Frontage Works
29. Footpath improvements such as topsoiling, grassing, and tree planting are required to the Ventura Street
and Orealla Crescent frontages of the site in accordance with Planning Scheme Policy PSP03
Landscaping Plants & Guidelines. Grass shall be couch, free of weeds.
30. All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel, footpath
paving and landscaping such as trees and grasses in accordance with Council’s Standard specifications
prior to commencement of the use permitted by this permit.
Pathway Trunk Network Contributions
31. A pathway trunk network contribution of $656 towards external major pathways, in accordance with
Planning Scheme Policy PSP20 Pathway Trunk Network Contributions, shall be paid to the Council prior
to obtaining a Development Permit for Operational Works. This amount will be subject to variations in the
Consumer Price Index, All Groups Brisbane from December 2006 until the date of payment.
Stormwater Drainage
32. All stormwater drainage shall be collected on site and discharged so there is no net increase in
stormwater runoff from the site. Stormwater drainage permitted to drain from the site shall be discharged
to Council’s existing drainage structures in Ventura Street. Plans of the drainage design shall be
prepared by a Registered Professional Civil Engineer and submitted to Council prior to obtaining a
Development Permit for Operational Works.
33. A survey plan of the existing Council infrastructure in Ventura Street shall be submitted to Council as part
of any application for a Development Permit for Operational Works. The plan shall be prepared by a
Licensed Surveyor and shall indicate the property boundaries and the surveyed location and levels of the
existing sewer main, kerb and channel and stormwater pits.
34. The stormwater drainage system shall be designed in accordance with Council’s Planning Scheme Policy
PSP5 Engineering Design Standards – Roads, Drainage and Earthworks and Planning Scheme Policy
PSP6 Engineering Design Standards – Water and Sewerage. The stormwater drainage system shall be
designed to ensure that clearances, both horizontal and vertical, are achieved to any existing service
infrastructure.
35. The stormwater drainage system for the access driveway and carparking area shall be designed to cater
for a Q100 storm event.
36. Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank (minimum
storage 3000 litres per dwelling/unit) that is installed to ensure water from the tank can be used for
external uses (such as watering gardens, irrigation, ornamental ponds, water features, topping-up
swimming pools, outdoor cleaning, etc) and for use in flushing of toilets internal to the dwelling. All
rainwater tanks are to be designed and installed in accordance with the Queensland Development Code
(QDC), Part 25 – Rainwater Tanks, and shall be part of the plumbing application in conjunction with the
building approval. The location and capacity of the tanks shall be clearly shown on the plans submitted
for Operational Works and Building Works approval and any overflow shall be directed to the stormwater
drainage system.
37. To ensure that polluted run-off does not enter Council’s stormwater drainage system, stormwater run-off
from the carparking areas and the driveways shall have the first flush (the first 12 mm of rainfall or hose-
down) collected in a grease/oil arrestor/gross pollutant trap provided on site prior to being permitted to
discharge into Council’s drainage system.
All other clean stormwater, such as roof water, can be collected on site and discharged through a single
underground drain line directly into the existing drainage system, bypassing the grease/oil arrestor/gross
pollutant trap.
To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil arrestors/gross
pollutant trap, which shall be submitted to the Council for approval prior to obtaining a Development
Permit for Operational Works.
The approved maintenance plan shall be incorporated in to the ongoing Maintenance Scheme for the
development and a copy of this shall be provided for Council’s records prior to commencement of the
approved Use.
A Development Permit for Building Works shall not be granted until a Development Permit for Operational
Works has been issued in regard to the drainage scheme.
38. All site stormwater drainage shall be by means of a gravity system and shall not include mechanical
pumps.
A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@d807e1ca\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2005.00002302.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 83 KB (small file)
- File type
No other editions are linked here.