MCU14/0106 & OPW15/0001 Town Planning Report & Appendix A Code Compliance
Original PDF page 153, section 1. The text section number identifies this passage in the reader.
Town Planning Report
28 Eenie Creek Road, Noosaville and parts of the road reserves of Hofmann Drive and Walter Hay Drive
A9 – Earthworks Code
The below code response has been prepared by Cardno HRP and Cardno Engineering. In addition to the Town Planning Report, reference should be made to the
Engineering Report (Appendix E) in reading this code response.
Table 14-52 – Earthworks
Specific Outcome Probable Solution Response
14.120 Effects of works
Drainage
O1 Finished surface levels ensure land is free S1.1 The finished surface gradient of any filled or excavated area R1.1 Complies
draining. is within the range 0.5% to 1.5% and drains to Council’s To ensure finished surface levels are free draining earthworks will be
stormwater infrastructure where available or where carried out in accordance with the Earthworks Grading Plan J13041-
stormwater infrastructure is not available, toward the street. CI-C03 in Appendix E of the Engineering Report (Appendix E to the
Town Planning Report).
Hydraulics
O2 Any change to the level of the land does not No solution provided. R2 Alternative Solution (as no Probable Solution is provided)
have an adverse flooding impact on the Proposed changes to existing ground levels will not impact on
flooding and drainage characteristics off- existing overland flow or flood storage characteristics.
site.
Refer to Appendix E – Engineering Report
Geotechnical considerations
O3 Earthworks do not result in geotechnical S3.1 Filling works are undertaken in accordance with Section 2.8- R3.1 Will Comply
instability on the premises or nearby Filling of Site of Council’s PSP5 - Engineering Design Refer Section 6.1.3 in Appendix A (Geotechnical Report) of the
premises. Standards- Roads and Drainage & Earthworks Engineering Report (Appendix E to the Town Planning Report).
AND
S3.2 Where the filling is for residential commercial or industrial R3.2 Will Comply
purposes the works comply with Sections 3 to 6 of AS 3798 - Refer Section 6.1.3 in Appendix A (Geotechnical Report) of the
Guidelines for earthworks on commercial & residential Engineering Report (Appendix E to the Town Planning Report).
development.
Local amenity
O4 Earthworks do not cause disturbance to the S4.1 The following control measures are implemented— R4.1 Will Comply
amenity of the neighbouring land. a) regular water spraying of exposed areas to suppress dust; Refer to measures detailed in Section 6, Appendix B (Construction
b) provision of dust stabilised or sealed internal roads; EMP) and Appendix C (Erosion and Sediment Control Plan) of the
Engineering Report (Appendix E to the Town Planning Report).
c) protective covering of exposed areas that are left for more
than 2 weeks; and
d) if there is no valid development permit for the site,
disturbed areas are revegetated using species identified in
PSP3 - Landscaping Plants and Guidelines;
AND
December 2014 Cardno HRP A72
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.