ensure that items 1-28 have been checked and/or completed including information regarding |
applicant details and owners consent.
5. PLANS | a ‘f .
5.1 Ensure that at least 6 sets of the Plan of Development (5 for Reconfiguration and Operational ip
Works) accompanies the application. In addition ensure that each set is complete.
§.2 Ensure that 1 of the copies of the Plan of Development is in an A3 or A4 format and is [YJ]
unbound.
6. SUPPORTING INFORMATION “~~ 7 7 ™ ee nee
6.1. Ensure that at least 6 copies of any report accompanies the application (5 for Reconfiguration _
and Operational Works), If the application is accompanied by a covering letter, ensure that it is
capable of reproduction.
6.2 In the case of reports, ensure that 1 of the copies is in an A3 or A4 format and is unbound.
7 FEES YLT SO ae 8
7.1 Ensure that the application fee, as determined from the Council $ adopted scale of fees, Y
accompanies the application or has been paid.
7.2 Ensure that the fee which has been paid is recorded on the application form. S
Receiving Officer
Having completed this form and accepted the apglication, please deliver both to the following IDAS Application Receiving
trays:-
e — {fthe application is for a Material Change of Use exclusively -AOP1’s desk in the Land Use Section.
¢ — {fthe application is for an Material Change of Use & Reconfiguration - AOP1’s desk in the Land Use Section.
«Ifthe application is for Operational Works (for parking, access, sewerage or drainage) exclusively - AOD2 in the
Land Development Section.
« Inall other circumstances - AOP1's desk in the Land Use Section.
Please DO NOT leave the application at the counter and DO NOT deliver the application to Records.
SEP! g.\ant\orms\application checklist.doc
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 15 pages
Page 2
Part A, Version 3.0, 3 September 2007
Part A
Common details
[identification of the premises the subject of the application
1. Can any part of the premises be identified by a street address or lot on plan description?
([] No - Answer Q1(a)
Yes - Complete Table B and answer Q1(b) and Qi{c)
Table B
@ Lot on plan description
Unit 1 Street Official suburb Post (place each description in a separate row)
number | number Street name Hocality name code tot Pian type Plan Local government area
number fe.9. RP, SP} number
35 Cloudstey St Noosaville 4566 20 RP 883865 Noosa Council
1(b). Can the address be further described by shop/tenancy number or storey/level?
No
LL] Yes - Complete Table C
4(c). _ Is any part of the premises strategic port land under the Transport Infrastructure Act 1994?
No
(11 Yes - Compete Table D
2. Can the premises best be identified by coordinates (e.g. for development proposed in waters, or on a site within a large rural lot)?
@ [X] No
(21 Yes - Complete Table E
3. Are the premises within or adjacent to a water body or watercourse?
[No
Yes - Complete Table F and answer Q3(a)
Table F
Name of water body or watercourse j
4 Noosa Waters Canal
3(a). Is anv part of the develooment provosed in tidal waters (.. helow hiah water mark)?
Page 3
INTEGRATED PLANNING ACT 1997 Part A, Version 3.0, 3 September 2007
4. Whatis the total area of land that makes up the premises {ie. the area covered by the application)?
Area of land above high water mark/outside watercourse Area in a water body or watercourse
931.00 [x]m? [_Jhectares (Tick applicable unit) LJm2 [hectares (Tick applicable unit)
Existing use of the premises oO a , : 7
5. Are the premises currently used for any purpose?
[x] No
LJ Yes - Ensure details of any existing use of the premises are provided in plans and documentation submitted with this application, e.g. location
and nature of existing uses, buildings, structures and services
6. Are there any existing easements on the premises (e.g. for vehicular access, electricity, overland flow)?
No
LD Yes - Complete Table H and ensure the location and dimensions of each easement are included in plans, submitted with the application
Broposaldetais
7. Are new uses proposed on the premises?
(J No
Yes - Provide details in Table |
Table |
Each proposed new use
1 Private timber jetty
8. Are new buildings or structures proposed to be erected on the premises?
CJ No
Yes - Ensure the nature, location and dimensions of the proposed new buildings, structures or services are included in plans, submitted with the
application
Roplicant details - ~— 4
9. Who is the applicant for the application?
Company/organisation name
(if applicable) Carol Rose C/- Noosa Jetty Builders
Individual/ contact person details
Title Mrs First name Emma Lastname (Reed
Postal address [po Box 299, Noosaville QLD 4566
Contact telephone number [07 5474 3480
Mobile phone number Jo408 137 526
Facsimile number [o7 5474 3480
e-mail address [[email protected]
JOwner's 's consent and resource entitlement _ ’
10. Does the application involve a State-owned resource prescribed by schedule 10 of the integrated Planning Regulation 7998 (IP Reg) or
any other regulation?
[x] No
[7] Yes - Complete a new Table J for each State-owned resource and submit, with the application evidence of resource allocation or entitlement
Page 4
INTEGRATED PLANNING ACT 1997 Part A, Version 3.0, 3 September 2007
11. Does the application invoive land other than State-owned land (ie. privately owned land) and require owner's consent?
{[] No
Yes - Complete Table K and submit, with the application, written documentation of all owner's consent
Table K
age Date written consent
Owner name/s Street address or lot on plan description was obtained
1 Carol Rose 35 Cloudsley St, Noosaville 4566 41/01/2008
(Mandatory attachments and supporting information = oe
12. What are the other parts of IDAS Application Form 1 submitted with this application, and the other mandatory attachments and
supporting information accompanying this application, not identified in those other form parts?
en Pat of Fam Lowers ‘onsen eee o (eg. General Aen ae setae Date ae ent meer
resource atocation/eilement, plans, drawings, reports) Report)
1 Owners letter of consent 11-Jan-2008 | over the counter
2 Part E 11-Jan-2008 over the counter
3 Plans Caro} Rose 08/ Jan 2008 over the counter
Portable Long Service Leave (PLSL) levy for building and construction work “]
13. (s payment of a Portable Long Service Leave (PLSL) levy required for building and construction work before a development permit for
the'application can be given?
No
CO Yes
13(a). Indicate the reason PLSL is not applicable
(CC The application is not for building and construction work under the Building and Construction Industry (Portable Long
Service Leave) Act 1991, section 3AA (e.g. the application is only for a change of use or for the following types of work carried
out solely for farming purposes: land clearing, site preparation, earthworks, fences, fodder harvesting, clearing of encroaching
vegetation, clearing of regrowth, thinning vegetation or controlling weeds or pests); or
[x] All costs, that relate to the work both directly and indirectly, are less than $80,000, inclusive of GST; or
(1 The work is being carried out under an owner-builder permit issued under the Queensland Building Services Authority
Act 1991- Complete and submit a QLeave Notification and Payment Form (no payment required if owner-builder permit number
stated). The receipted form must be sighted by the assessment manager before a development permit can be given
OFFICE USE ONLY
Date Received [ 3.5 [:loe Reference Numbers [| of’ ( AE
[ ~~ FORCOMPLETION BYASSESSMENTHANAGER = stsSts=sdS
Is a QLeave Notification and Payment Form required for this application?
(1) No
(J Yes - Complete Table M
[ NOTIFICATION OF ENGAGEMENT OF PRIVATE CERTIFIER - ]
To Council
| have been engaged as the private certifier for the building work referred to in this application
Date of 7 : Seog oi .
engagement Accreditation number Name BSA Certification number Building classification
Page 5
PILE-IT Pty Ltd Trading as PLEASE RETURN Noosa Jetty Builders LETTER oe tL eas No: 0006 : FROM: Noosa Jetty Builders PO Box 299 Noosaville QLD, 4566 To Whom It May Concern, +, ABN: 55099036736 "BSA: 1111115 DATE:1 1/01/2008 Phone: (07) 5474 3480 Fax: (07) 5474 3480 Mobile: 0408 137 526 I Carol Rose, give Pile-It Pty Ltd t/a Noosa Jetty Builders permission to submit an application for prescribed title works on my behalf. Address: 35 Cloudsley St Noosaville Phone: 3Y JS&5S0 4 Email: [email protected] Yours Sincerely, Dnt Kee Post Code: 4566 Mobile: 0412 099 839
Page 6
CM SM esa Me elle ol Fiomectbewns oo 1. Is the application seeking approval of building work assessable against the local goverment planning scheme? No OO Yes 2. Is the application seeking approval of operational work assessable against a planning scheme? eS OO No [xX] Yes 2(a) ‘Is the application seeking approval for more that one type of operational work? No - Complete Table B (2 Yes - Complete a new Table 8 for each type of operational work Table B (i) What is the nature of the operational work? ( Roadworks [7] Stormwater ([] Water infrastructure (-] Sewerage infrastructure [J Landscaping (C1 Clearing vegetation under the planning scheme LJ Earthworks LJ Drainage Works —[] Other - Specify below Timber Jetty (ii) 's the application for operational work involving the creation of new lots? @ [x] No CO Yes - Specify number below [ (iii) What type of approval is being sought? (CD Preliminary approval Development Permit (iv) ts there a current Preliminary Approval for this operational work on the premises? No [1 Yes - Complete Table Bfa) (v) Are the works subsequent to a previous Development Permit or Preliminary Approval for another aspect of development? No (1 Yes - Complete Table B(b) (Mandatory Information | 3. Confirm that the following mandatory information accompanies this application Confirmation of i lodgement Method of lodgement Plans showing the nature and location of the proposed works fincluding the extent of any cut and fil) Confirmed over the counter
Page 7
INTEGRATED PLANNING ACT 1997 Part E, Version 3.0, 3 September 2007 ‘OFFICE USE ONLY Date Received Reference Numbers [
Page 8
INTEGRATED PLANNING ACT 1997 : IDAS Assessment Checklist, Version 21.0, 3 September 2007
IDAS
Assessment Checklist
Cs a
[DAS Development Application Form 1 is the approved form for all development applications under the Integrated Planning Act
1997. Form 1 is made up of various Parts. Part A (Common details) of Form 1 must be completed for all applications. The
relevance of other Parts of Form 1 depends on the nature of the application.
Form 1 also includes the IDAS Assessment Checklist, which is used to assist in determining State assessment and referral
requirements, and the Parts of Form 1 relevant to the application.
Section 1 and all other relevant sections of the IDAS Assessment Checklist must be completed for all development applications
except those for building work requiring assessment against the Building Act 1975 only. For more advice refer to Part B of the
IDAS Application Form.
Answering the following questions will assist you in determining which sections of the checklist must be completed for your application.
lf unsure, phone or visit your local goverment or log on to the IPA website for help.
Does the application seek approval to materially change use of the premises?
Ifyes - complete Section 2 of this checklist Yes |{x]No
Does the application seek approval to reconfigure a lot?
if yes - complete Section 3 of this checklist and Part F of IDAS Application Form 1 DYes |{x]No
Assessment is by the local government
Does the application seek approval to carry out operational work?
ifyes - complete Section 4 of this checklist f] Yes |[]No
Does the application seek approval to carry out building work requiring assessment against the Fisheries Act 1994?
if yes - complete Section 5 of this checklist
Does the application seek approval to carry out building work requiring assessment against a local government planning
scheme?
If yes - complete Part E of IDAS Application Form 1 (1 Yes |PxJNo
Assessment is by the local government
Does the application seek approval to carry out building work requiring assessment against the Building Act 1975?
If yes - go to Appendix 1 of this checklist for advice on building referrals. Complete Part B of IDAS Application Form 1 OYes |—x)No
Assessment is by a building certifier
(Yes {[JNo
6 ey Section 1 must be completed for ai! applications that require compietion of the IDAS Assessment Checkiist.
HERITAGE J ]
14 is any part of the proposal intended to be carried out on a registered place under the Queensland Heritage Act 1992?
No
CI Yes
IPA, schedute 8, part 1, table 5, tem 2
IP Regulation, schedule 2, table 2, item 18
IPA, section 1.3.5 (Definitions for terms used in development)
[REMOVING QUARRY MATERIAL; WILD RIVER AREA _ j
1.2 Does the proposal involve removing quarry material from a watercourse or lake as defined under the Water Act 2000?
No
C1 Yes
Page 9
INTEGRATED PLANNING ACT 1997 {DAS Assessment Checklist, Version 21.0, 3 September 2007
JPA schedtite 8 part? table 5, tem 1
IP Regu. nec’ 2, table 2, dem 11
IP Regist er sents V table 5 fem 2 ia dren ate}
Water Art 2000 section 966C
Vind Rivers A. 12005 section 43A
ENVIRONMENTALLY RELEVANT ACTIVITY: WILD RIVER | AREA
1.3 Does the proposal involve an environmentally relevant activity € RA), other than a mining activity or a petroleum activity?
[xX] No
( Yes
IPA schedutt 8 part 7, table 2. tem 7
IPA, schedule 8 part 1. table 5 wems 3 and 4
IP Regulation schedule 2 table 2, tems 1 and 23
Environmental Protection Act 1994, section /3AA (wid river area)
Wad Rivers Act 2005, section 43A
THIN THE UBATS OF APORT oy
14 ls any part of the premises within the limits of a port under the Transport Infrastructure Act 1994?
[x] No
C1 Yes
IP Regulation, schedule 2, table 2, items 15 and 16
DECLARED FISH HABITAT AREA ~ |
15 Does any part of the premises adjoin a declared fish habitat area under the Fisheries Act 1994?
[X] No
Yes - if answers to questions in other sections of this checklist indicate that the proposed development is assessable under IPA,
1p!
schedule 8, this application requires assessment by the Department of Primary Industries and Fisheries (DPI&F). if DPI&F is not
the Assessment Manager for the application, the agency has jurisdiction as Advice Agency.
IP Regulation, schedule 2, table 2, item 26
COMMUNITY INFRASTRUCTURE s——s—“—=s<“‘<“<i <;< CO]
1.6 (s any part of the premises designated for community infrastructure?
[x] No
CL) Yes
JP Regulation, schedule 2, table 3. kem 7
WVASTE WATER MANAGEMENT 3
17 Does the proposal involve the establishment or expansion of a waste water disposal system?
[x] No
( Yes
IP Regutation, schedule 2, table 3, tem 5
Section 4 must be completed when the application seeks approval to carry out operational work.
PLANNING SCHEME = ————
44 ts any of the proposed operational work assessable under a planning scheme?
[K] No - Go to Question 4.2 below
[Yes - Complete Part E of IDAS Application Form 1 and Questions 4.1.1 - 4.1.8 below
ASSOCIATED WITH RECONFIGURING A LOT; RESIDENTIAL, COVMERCIAL OR INDUSTRIAL DEVELOPMENT INA WILD RIVER
(AREA _
42 Is any of the proposed operational work associated with reconfiguring a lot, if the reconfiguration is also assessable?
No
( Yes
IPA, schedule 8, part 1, table 4, item 2
IP Regulation, schedule 1, part 2, table 5, item 1(c)
Wild Rivers code (Note. the code does not currently contain applicable provisions for residential, industrial of commercial development inside 4 designated urban
area)
Page 10
INTEGRATED PLANNING ACT 1897
\EGETATION CLEARING; KOALA CONSERVATION; WILD RIVER AREA
43
[TAKING OR INTERFERING WITH WATER; WILD RIVER AREA
44
45
4.6
47
48
Is any of the proposed operational work for the clearing of native vegetation to which the Vegetation Management Act 1999
applies?
No
C1 Yes
"3 pat? table 4 tems TA 1G
en schedule 2 table 2 #em $ (vegetated Ceccng?
hon schedule 2 table 2 tem 34 (kodia (Ud:
W Regei.tion whedce T pant 3 be 4 sem
Vegetation Wen--gement Act 1999. sectien 224 ba
Wud Rivers Act 2005. sections 31F and 43A
1G 4D ef Fein
sid cyer 3783}
Is any of the proposed operational work to allow, under the Water Act 2000, for taking or interfering with water from a
watercourse, lake or spring (other than under the Water Act 2000, section 20(2), (3) or (5)), or from a dam constructed on a
watercourse?
[x] No
(1 Yes - This application requires assessment by the Department of Natural Resources and Water (NRW). if NRW is not the Assessment
Manager for the application, the agency has jurisdiction as Concurrence Agency
IPA, schedule 8, part 1, table 4, items 3(a)
JP Regulation, schedule 2, table 2. tem 8
IP Regulation, schedule 1. part 3, table 4, items 3 and 3A
Water Act 2000. section 966A (wild rver area)
Wild Rivers Act 2005, section 43A
Is any of the proposed operational work to allow, under the Water Act 2000, for taking or interfering with artesian water?
[x] No
(71 Yes - (Complete Part K,) This application requires assessment by the Department of Natural Resources and Water (NRW). If NRW is
not the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency.
IPA, schedule 8, part 1. table 4 item 3{b)
IP Regulation, schedule 2, table 2, tem 8
IP Regulation, schedule 1, part 3, table 4, tem 3
Wild Rivers code (Note: the code does not currently comain applicable provisions for taking or interfering with artesian water)
ls any of the proposed operational work to allow, under the Water Act 2000, for taking overland flow water?
No
(D1 Yes - Answer (a) and (b) below
IPA, schedule 8, part 7, table 4, item 3{c)f)
IP Regulation schedule 2, table 2, tem 8
JP Regulation schedule 1 part 3, table 4. item 3
Water Act 2000, section 966A (wild river area)
Wild Rivers Act 2005, section 43A
Is any of the proposed operational work to allow, under the Water Act 2000, for taking or interfering with subartesian water?
No
C] Yes
IPA, schedule 8, part 1, table 4, iter 3(c)(ii}
IP Regulation, schedule 2, table 2. item 8
IP Regulation, schedule 1. part 3, table 4, kem 3
Water Act 2000, section 966A (wild river areaj(Note’ no current Wild River declaration identifies taking or interfering wath subartesian water as assessable)
Wild River code (Note: the code does not currently conta:n applicable provisions for sub artesian water)
No
[11 Yes - Answer both (a) and (b) betow
IPA, schedule 8 part 1, table 4, items 3(c)() and 3{d)
IP Regulation, schedule 2, table 2, tem 9
JP Regulation, schedule 1, part 3. table 4, item 3A
Water Act 2000, section 9668 (wild river area)
Is any of the proposed operational work to allow, under the Water Act 2000, for interfering with overland flow water?
IDAS Assessment Checklist, Version 21.0, 3 September 2007
Page 11
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 21.0, 3 September 2007 49 Is the proposed operational work for the following? e For the construction of a referable dam as defined under the Water Act 2000 = [x] No CO Yes © To increase the storage capacity of a referable dam by more than 10% —) No 1 Yes If yes to either or both - (Complete Part Ks) This application requires assessment by the Department of Natural Resources and Water (NRW). if NRW is not the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency. IPA shed. '#! pad] iab'e 4 tem 4 JP Regulation schedite 2 iable 2. tem 70 DAL WORK; wiLD RIVER AREA _ 4.10 ls any of the proposed operational work tidal work, other than excluded work defined under the IPA? [x] No (1) Yes - Answer (a) and (b) below IPA, schedute 8 part 1, table 4, item 5 IP Regutation schedule 2. table 2, hems 12, M4 and 1/ IP Regulation schedule 1. part 3 table 4, tems 4A and § Coastal Protection and Management Act 1995 section 104A (wild river area) COASTAL MANAGEMENT DISTRICT: : WILD RIVER RAREA 411 ts any of the operational work proposed to be carried out within a coastal management distil? [x] No LC] Yes IPA, schedule 8, part 1, table 4 uem 5 IP Regutation, schedule 2, table 2, tems 12 and 14 IP Regulation, schedule 1, part 3, able 4, wems 4A and § Coastal Protection and Management Act 1995 Act 1995, section 104A (wad nver ded) Wald Rriers Act 2005, section 434 AVATERWAY BARRIER WORKS; WILD RIVER AREA i. 4.12 is any of the proposed operational work for constructing or raising waterway barrier works under the F Fisheries Act 1994? [X] No LJ Yes IPA schedute 8 part 1, table 4, item 6 IPA schedule 8, part 2, table 4, item 2 IP Regulation, schedule 2, table 2, item 28 IP Regulation, schedule 1, part 3, table 4, item 6 Fisheries Act 1994, section 76D (wild river area) Wild Rivers Act 2005, section 43A pec CLARED FISH HABITAT AREA, WILD RIVER AREA 4.13 Is any of the operational work proposed to be carried out completely or partly within a declared fish habitat area under the Fisheries Act 1994? No C] Yes IPA, schedule 8 part 1, table 4, tem 7 IPA, schedule 8 part 2, table 4, item 3 IP Regulation, schedule 2, table 2, item 25 IP Regulation, schedule 1, part 3, table 4, item 7 Wud Rivers Act 2005, sections 43A Fisheries Act section /6DC (wild river area} REMOVAL, DESTRUCTION OR DAMAGE OF A MARINE PLANT; WILD RIVER AREA 4.14 Is any of the proposed operational work removing, destroying or damaging marine plants under the Fisheries Act 1994? No C Yes
Page 12
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 21.0, 3 September 2007 “ JPA scheti » & per? table 4, item 8 rh pid? table 4 item 4 hedu'e 2. lable 2, tem 29 vhedue 7) part 3. tabled tem 8 Fisheres Aol 4:44 sector 76DA (vid fiver ares Wid Ris At eceS section 43A WILD RIVER AREA oo SY 4.15 1s any of the operational work proposed to be carried out in a wild river area declared under the Wild River Act 2005? No (1 Yes IPA schedute 8 part 1, table 4, tem 10 IP Reguiation, schedule 2. table 2. tem 37 Wild Rivers Act 2005. sections 42, 43A TATE-CONTROLLED ROAD : ee et 4.16 Is any part of the premises within 100m of a State-controlied road, or part of a future State-controlled road? No (I Yes e IP Regulation, schedule 2, table 2, item 3 Disclaimer: While the Department of Locat Government, Planning, Sport and Recreation (ODLGPSR) believes that this information contained on this form and provided as part of this process will be of assistance to you, it is provided on the basis that you will not rely on the information without first making your own enquiries regarding the interpretation and application of the applicable legislation to your circumstances. To the full extent permitted by law DLGPSR expressly disclaims all liability (including but not limited to liability for negligence) for errors or omissions of any kind or for any loss (including direct and indirect losses), damage or other consequence which may arise from your reliance on this process and the information contained on this form Proposal ID Click here to submit your DA
Page 13
101/80. yo ” ONG SREOM oe , 4 LNOAVI ONINVYS SL mae NV1d 3LIS om by wwoe _ UV HOMWN ALNNOO = tg | TIHAAO OOlY 9002.4 NOLMBY § VSARM HSIeWd oe =e _ Ae Av ava NANO SOBES8dY . ' — | > 0% 107 : 4S \ _ fs inch apr achies + Leap t ~— io Ty Fe ba 20 84 LEZ dd NOlidhaosaa i , | | memos oes ET Awadoud wad} A ee ee 4 ATA] UENO 9) ang ¥ 19RL oon gees \ re S . — Ey ‘ : | ~ ~ : qeeurSug uBreeg BAD | RUMON[g = a \ i un a i aa INT ; * x a a \ } i seyeloossy 9 | i. . o> USPJON UYOr & $310d OMH & 3 § 7 =—_—_ O3LVIUL NIN 002 @ “0, |F 3 SYALVM VSOON ‘S31 | ; 1334S AZISsano19 | oNa Kova siu0s 7321s al ty (Seon) SSI INIVLS OML HLIM _¢_ Z SUBYV3E OL O3XI4 GMH +14 SZi x BE 0c LOT ONDIDSC ae , ALLsr d3sOd0ud 5 oruev4 31KALOZO ro == . sols ioevyo 01 aN a : N Y ese eceumretoon, / | | j Bwownoe Auwsaous | MOTITRANR Sere TS i |Z — \ ! 1 ? 3 “a j emilee xt oe oo Siow w/) TV ONINIVLEY BLIWONOD sYsqing ; 02 107 ; | soon ALLSr VSOON j SV ONIOVALL , GLI Ald LIS ge 7 06 - ; L NOILVAS 13 aS | dik ke s ao m @ NOILVAS13 | ~ 4 | : : | | | | | \ | : > 9 era; | i | fj bo por *33Mis a7 | ! | 1 of ft nt "anor L x ney . ' i ~ o DID Be 2 VOTER > SESH I 8 3GOO ONMId - 6S4Z SV HLM SEES < A L | BZONVOYODOV NI GSTIVISNI 38 TIVHS S31Id Ty ib : / "9 GUVZVH O1 G3ALVSYL ONY eh COOMGYWH C3AONddv 38 TIWHS SStid Ty ‘ST1d ~ OHV ++'0 TY MALYM WONININ a t Se — ~ OHVOLTY " ~ Toe ——GHY OT Te O30 — OHV 0'1 Ty OHV 071 Ta yOsT I 4 TVM dO. dOL TM HO-dOL . GHV 00% Td 73A31 GO014 G30uO0SY WNNIXWN
Page 14
\ BEARERS: 150 x 75 HWD FIX TO EACH PILE KICKER: 75 x 38 HWD 1/75 x No14 TYPE 17 STAINLESS STEEL SCREWS @ 450 CRS PILES: @ 200 H6 MARINE HWD POLES NOTE THAT ALL POLES TO COMPLY WITH AS 2189 - PING COOE PILES: @ 200 H6 MARINE HWD POLES NOTE THAT ALL POLES TO COMPLY WITH AS 2158 - PILING COOE NOTES: 1. UNLESS NOTED OTHERWISE ALL TIMBER SHALL BE DURABILITY CLASS 1 OF APPROVED SPECIES AND HAVE A STRESS GRADE OF F14 MIN. 2. UNLESS NOTED OTHERWISE ALL CONSTRUCTION SHALL COMPLY WITH THE ENVIRONMENTAL PROTECTION AGENCYS' OPERATIONAL POLICY - "BUILDING AND ENGINEERING STANDARDS FOR TIDAL WORKS.” 3. ALL STAINLESS STEEL BOLTS, RODS, ETC., SHALL BE APPROVED MARINE GRADE 316. ALL OTHER STEELWORK INCLUDING NUTS, BOLTS, WASHERS, SCREWS, NAILS, ETC., SHALL BE HOT DIPPED GALVANISED OR STAINLESS STEEL. wrwamipameent | DETAIL “1 \ 4. TOP OF PILES SHALL BE SEALED AND FULLY CAP FLASHED OR RINGED. 5. DIMENSIONS AND LEVELS SHALL NOT BE SCALED FROM SECTION“A~ THE DRAWINGS. oh 4:20 \ 1 ) Ni ~—~— 180 « 75 HWO 10 PL ANGLE BRACKET TRADING AS NOOSA JETTY BUILDERS DETAIL Ce PROPOSED JETTY LOT 20 (No.35) CLOUDSLEY STREET a NOOSA WATERS | JETTY USE: . RABRINK PTY LTD T/A ‘SINGLE USER, PRIVATE John Norden | NO VEHICULAR ACCESS | & Associates WALKWAY DECK VERTICAL umene DESIGN LIVE LOAD - 2.0 kPa MAXIMUM MOORED VESSEL - 5m BERTHING VELOCITY - 0.5 m/sec Pr 07 $4497137 Fax 07 54407172 Emel. n_s@'ntermode on net Cre | (apin_| WORKING DRG ~"08/10-2 |_|
Page 15
xm a __ ‘LAND USE SECTION FEES hw MNOS : RECEIPT TYPE SALE OF DOCUMENTS Superseded Planning Scheme Documentation §20 Copy of Permit/Approval Letter 110 The Noosa Plan Documentation 111 APPLICATION FEES , Material Change of Use - Code/Impact Consistent 521 Inconsistent 521 Assessment under Superseded Planning Scheme §21 Modification to a Development Permit 521 Extension of a Currency Period : §21 Operational Works - Landscaping §21 e@ Bldg Work assessable against the Planning Scheme 521 PRE LODGEMENT REVIEW Half Hour 522 One Hour §22 ADVERTISING Purchase Advertised Applications 523 JETTIES . Jetty Application Fee (3002 524 Jetty Bond S20 51 (Category 4) BONDS / Performance Bond 51 (Category 9) SIGNS . . Registration Fee . : . 222 sfcn FEE Search of Land Use Section file 112 Liquor Licensing Request : 113 TOTAL § /FOO NAME: PR NR oer, ADDRESS: af-_ Carrt Leore, FILENO: O87 14y pareo 5/2/08 = TS y RECEIPT NO: r 3 622. . Signature of TP Officer: e 3 SV rene _y AUTHORITY NO: U (4 f 22087] Fe)
Page 16
CALCULATION OF FEES APPLICATION FEE TOTAL FEES MCU - CODE ASSESSMENT Details of Development Consistent 1.0 Inconsistent 3.0 FEE CALCULATION MCU - IMPACT ASSESSMENT Details of Development Consistent 1.0 Inconsistent 3.0 FEE CALCULATION © OPERATIONAL WORKS Details of Development FEE CALCULATION TOTAL FEES
Used in these records
08/0194 - Operational Works - Transport Type 5 - Domestic Marine [As Published]Related documentApplication case desk ↗
About this file
- File size
- 746 KB (small file)
- File type
No other editions are linked here.