5.0 Service Provisions
5.1    Potable Water & Sewer
A new potable water main along with a new sewer main and property service will be provided to the lot
within the future adjacent road reserve by the surrounding subdivision. As such the existing service
shall be utilised by the development.

5.2    Communications & Electrical
Details of electrical supply and communication infrastructure and services proposed for the
development site are outside the scope of this report. However, we understand that supply to the
development can be provided via an extension to the adjacent underground electricity network.



6.0 Conclusion
This Engineering Services Report has been prepared to provide a review and information on the
Engineering requirements to support the application for OPW on the proposed development at 62 Lake
MacDonald Drive, Cooroy (Lot 105 on SP118458). The following requirements have been reviewed
as part of this report:
•   Suitable access can be provided off the future subdivision road;
•   Minimum site distance can be achieved by the development;
•   A total of 31 parking spaces shall be provided;
•   The development can be servied by a WCV;
•   The site is not impacted by flooding or significant external catchments;
•   The surrounding subdivision is providing stormwater quality management;
•   On-site detention shall be provided to cater for stormwater quantity management;
•   Sewerage reticulation can be connected to the future Unitywater network; and
•   Water reticulation can be connected to the future Unitywater network.
In summary, this report shows that the development site can be adequately serviced and provision
made as currently shown and in further detailed design for this development to be in accordance with
Council's code requirements.




12 May 2026

Log in to download the original (Stormwater Management Plan 12_05_26.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.