R RECONFIGURING A LOT CODE
The Noosa Plan
O18 Noted. All proposed uses and works will maintain a safe distance from electrical
infrastructure including substations, overhead power lines, power poles and
transformers.
O19 A bio-retention basin is proposed on Lot 800 for treatment of stormwater run-off such
that water quality and quantity is maintained
O20 Not applicable. No filling or excavation is proposed as part of this application.
O21 The proposed lot layout has been determined on the basis of the sites environmental
constraints.
O22 A 50m buffer area will be provided measured from the rear of the lots (within the
proposed balance park lot) to the edge of the vegetation/ Wooroi Creek.
O23 Not Applicable. No buildings or structures are proposed as part of this application.
O24 The balance land is to be dedicated for the purposes of a reserve.
O25 The proposed park lot (lot 900) retains the existing vegetation to preserve the sites
ecological values. A clear and legible pedestrian connection is provided between lots
6 and 7 to enable access to the park.
O26 The proposed park will be suitable for its intended use and is not subject to
contamination.
O27 The park will cater to the recreational needs of residents and visitors. It is anticipated
that the park will be landscaped and provided with the relevant infrastructure.
O28 Not applicable. The site is not included in the Open Space Conservation Zone.
O29 The balance land will be dedicated to Council for the purposes of a park.
O30 A 50m buffer area (within the balance park lot) will be provided measured from the
rear of the lots to the edge of the vegetation/ Wooroi Creek.
O31 The site does not adjoin a major road network or rail corridor and as such, is not
subject to high traffic noise levels.
O32 Proposed access easements (where required) will be designed in accordance with
Sections 2 and 3 of PSP5 Engineering Design Standards – Roads, Drainage and
Earthworks.
O33 Traffic generated by the development will be within the acceptable capacity of
external road network.
O34- 035 Not applicable. The site is not included within the Noosa Trail Network
O36 Not applicable. The site is not included in the Cooribah Locality
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix I - Planning Scheme Code Response.pdfRelated documentApplication case desk ↗
About this file
- File size
- 99 KB (small file)
- File type
No other editions are linked here.