Skip to the record
Trusted by locals. Built for Noosa.

Council archive · source document

Decision Notice - 010.2005.00002302.001 [As Published] · 132005.2302

of 15

Text shows just the words. Original shows the document exactly as it was published.

                                    Form 6 - Decision Notice
                                    INTEGRATED PLANNING ACT 1997, S3.5.15, IDAS DEVELOPMENT APPLICATION


 File No:    2005/2302                             Date of Decision:    31 May 2007

1.    APPLICANT DETAILS

 Name:               Parish Clarke Architects

 Postal address:     PO Box 4153
                     ST LUCIA SOUTH QLD 4067

 Phone no:           3876 0188                  Fax no:     3371 5100

2.    PROPERTY DESCRIPTION

 Street address:     29 Ventura Street, Sunrise Beach

 Real property       Lot 124 RP 132134, County of March, Parish of Weyba
 description:

3.    OWNER DETAILS

 Name:               Anne L Weber

 Postal address:     16a Truscott Street
                     CAMPBELL ACT 2612

4.    REFERRAL AGENCIES

 Referral Agency            Address                                                    Basis
 Environmental              GPO Box 2771, Brisbane Qld 4001                            Concurrence Agency
 Protection Agency

5.    APPLICATION TYPE

 Development                      Development Details                        Preliminary          Development
                                                                              Approval               Permit
 Material Change of Use           Duplex Dwelling                                 No                   Yes

6.    DECISION DETAILS

Council on 31 May 2007 decided to:
A.    Approve the application and grant a Development Permit, subject to conditions.
B.    Approve the application despite its conflict with the Transitional Planning Scheme for the following
      reasons:
      1.     The applicant acted in good faith by complying with the plot ratio requirements of 0.5:1 of the draft
             Noosa Plan, which had been publicly advertised at the time of the application was lodged.
      2.     The propose development is unlikely to have a significant adverse impact on the amenity of the
             area.
      3.     No submissions were received objecting to the proposal.
Full text of the other 14 pages

Page 2

NOOSA COUNCIL IDAS Development Application Decision Notice                                                 2 of 15

7.     APPLICABLE CODES

The developer must comply with the following codes for self-assessable development related to the development
approved under this Development Permit:-
Nil.

8.     SUBMISSIONS

Nil.

9.     CONDITIONS

The approval is subject to conditions. Noosa Council’s conditions are attached. Conditions from the
Environmental Protection Agency, as a concurrence agency are also attached.

10.    FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit required                 Subject of the required Development Permit
 Development Permit for Building Works               All building works

 Development Permit for Operational Works            Landscaping, Access and/or Carparking, Stormwater
                                                     Drainage, Frontage Works, Excavation of materials to fill
                                                     another site and Erosion & Sediment Control

11.    RIGHTS OF APPEAL

Rights of appeal in relation to this application are attached.

12.    ASSESSMENT MANAGER

 Name:      Noosa Council                 Signature:                               Date:        01/06/07




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 3

NOOSA COUNCIL IDAS Development Application Decision Notice                                                 3 of 15




                                    Noosa Council Conditions
                                    INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION


Land Use
4.     Development undertaken in accordance with this approval must generally comply with the approved plans
       of development. The approved plans are titled and numbered Site Plan 480.NOO 001 Issue 01; Basement
       Plan 480.NOO 101 Issue 01; Ground Floor Plan 480.NOO 102 Issue 01; First Floor Plan 480.NOO 103
       Issue 01; Roof Plan 480.NOO 104 Issue 01; Sections AA/BB/CC 480.NOO 301 Issue 01; Elevations 1/2
       480.NOO 201 Issue 01 and Elevations 3/4 480.NOO 202 Issue 01 prepared by design team and dated 3
       May 2007 and as may be amended by these conditions.

5.     The development must be undertaken and operated in a manner that causes no detrimental effect upon
       the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other
       emissions.

6.     Existing trees on the site and within road reserves are to be retained, except where required to be
       removed due to building operations or the conduct of the approved use. The landscape plans required to
       be submitted are to denote areas of existing vegetation or existing trees proposed or required to be
       retained.

7.     The open space and setback areas are to be landscaped in accordance with Council’s Policy on
       Landscaping Guidelines and a properly prepared landscape plan prepared by a suitably qualified
       Landscape Architect or Horticulturalist. Such landscaping is to be completed prior to the premises being
       occupied and maintained at all times thereafter. The submitted landscape plan shall detail the following:-

       7.1.   the provision of dense screening vegetation along the side (western and southern) property
              boundaries of the site to provide privacy screening to adjoining properties.

       7.2.   the provision of dense screening vegetation around the perimeter of the building in order to screen
              basement walls and raised deck areas.

       7.3.   the retainment of one Banksia species, in good health and the replacement of the Banksia species,
              in poor health, located on the southern boundary of the site.

8.     All fencing shall be setback at least 1 metre from the front property boundary, with at least half of the
       fencing setback 2 metres with the exception of the northern corner of the site adjacent to the Orealla
       Crescent and Ventura Street intersection in which fencing may be aligned on the boundary in accordance
       with the approved plans. The area of land between the fence and the front property boundary shall be
       densely landscaped to screen any fencing from the street.

9.     All fencing/walls shall not exceed a maximum height of 1.8 metres above natural ground level.

10.    All balustrading, including for the roof top terraces, decks, balconies and stairs fronting Ventura Street
       shall be constructed of open or transparent materials.

11.    Any deck or balcony areas are not to be enclosed with shutters, glass panelling or the like, thus remaining
       as open structures.

12.    All hot water systems installed shall be either solar systems; electric heat pump systems; or gas systems
       (LPG or natural).

13.    The proposed development shall have all kitchen, laundry and bathroom fittings that comply with the AAA
       Water Conservation Rating System as defined by the AS/NZS 6400 (Water Efficient Products - Rating
       and Labelling 2003) and AS/NZS 3500 (National Plumbing and Drainage Standard Part 1.2), with toilets to
       comply with the AAAA Water Conservation Rating System. All tap ware and shower roses shall not
       exceed a maximum flow of 9 litres per min. Dishwashers and washing machines are excluded from this
       requirement.

14.    The development shall not exceed a maximum building height of 2 storeys and 8 metres above natural
       and finished ground level.




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 4

NOOSA COUNCIL IDAS Development Application Decision Notice                                                    4 of 15


15.    A verification survey of the building is to be carried out by a Licensed Surveyor and a certificate lodged
       with Council at completion of the work confirming compliance with the maximum building height above
       natural surface, required by the provisions of the Planning Scheme.

16.    Security in the form of a cash bond or trading bank guarantee to the sum of $12,500 must be submitted,
       to secure performance of all conditions of this approval, prior to the issue of a Development Permit for
       operational works. The cash bond or trading bank guarantee will be returned on performance of
       conditions of approval less any costs incurred by Council in respect of enforcing performance of this
       permit.

17.    The requirements of this development approval are to be effected, prior to the use of the premises.
       Council reserves the right to call upon the bond or guaranteed sum referred to in this approval to effect
       compliance with conditions.

18.    The Development Permit for a Material Change of Use of premises lapses if the use has not happened by
       31 May 2011, unless an application to extend the currency is approved by Council.

19.    The developer must obtain all of the other Development Permits referred to in the Decision Notice, prior to
       obtaining a Development Permit for Building Works.
Land Development
Vehicle Access
20.    A vehicular access driveway to serve the development shall be constructed from the Ventura Street
       frontage of the site. The driveway shall be a maximum of 4.5m wide in the Ventura Street road reserve.

21.    The driveway shall be designed and constructed to Council’s design standards and to grades that prevent
       vehicles from scraping and/or bottoming whilst also allowing pedestrian movements along the footpath
       without any level difference. Should any driveways be constructed to grades that do not comply with
       AS/NZS 2890.1-2004, Council will require that the driveway be removed and reconstructed to levels that
       do comply.
       Please note, a step between the driveway and the footpath shall be avoided, as it is preferred to have the
       footpath continue at a constant grade to minimise the potential for pedestrians to trip or fall.
22.    The access driveway shall be designed to comply with the provisions of AS/NZS 2890.1-2004 with
       allowance for vehicles to enter and leave the site with a minimum head clearance (headroom) at any point
       of 2.3m.

23.    To ensure pedestrian safety between vehicles exiting the site and pedestrians on the footpath, the
       driveway and any associated fencing or vegetation near the driveway shall comply with the minimum sight
       line requirements as defined in AS2890.1, section 3.2.4. The applicant shall demonstrate compliance by
       illustrating these sight lines on the plans submitted for both Operational Works approval and Building
       Works approval.

24.    All vehicles shall enter and leave the site in a forward direction.
Carparking
25.    Carparking shall be provided within the site generally as shown on drawing number PSD3a(B) dated 10
       December 2006 by Parish Clarke Architects, except as modified herein.

26.    The carparking area shall be designed to comply with the provisions of AS/NZS 2890.1-2004 for user
       class 1A with allowance for vehicles to enter and leave the site in a forward gear and with a minimum
       head clearance (headroom) at any point of 2.3m.

27.    All carparking shall be kept, maintained and line-marked in a condition fit for use.

Public Open Space Contributions

28.    A Public Open Space contribution of $2,920 towards the acquisition of additional parkland or the
       improvement of existing parkland and facilities in the locality shall be paid to the Council prior to obtaining
       a Development Permit for Operational Works in accordance with Council’s Planning Scheme Policy
       PSP12 Public Open Space Contributions (Park). This amount will be subject to variations in the
       Consumer Price Index, All Groups Brisbane from December 2006 until the date of payment.




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 5

NOOSA COUNCIL IDAS Development Application Decision Notice                                                 5 of 15


Frontage Works
29.    Footpath improvements such as topsoiling, grassing, and tree planting are required to the Ventura Street
       and Orealla Crescent frontages of the site in accordance with Planning Scheme Policy PSP03
       Landscaping Plants & Guidelines. Grass shall be couch, free of weeds.

30.    All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel, footpath
       paving and landscaping such as trees and grasses in accordance with Council’s Standard specifications
       prior to commencement of the use permitted by this permit.
Pathway Trunk Network Contributions
31.    A pathway trunk network contribution of $656 towards external major pathways, in accordance with
       Planning Scheme Policy PSP20 Pathway Trunk Network Contributions, shall be paid to the Council prior
       to obtaining a Development Permit for Operational Works. This amount will be subject to variations in the
       Consumer Price Index, All Groups Brisbane from December 2006 until the date of payment.
Stormwater Drainage
32.    All stormwater drainage shall be collected on site and discharged so there is no net increase in
       stormwater runoff from the site. Stormwater drainage permitted to drain from the site shall be discharged
       to Council’s existing drainage structures in Ventura Street. Plans of the drainage design shall be
       prepared by a Registered Professional Civil Engineer and submitted to Council prior to obtaining a
       Development Permit for Operational Works.

33.    A survey plan of the existing Council infrastructure in Ventura Street shall be submitted to Council as part
       of any application for a Development Permit for Operational Works. The plan shall be prepared by a
       Licensed Surveyor and shall indicate the property boundaries and the surveyed location and levels of the
       existing sewer main, kerb and channel and stormwater pits.

34.    The stormwater drainage system shall be designed in accordance with Council’s Planning Scheme Policy
       PSP5 Engineering Design Standards – Roads, Drainage and Earthworks and Planning Scheme Policy
       PSP6 Engineering Design Standards – Water and Sewerage. The stormwater drainage system shall be
       designed to ensure that clearances, both horizontal and vertical, are achieved to any existing service
       infrastructure.

35.    The stormwater drainage system for the access driveway and carparking area shall be designed to cater
       for a Q100 storm event.

36.    Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank (minimum
       storage 3000 litres per dwelling/unit) that is installed to ensure water from the tank can be used for
       external uses (such as watering gardens, irrigation, ornamental ponds, water features, topping-up
       swimming pools, outdoor cleaning, etc) and for use in flushing of toilets internal to the dwelling. All
       rainwater tanks are to be designed and installed in accordance with the Queensland Development Code
       (QDC), Part 25 – Rainwater Tanks, and shall be part of the plumbing application in conjunction with the
       building approval. The location and capacity of the tanks shall be clearly shown on the plans submitted
       for Operational Works and Building Works approval and any overflow shall be directed to the stormwater
       drainage system.

37.    To ensure that polluted run-off does not enter Council’s stormwater drainage system, stormwater run-off
       from the carparking areas and the driveways shall have the first flush (the first 12 mm of rainfall or hose-
       down) collected in a grease/oil arrestor/gross pollutant trap provided on site prior to being permitted to
       discharge into Council’s drainage system.
       All other clean stormwater, such as roof water, can be collected on site and discharged through a single
       underground drain line directly into the existing drainage system, bypassing the grease/oil arrestor/gross
       pollutant trap.
       To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil arrestors/gross
       pollutant trap, which shall be submitted to the Council for approval prior to obtaining a Development
       Permit for Operational Works.
       The approved maintenance plan shall be incorporated in to the ongoing Maintenance Scheme for the
       development and a copy of this shall be provided for Council’s records prior to commencement of the
       approved Use.
       A Development Permit for Building Works shall not be granted until a Development Permit for Operational
       Works has been issued in regard to the drainage scheme.
38.    All site stormwater drainage shall be by means of a gravity system and shall not include mechanical
       pumps.




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 6

NOOSA COUNCIL IDAS Development Application Decision Notice                                                    6 of 15


Sewer Mains
39.    The site shall be connected to Council’s existing sewerage reticulation systems and be constructed in
       accordance with Council’s standards and requirements at no cost to Council.

40.    The existing sewer manhole that stands within the proposed access driveway in Ventura Street shall be
       provided with a trafficable “Class D” lid. The finished level of the lid shall match smoothly with the finished
       surface level of the access driveway.
       All modification works to the sewer manhole shall be undertaken by Council or a Council approved
       contractor. All costs incurred by Council in any modification works shall be paid to Council prior to the
       commencement of the use.
Town Water Supply
41.    The site shall be connected to Council’s existing town water supply and be constructed in accordance with
       Council’s standards and requirements at no cost to Council.

42.    Each individual water connection to the water reticulation system shall extend to the property boundary
       and be metered. All fees for the supply of water meters shall be paid to the Council.

43.    All water meters must be located outside the property boundary and in an easily assessable location to
       facilitate unhindered reading by Council and/or Council’s contracted water meter readers, and not behind
       fences or locked gates. In this regard approval of the water meter configuration and location must be
       obtained from Council’s Water & Sewerage Capital Works Manager prior to lodgement and approval of
       hydraulic drawings.

44.    For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the development shall be
       served by:

       44.1. A single Body Corporate water meter to measure the total water consumption (including fire hose
             reels, but excluding fire hydrants and fire sprinkler systems), and

       44.2. Individual water meters to each tenement capable of being separately rated, and

       44.3. A fire service (fully testable single detector check with metered bypass), where applicable, for flows
             to fire hydrants and fire sprinkler systems (excluding fire hose reels).
Headworks Contributions
45.    Contributions shall be paid to Council in accordance with Planning Scheme Policies PSP17 and PSP16
       on Water Supply Headworks Contributions and Sewerage Headworks Contributions respectively and at
       the rates applicable at the time of payment. An estimate only of the contribution rates under the current
       policies is outlined below. These amounts will adjusted in line with changes to the Consumer Price Index,
       All Groups Brisbane from December 2006 until the date of payment.
       Water Supply          $4,137
       Sewerage              $2,870
       TOTAL                 $7,007
       All headworks contributions must be paid prior to the issue of a Development Permit for Operational
       Works.
       Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the headworks
       contributions not be paid at the due time, Council shall call upon the trading bank guarantee in full.
       In the event that the Development Permit for Material Change of Use of Premises lapses or is cancelled,
       the contribution or trading bank guarantee will be returned.
Earthworks
46.    Earthworks required on site shall be carried out in accordance with Section 3.8 of Council’s Engineering
       Design Standards Manual and so as not to cause the additional ponding of water on any adjoining lands
       or the blockage of, or interference with, any natural watercourses.

47.    Earthworks carried out on site shall not affect the structural integrity of any of the existing fences and/or
       structures and/or lands that border the development site. Fences that are affected shall be replaced prior
       to the Building Certifier issuing the Certificate of Classification. In this regard any fences to be replaced
       shall be clearly shown on the plans submitted for Operational Works approval.




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 7

NOOSA COUNCIL IDAS Development Application Decision Notice                                                  7 of 15


Site Stability
48.    A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site, determine the
       soil classification, establish whether any measures are required to protect the stability of adjoining
       buildings and/or structures and/or lands, and make recommendations on the type of foundation system(s)
       best suited for the proposed development. The recommendations of this report shall be incorporated into
       the design and construction of the proposed development.
Erosion and Sediment Control
49.    Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
       control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
       waste, will be necessary.
       In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
       to the Council for approval prior to obtaining a Development Permit for Operational Works.
General
50.    A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
       specifications for all engineering works that will become Council infrastructure, which shall be submitted in
       conjunction with an application for a Development Permit for Operational Works. In this regard a
       DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be submitted in conjunction
       with any application for Operational Works.

51.    Digital detailed design drawings and calculations shall be submitted with any application for a
       Development Permit for Operational Works in respect of roadworks and stormwater drainage works. The
       design shall be in accordance with Council’s Planning Scheme Policy PSP05 – Engineering Design
       Standards – Roads, Drainage and Earthworks. To avoid conflict with underground pipes or services, all
       existing and proposed services required by the development shall be shown on the plans.

52.    To facilitate production of As Constructed drawings it is suggested that all design drawings are submitted
       in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC are
       available at www.adac.com.au).

53.    Any damage caused to any public utility during the course of construction shall be repaired to Council’s
       standards and at no cost to Council.

54.    Any alteration of any public utility or other facilities necessitated by the development of the land or
       associated construction works external to the site shall be at no cost to Council.

55.    The transportation of all materials to and from the site shall be undertaken in a manner such that no
       particle matter escapes onto a public road. All vehicles carrying materials either to or from the site shall
       be covered to prevent materials including dust being windblown from the vehicle.

56.    As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer for design
       intent, and a Licensed Surveyor shall certify the cadastre and the location, level and type of all services
       and structures. All of which shall be submitted to Council for checking and for Council’s records.
       The data must fully detail levels for all engineering works including but not limited to drainage structures,
       finished ground levels and pavement surface levels. The data shall be submitted in the Asset Design and
       As Constructed (ADAC) digital format.            (Guidelines on the use of ADAC are available at
       www.adac.com.au).
       Approval of works shall not be granted until all As Constructed information has been supplied and
       accepted by Council.
Building Services
57.    Fencing to the swimming pool must comply with the Queensland Building Act 1975 Part 3 (as amended)
       and Part 5 of Standard Building Regulation 1993 in all respects. Direct access from the dwelling to the
       pool enclosure is not permitted.
Environmental Health
58.    A Waste Management Plan (Demolition/Construction) in accordance with Planning Scheme Policy “Waste
       Management Multi-Dwellings and Commercial and Industrial Premises”, shall be submitted for the
       demolition and construction phases of the development and approved by Council’s Environmental Health
       Section prior to the issue of the development permit for operational works. The Plan shall contain the
       following information:




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 8

NOOSA COUNCIL IDAS Development Application Decision Notice                                                   8 of 15


       MATERIALS ON-SITE                        DESTINATION
                                                Re-use and Recycling                 Disposal
       Expected          waste     Estimated    On-site              Off-site             *specify
       materials                   volume       *specify proposed *specify                contractor   and
                                   (m³)         re-use or on-site contractor       and landfill site
                                                recycling methods    recycling outlet
       Excavation material
       Green waste
       Bricks
       Concrete
       Timber-please
       specify
       Plasterboard
       Metals    -   please
       specify
       Asbestos
       Other    -    please
       specify
       Note: Details of site area to be used for onsite separation, treatment and storage (including weather
       protection) shall be provided on the plan drawings accompanying your application.
59.    Noise emission from swimming pool and spa equipment (including heating equipment) shall comply with
       the following requirements:

       59.1. The equipment shall be installed and located in a manner that prevents excessive noise in
             accordance with Council’s Local Law No. 12 - Control of Nuisances. Infringement Notices (on-the-
             spot fines) may apply for offences.

       59.2. A person must not use equipment on any day if it makes or causes noise to be made:

              59.2.1.From 10pm to 7am: Which is audible outside the most exposed part of an affected building

              59.2.2.From 7am to 7pm: More than the lower of either –

                              50 dB(A)

                              5 dB(A) above the background noise level

              59.2.3.From 7pm to 10pm: More than 3 dB(A) above the background noise level.

60.    Noise emission from air conditioning equipment shall comply with the following requirements:

       60.1. The equipment shall be installed and located in a manner that prevents excessive noise in
             accordance with Council’s Local Law No. 12 - Control of Nuisances. Infringement Notices (on-the-
             spot fines) may apply for offences.

       60.2. Submission of written certification from a suitably qualified person confirming that the noise levels
             comply when measured at either the residential boundary or outside the most exposed part of an
             affected building, whichever is the closest to the equipment. This is required immediately after
             installation of the equipment and prior to any occupation of the building, and in a format approved
             by Council. This assessment must take into account noise from any other fixed equipment on the
             property e.g. swimming pool pump, heating equipment, that may increase the overall noise level
             emitted.

       60.3. A person must not use equipment on any day if it makes or causes noise to be made:

              60.3.1.        From 10pm to 7am: More than the lower of either –
                             40 dB(A)

                             3 dB(A) above the background noise level


              60.3.2.        From 7am to 7pm: More than the lower of either –




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 9

NOOSA COUNCIL IDAS Development Application Decision Notice                                               9 of 15


                        50 dB(A)

                        5 dB(A) above the background noise level


              60.3.3.   From 7pm to 10pm: More than 3 dB(A) above the background noise level.

61.    Noise from building works associated with residential development shall comply with the following –

       61.1. Limited to between 7:00am to 6:30pm Monday to Saturday.

       61.2. All reasonable measures are taken to minimise noise emissions.

       61.3. Not permitted on Sunday or public holidays.

62.    Prior to occupation a noise consultant’s report is to be submitted, demonstrating compliance with the
       noise conditions.




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 10

NOOSA COUNCIL IDAS Development Application Decision Notice                                                    10 of 15




                                        Concurrence Agency Conditions –
                                        Environmental Protection Agency
                                        INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION




                                    Concurrence agency response
                                    Integrated Planning Act 1997 ss3.3.16 and 3.3.18


Applicant:                             Parish Clarke Architects
                                       PO Box 4153
                                       ST LUCIA SOUTH QLD 4067

Application no.:                       2005/2302
Date received by EPA:                  12 May 2006
Jurisdiction:                          Environmental Protection Act 1994
Role:                                  Concurrence
Description:                           Material Change of Use
                                       29 Ventura Street, SUNRISE BEACH

                               Lot no.: 124 Registered Plan no.: RP132134

1        Type of development
        Material change of use
        Reconfiguration of a Lot
where:
        the existing use of the land is, or if the land is vacant land with no existing use the most recent use of the
         land was, for a notifiable activity under the Environmental Protection Act 1994.
        the proposed use of the land is for child care, educational, recreational, residential or similar purposes
         and the existing use of the land is, or if the land is vacant land with no existing use the most recent use of
         the land was, for an industrial activity.
        the land is on the Environmental Management Register or Contaminated Land Register under the
         Environmental Protection Act 1994.
        the land is wholly or partly within an area for which an Area Management Advice for industrial activity or
         natural mineralisation has been issued and the proposed use of the land is for child care, educational,
         recreational, residential or similar purposes.
        the land is wholly or partly in an area for which an Area Management Advice for unexploded ordnance
         (UXO) has been issued.

2        Response to development application
The Environmental Protection Agency (EPA), acting as a concurrence agency under the Integrated Planning Act
1997, provides the following response to the application detailed above –
        conditions must attach to any approval of the development
        any approval must be for part only of the development
        any approval must be a preliminary approval only
        there are no concurrence agency requirements
        the application must be refused

3        Reasons for including condition(s) or refusal
The site (the subject lot/s) is part of an area of land within which the Department of Defence (Defence) has
assessed a ‘substantial’ risk of residual UXO contamination exists. Visit the Defence website
http://www.defence.gov.au/uxo for details.

Defence advises that development or land use rezoning proposals for land within a ‘substantial’ zone should only
proceed following the conduct of UXO investigation and clearance activities. Defence maintains a list of commercial
UXO investigation and remedial search contractors that it accredits to carry out this work.




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 11

NOOSA COUNCIL IDAS Development Application Decision Notice                                                   11 of 15


Defence also recommends that owners or occupiers of potentially affected land and workers and contractors
employed on the land need to be aware of the procedure if a suspect object is found.

As the EPA has no record of the site being further investigated or remediated, it is considered that there remains a
possibility of UXO being found on it.

4       Conditions
The following concurrence agency conditions are to be attached to any approval:

4.1       Prior to the commencement of any development-related excavation, earthworks or soil disturbance, that
          part of the site to be so worked is to be subjected to investigation and, where necessary, appropriate
          remedial action.

4.2       Any person employed to work on any part of the site where Condition 4.1 has not been satisfied is to be
          forewarned in writing by the applicant.

          This warning is to explain that information available to the EPA indicates a potential for residual UXO
          exists on the site and work should proceed with due caution. It is to state the procedure to be followed
          by any person finding an object suspected of being explosive ordnance or component thereof:

             Do not disturb the object.
             Take action, where appropriate, to prevent it being disturbed by another person.
             Note its approximate dimensions and general appearance.
             Note the route to its location.
             Advise the Police as soon as possible.

4.3       Following investigation and any remedial action taken to satisfy Condition 4.1 above, the applicant is to
          submit a report, prepared in accordance with current guidelines, to the EPA for assessment. The EPA is
          to subsequently advise the Noosa Council and the applicant of its assessment in regard to Condition 4.1
          being satisfied.

4.4       No gravel, rock, sand or soil is to be removed from the site without written EPA approval.

4.5       The applicant is to advise the owner and any occupier of the site of the above responsibilities.

5       Additional comments or advice

Applicants may contact the EPA’s Contaminated Land Unit on (07) 3224 5644 or visit the Defence website
http://www.defence.gov.au/uxo for the details of current UXO investigation and remedial search
contractors. The EPA accepts reports based on investigative and remedial work carried out by these contractors.

Investigation and remedial action to satisfy Condition 4.1 typically involves sampling/search programs with
detection equipment unless the use of such equipment is:

    considered unwarranted by a UXO contractor due to the extent of any prior excavation or earthworks or,
      conversely, of any filling proposed as part of the development program; or
    prevented or made impracticable by the presence of a structure, stockpile, natural barrier or metal waste.

In the latter case, alternative action may be appropriate to minimise the risk in the first instance. For example,
where the risk of exposure to any UXO that may exist is reduced by the presence of a structure or natural barrier,
issuance of the standard UXO warning (see Condition 4.2) may suffice while the structure, stockpile or barrier
remains in place. Where a structure is to be removed or reduced as part of the development program, protective
precautions, commensurate with any greater risk to which workers might then be exposed, may need to be
considered. Progressive assessment will be necessary where such circumstances exist. Unless, at the
completion of preliminary works, there is evidence then available to the UXO contractor that any residual risk is
negligible, the use of detection equipment will typically be required to confirm the site’s status.

Where investigation, along with any subsequent remedial action and assessment, is to be implemented by stages
to satisfy Condition 4.1 and 4.3, a preliminary investigation report should be submitted by the applicant to the
EPA along with a management plan for the proposed work. Staged investigation/remediation is most likely to be
applicable where development of smaller, built-on lots (which can present circumstances such as those discussed
above) or broadhectare sites is proposed. In such cases, the EPA’s assessment of the report and advice to Council
in regard to approval of the development will be dependent on agreement with the management plan.




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 12

NOOSA COUNCIL IDAS Development Application Decision Notice                                                 12 of 15


Where Condition 4.1 is to be satisfied by a whole lot or broadhectare development stage being subjected to
investigation and any necessary remedial action, the EPA, based on the subsequent investigation/remediation
report’s findings and recommendation/s, may reassess the lot, or that portion comprising the development stage, as
being remediated or not needing remediation, and advise the applicant and Council accordingly. Otherwise, any
balance of land that has not been further investigated will retain the risk assessment made by Defence. This is
unless evidence obtained from the investigated part/s can be used to refute Defence’s assessment in regard to all or
part of the balance. In the latter case, the EPA may reassess all of the balance or the applicable part/s as being
unaffected by UXO.

6      Additional information
This concurrence response applies only to contaminated land issues and does not remove the need to obtain
any further approval for this development which may be required by this or other legislation, State and/or
Commonwealth. Applicants are advised to check with all relevant statutory authorities. Applicants should also
comply with all relevant legislation.

The EPA has not provided a notification to native title parties for this application. The State’s Native Title Work
Procedures indicate that the responsibility for assessment of native title issues for an IDAS application rests with
the Assessment Manager. It is recommended that the Assessment Manager determines whether native title
notification is required for this application.

                                                *End of response*
IDAS C-6 CLM




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 13

NOOSA COUNCIL IDAS Development Application Decision Notice                                               13 of 15



                                     Local Laws, Policies & State
                                     Regulation Requirements
                                     INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION


     THE FOLLOWING ADVICES ARE FOR INFORMATION PURPOSES ONLY AND DO NOT FORM
                             CONDITIONS OF APPROVAL

1.      The applicant is advised that development contributions and infrastructure charges applicable to this
        development approval have been based on the following Uses Class/ Uses and applicable quantities:-

                  Existing Development                                  Approved Development
        Existing Use Class /
                                  Existing Quantity       Approved Use Class / Use          Approved Quantity
                Use
                                                       Multiple Housing - Type 2 –
        Detached House           1 Dwelling                                               2 x 3 Bedroom Units
                                                       Duplex

2.      The applicant is informed that approval of this development application will trigger an Infrastructure
        Charge in accordance with the Coastal Major Road Network Infrastructure Charges Plan for the estimated
        amount of $1,017 and is subject to variations in the Consumer Price Index, All Groups Brisbane from
        December 2006 until the date of payment. An Infrastructure Charge Notice will be issued in accordance
        with Chapter 5 of the Integrated Planning Act 1997.

3.      The applicant is informed that payment via credit card transaction will not be an acceptable method of
        payment for development contributions conditioned in this permit or for infrastructure charge notices
        issued separately.

4.      The applicant is advised that a Compliance Permit for all plumbing and drainage works within the
        boundaries of the development site shall be obtained from Council’s Plumbing Services Section prior to
        obtaining a Development Permit for Building Works.

5.      Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if the cost of
        operational works exceeds $80,000, then a portable long service leave levy is required to be paid. In
        accordance with Section 77.(1) of the Act, Council is required to sight the approved form issued by the
        Building and Construction Industry (Portable Long Service Leave) Authority that confirms that the
        requirements of the Act have been satisfied. A statutory declaration outlining the cost of the operational
        works must be submitted to Council with the lodgement of any application for operational works over the
        site.

6.      The development should be undertaken and operated in a manner that causes no detrimental effect upon
        the amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
        hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions in accordance
        with the nuisance provisions of the Environmental Protection Regulation 1998 or Council’s Local Law No.
        12 – Control of Nuisances.

7.      In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud, paint, cement,
        concrete, builder’s waste or rubbish should not be permitted to enter or be placed where it could
        reasonably be expected to move into a roadside gutter, storm water drain or a watercourse. On the spot
        fines apply for such offences.




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 14

NOOSA COUNCIL IDAS Development Application Decision Notice                                                        14 of 15



                                                    Appeal Rights
                                                    INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION

   The following is an extract from the Integrated                           (6) If an application involves assessment against
   Planning Act (Chapter 4).                                              a concurrence agency code, appeal rights for
                                                                          submitters for the application are not available
   Division 8 - Appeals to                   court      relating     to   against the part of the approval that represents the
   development applications                                               concurrence agency’s response for the code.
   Appeals by applicants                                                  Appeals by advice agency submitters
   4.1.27.(1) An applicant for a development application                  4.1.29.(1) An advice agency may, within the limits of
   may appeal to the court against any of the following-                  its jurisdiction, appeal to the court about the giving of
   (a) the refusal, or the refusal                 in   part,   of   a    a development approval for a development
       development application;                                           application if-

   (b) a matter stated in a development approval,                         (a) the development application involves impact
       including any condition applying to the                                assessment; and
       development, and the identification of a code                      (b) the advice agency told the applicant and the
                            1
       under section 3.1.6;                                                   assessment manager to treat its response to the
   (c) the decision to give a preliminary approval when a                     application as a submission for an appeal.
       development permit was applied for;                                   (2) The appeal must be started within 20 business
   (d) the length of a currency period;                                   days after the day the decision notice or negotiated
                                                                          decision notice is given to the advice agency as a
   (e) a deemed refusal.                                                  submitter.
      (2) An appeal under subsection (1)(a) to (d) must                   Appeals for matters arising after approval given
   be started within 20 business days (the “applicant’s                   (co-respondents)
   appeal period”) after the day the decision notice or
   negotiated decision notice is given to the applicant.                  4.1.30.(1) For a development approval given for a
                                                                          development application, a person to whom any of
       (3) An appeal under subsection (1)(e) may be                       the following notices have been given may appeal to
   started at any time after the last day a decision on the               the court against the decision in the notice-
   matter should have been made.
                                                                          (a) a notice giving a decision on a request for
   Appeals by submitters                                                      extension of the currency period for an approval;
   4.1.28.(1) A submitter for a development application                   (b) a notice giving a decision on a request to make a
   may appeal to the court about-                                             minor change to an approval.
   (a) the giving of a development approval, including                        (2) The appeal must be started within 20 business
       any conditions (or lack of conditions) or other                    days after the day the notice of the decision is given
       provisions of the approval; or                                     to the person.
   (b) the length of a currency period for the approval.                        (3) Subsection (1)(a) does not apply if the
                                                                          approval resulted from a development application
       (2) The appeal must be started within 20 business                  (superseded planning scheme) that was assessed as
   days (the “submitters appeal period”) after the day                    if it were an application under a superseded planning
   the decision notice or negotiated decision notice is                   scheme.
   given to the submitter.
                                                                             (4) Also, a person who has made a request
      (3) If a person withdraws a submission before the                   mentioned in subsection (1) may appeal to the court
   application is decided, the person may not appeal the                  against a deemed refusal of the request.
   decision.
                                                                              (5) An appeal under subsection (4) may be
      (4) If an application involves both impact                          started at any time after the last day the decision on
   assessment and code assessment, appeal rights for                      the matter should have been made.
   submitters are available only for the part of the
   application involving impact assessment.                               Division 9 - Appeals to court about other matters
       (5) If an application is processed under section                   Appeals for matters arising after approval given
   6.1.28(2), appeal rights for submitters for the                        (no co-respondents)
   application are available only for the aspects of the
   development that would have required public                            4.1.31.(1) A person to whom any of the following
   notification under the repealed Act.                                   notices have been given may appeal to the court
                                                                          against the decision in the notice-
                                                                          (a) a notice giving a decision on a request to change
                                                                              or cancel a condition of a development approval.
   1
        Section 3.1.6 (Preliminary approval may override local planning
       instrument)



A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Page 15

NOOSA COUNCIL IDAS Development Application Decision Notice                                      15 of 15

                                      2
(b) a notice under section 6.1.44 giving a decision to
    change or cancel a condition of a development
    approval.
    (2) The appeal must be started within 20 business
days after the day the notice of the decision is given
to the person.
   (3) Also, a person who has made a request
mentioned in subsection (1)(a) may appeal to the
court against a deemed refusal of the request.
    (4) An appeal under subsection (3) may be
started at any time after the last day the decision on
the matter should have been made.
Appeals against decisions to change approval
conditions under the repealed Act
4.1.33A.(1) A person who is dissatisfied with a
decision made on an application to change the
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act may
appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
    (2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of
the decision is to be given to the person.
    (3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on the
matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions
applied under a local law about the use of premises
or the erection of a building or other structure
permitted by the planning scheme may appeal to the
court against the decision or the conditions applied.
    (2) The appeal must be started within 20 business
days after the day notice of the decision is given to
the applicant.




2
     Section 6.1.44 (Conditions may be changed or cancelled by
    assessment manager or concurrence agency in certain
    circumstances)




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]

Used in these records

About this file

File size
83 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2005.00002302.001 [As Published].pdf · 83 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.