Delegated Report - Code - Planning - MCU25 0022 & OPW26 0029 (As Published) · MCU25/0022
Figure 5 – Mapped Major Transmission Line Corridor and a Major Electricity Transmission Buffer under the
Regional Infrastructure Overlay Map
4. CONSULTATION
4.1. Referral Agencies
In accordance with its jurisdiction under Schedule 10 Part 9 Division 2 of the Planning Regulation
2017, Powerlink Queensland was a Referral Agency (Advice) for the above development
application.
Specifically, the application required assessment by Powerlink Queensland under the following
referral triggers:
• For material change of use – all or part of the premises are subject to a transmission entity
easement which is part of the transmission supply network (Table 2 1b).
• For operational work – all or part of the premises are subject to a transmission entity
easement which is part of the transmission supply network (Table 3 1a).
The applicant referred the application to Powerlink Queensland on 14 April 2025. The referral was
made in accordance with Section 54 of the Planning Act 2016.
Powerlink Queensland responded on 4 June 2025 confirming support of this application subject to
the inclusion of the conditions in their response in Council’s Decision Notice.
With reference to the unapproved structure shown in Figure 4, Powerlink has in their amended
response stated that the submitted plans and reports are supported, subject to their recommended
conditions.
The conditions recommended by Powerlink include the requirement to surrender the existing
easement referenced 601108825 over Lot 6 on RP216727 and contemporaneously register a
replacement easement over Lot 6 on RP216727 on terms satisfactory to Powerlink.
The terms of the replacement easement shall include but not be limited to permitting the location
of the awning/shelter site (set out in Attachment 2 - Assessed Plans) to remain within the easement
area only while the Applicant remains the registered owner of Lot 6 on RP216727 and requiring
the awning/shelter to be removed or relocated at the applicant's cost, if directed by Powerlink.
As requested by Powerlink, the conditions included in their amended Referral Agency Response
will be imposed by Council in their role as the Assessment Manager for this development as an
attachment to the decision made by Council.
Page 11 of 21
Document Set ID: 24249087
Version: 16, Version Date: 24/07/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning - MCU25 0022 & OPW26 0029 (As Published).pdfRelated documentApplication case desk ↗
Delegated Report - Code - Planning - MCU25 0022 & OPW26 0029 (As Published)Related documentApplication case desk ↗
About this file
- File size
- 5.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.