20230025_RECOR_MCU Engineers Letter_20.12.24
• Item 37 to 39 – Upon review, there is a none net worsening of site conditions in
regards for potential flooding when comparing existing to the new development
finished ground levels. All surface drainage is directed towards new on site drainage
pits connected to the existing stormwater system and or overland flow is directed to
existing kerb and channels.
• Item 40 and 41 – The drawings have been revised to include an updated
earthworks layout.
Trusting the above is to your satisfaction and should further information be required please
contact this office.
Yours faithfully,
RECOR Pty Ltd
Signature
Blake Wetherall
Structural Engineer
BEng (Hons)
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads Qld 4567 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.