Stormwater Treatment & Water Quality Management Plan_April2014
Attached to the e-mail REC13/0146 - Response to Information Request - Email 2.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn4.0 STORMWATER DISCHARGES TO No 2 PEARSONS ROAD A catchment area of 2.49 hectares presently drains across the northern boundary of the site and onto No 2 Pearsons Road, as shown for the pre-development scenario in Figure 3. Local stormwater discharges onto the adjoining property will be maintained at or below their existing rates by diverting part of the runoff from the relevant catchment, directly across to the western tributary floodway within the site, as shown for the post-development scenario in Figure 3. The existing discharge rates to the adjoining property, as calculated by the Rational Method for the partial-area of 2.43 hectares shown in Figure 3, are summarised in Table 4 below: Table 4: Rational Method Calculations Of Pre-Development Peak Flow Rates To No 2 Pearson Road C10 Tc I (mm/hr) A Q (m3/s) (min) 1 / 2 / 5 / 10 / 20 / 50 / 100 (Ha) 1 / 2 / 5 / 10 / 20 / 50 / 100 0.72 24 65 / 73 / 98 / 116 / 130 / 152 / 166 2.43 0.25 / 0.30 / 0.45 / 0.56 / 0.66 / 0.85 / 0.97 In the post-development scenario, runoff from the 2.40 hectare post-development catchment (excluding a 0.018 hectare drainage corridor connecting to the adjoining property) will be collected at the sag in the proposed road, from which flows up to Q5 will be diverted eastward by piping along the road, to the western tributary channel. Flows in excess of Q5 at the sag will discharge overland, through the abovementioned drainage corridor, to the adjoining property. The Q5 diversion capacity, as calculated by the Rational Method for a partial area of 2.25 hectares, is summarised in Table 5, below: Table 5: Rational Method Calculation Of Q5 Diversion Capacity C10 Tc (min) I5 (mm/hr) A (Ha) Q5 (m3/s) 0.78 18 112 2.25 0.00278 x (0.95 x 0.78) x 112 x 2.25 = 0.52 The post-development discharge rates to the adjoining property up to Q5, being just the runoff from the surface of the connecting drainage corridor, are calculated by the Rational Method as in Table 6 below. These flow rates are all practically zero. Table 6: Rational Method Calculations Of Post-Development Flows Up To Q5 To No 2 Pearson Road C10 Tc I (mm/hr) A Q (m3/s) (min) 1 / 2 / 5 (Ha) 1 / 2 / 5 0.90 10 97 / 109 / 147 0.018 0.003 / 0.004 / 0.006 The post-development discharge rates to the adjoining property from Q10 to Q100, as calculated by the Rational Method for the partial area of 2.30 hectares shown in Figure 3, are summarised in Table 7, below: Table 7: Rational Method Calculations Of Post-Development Flows Q10 - Q100 To No 2 Pearson Road C10 Tc I (mm/hr) A Q (m3/s) (min) 10 / 20 / 50 / 100 (Ha) 10 / 20 / 50 / 100 0.78 18 132 / 151 / 172 / 192 2.30 0.66 / 0.79 / 1.00 / 1.15 Less 0.52 m3/s Q5, = 0.14 / 0.27 / 0.48 / 0.63 Brisbane Stormwater Management Pty Ltd Document File: ValkevSDF.Doc Page 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.