Stormwater Management Plan 12_05_26
Original PDF page 9, section 1. The text section number identifies this passage in the reader.
ABN 51 640 311 842
CONTACT
arcosgroup.com.au
OFFICES
Sunshine Coast | Brisbane | Gold Coast
TABLE 3: MODEL LOSS PARAMATERS
Surface Type ARR Data Hub ARR Data Hub Adopted IL(mm) Adopted CL
IL (mm) CL (mm/h) (mm/h)
Impervious - - 1 0
Pervious 32 2.6 25 2.6
The DRAINS model layout is for the existing, developed, and mitigated case is shown in Figure 3
FIGURE 3: DRAINS MODEL LAYOUT
4.5.4 Existing & Developed Case Summary
DRAINS modelling was undertaken, peak flow summary of the existing case and developed case for
the site are shown in the following Table 4. The peak discharges were estimated using all storm
ensembles across 5-minute to 360-minute durations.
TABLE 4: DRAINS PEAK FLOWS
Storm Event Existing Case Developed Case Difference Difference
(AEP) (m3/s) (m3/s) (m3/s) (%)
63% 0.041 0.073 0.032 78.0%
39% 0.063 0.091 0.028 44.4%
18% 0.092 0.119 0.027 29.3%
10% 0.110 0.139 0.029 26.4%
5% 0.134 0.171 0.037 27.6%
2% 0.154 0.199 0.045 29.2%
1% 0.174 0.227 0.053 30.5%
1% (CC) 0.218 0.283 0.065 29.8%
12 May 2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Stormwater Management Plan 12_05_26.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.