STP22-0347 DA Engineering Report RFI Response Rev C
STP CONSULTANTS
4. Water Supply and Sewerage
4.1 WATER CONNECTION
The new buildings will connect into the existing internal reticulation as illustrated in Figures 3.1 and 3.2 above. All
new and amended fixtures will be subject to a Plumbing and Drainage Application to Noosa Shire Council. It is
unlikely that the existing connection to the Unitywater infrastructure will require upgrading. This is located to the
north of the main entrance in Cooyar Road and fed by a crossing from the 150mm main located on the opposite
side.
4.2 SEWER CONNECTION
The new buildings will connect into the existing internal reticulation as illustrated in Figures 3.1 and 3.2 above. All
new and amended fixtures will be subject to a Plumbing and Drainage Application to Noosa Shire Council. It is
unlikely that the existing connection to the Unitywater infrastructure will require upgrading.
As illustrated in Figure 4.1, the site is traversed by existing Unitywater sewer infrastructure. Any construction within
5m of this 300mm trunk main will require approval from Unitywater under Queensland Development Code MP1.4.
Figure 4.1 – Existing sewer infrastructure (Unitywater)
Civil Engineering Report & Site Based Stormwater Management Plan | STP22-0347 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.