NOOSA COUNCIL IDAS Development Application Decision Notice                                                   5 of 10


22.    Sediment and erosion control measures must be in place prior to works commencing. If such measures
       are not in place or are not satisfactory, “on the spot “fines may be issued. Such fines can be issued if
       sediments from the site are found to enter or have the potential to enter Council’s stormwater system or
       natural waterways. Although the sediment and erosion control measures have been approved on
       drawings Nos. CB0849-ESC01-C, CB0849-ESC02-B, CB0849-ESC03-B, CB0849-ESC04-A Council’s
       Manager – Land Development may request further controls to be installed should approved measures be
       inefficient.

23.    Pursuant to Section 3.5.21(5) of the Integrated Planning Act 1997, the Relevant Period is two (2) years
       from the day this permit takes effect (4 February 2010) during which time all conditions must have been
       complied with and the Plan of Survey lodged with the Council for endorsement.

24.    Notwithstanding that Council has checked the plans with due care, where it is found during construction
       that variations from Council's standards exist, then Council standards shall apply.

Water & Sewerage

This Decision Notice is issued subject to and conditional upon the relevant Approved
Development Permit having been granted to the applicant.
25.    Existing sewer to be capped at the eastern boundary to the satisfaction of Noosa Council’s Water and
       Sewerage Capital Works Manager – Mike Froude (Ph 5449 5288).



26.    The names of any proposed contractors for works are to be submitted in writing, together with copies of
       current Public Liability and Workers Compensation Insurances together with certificates of currency for
       those policies, for consideration by the Assessment Manager seven (7) days prior to pre-start meetings
       and commencement of works.

      A separate letter will then be issued approving the contractor (or otherwise) for the works. No other
      contractor or subcontractor shall be engaged to carry out the works or any part of the works without the
      written approval of the Assessment Manager.

27.    Council’s Water & Sewerage Inspector shall be given (7) days notice of intention to commence works. A
       pre-start meeting shall be arranged prior to commencement of works by contacting Council’s Water &
       Sewerage Inspector, Mr Trevor Mourilyan, Ph. 0417 780 830. Inspector is only available for pre-start
       meetings, inspections and testing etc. between the hours of 6:30am to 4:00pm, Monday to Friday.
       Inspector will not be available outside these hours unless prior approval is obtained from the Water &
       Sewerage Capital Works Manager with any costs incurred by Council outside the hours nominated above,
       met by the Contractor/Developer. These costs will be in addition to normal inspection fees.



28.    It is the responsibility of the applicant to ensure that its consultants and contractors take all reasonable
       care during the construction of the engineering works to ensure that Council property or facilities (such as
       underground drainage, water supply and sewerage) are protected against any damage or interference
       whatsoever. If any Council property or facilities should be damaged by the applicant or any of its
       consultants or contractors through any cause whatsoever in the course of, directly or indirectly, carrying
       out the engineering works, the applicant and/or its contractors shall forthwith notify the Assessment
       Manager and shall forthwith rectify the damage to that property or facility at its cost to the satisfaction of
       the Assessment Manager prior to the sealing of the survey plan and/or acceptance of the works on-
       maintenance. Alternatively, the applicant may request the Council to carry out the rectification work at the
       applicant's cost, such cost being paid by the applicant to the Council prior to the sealing of the survey plan
       and/or acceptance of the works 'on maintenance' provided that in the case of emergency, the Council
       shall be entitled to rectify such damage at the cost of the applicant such cost being paid prior to the
       sealing of the survey plan and/or acceptance of the work 'on maintenance’.



29.   As Constructed drawings in both hardcopy and digital format (ADAC) produced in GDA94 Zone 56
      coordinate value to the standards and requirements of the Assessment Manager are required for Council
      records. Such 'as constructed' drawings will be required prior to works being accepted "on maintenance",
      where applicable. Requirements for "as constructed" information are detailed in the current version of
      Council's Engineering Design Standards (Water & Sewerage) Manual.




NSC c:\docume~1\amoore\locals~1\temp\bcl technologies\easypdf 5\@bcl@d00f88d5\@[email protected]

Used in these records

About this file

File size
49 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2007.00002125.001 [As Published].pdf · 49 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.