MCU14/0106 Appendix G - Covenant Interface Management Plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnCovenant Interface Management Plan
Noosa Civic Expansion
3 Covenant J Interface Management Measures
3.1 Element 1 – Weed Establishment
Target Weed species detrimental to the health of existing vegetation do not
establish in the Covenant J area.
Actions / Tasks No litter dumping within Covenant J; and
only local native species are used in landscapes in covenant interface
areas.
Performance Indicators Covenant J is free from declared Class 1 and Class 2 weed species under
the Land Protection (Pest and Stock Route Management) Act 2002 and
those listed as ‘Broad control’ under the Sunshine Coast Pest
Management Plan 2012-2016.
Monitoring and Review Annual inspection or assessed on an as needs basis.
Corrective Actions If monitoring indicates the presence of weed infestations and litter dumping the
following corrective actions will be triggered:
undertake weed removal within 6 weeks of the corrective action being
triggered.
Responsibilities QIC Noosa Civic Pty Ltd will be responsible for the implementation of this
element.
3.2 Element 2 – Native Vegetation Retention
Target Native vegetation is retained and protected within Covenant J as stated
in the Covenant conditions or as approved by negotiation with Council.
Actions / Tasks Conditions of covenant are adhered to.
Performance Indicators The overall integrity of vegetation within the covenant is maintained; and
there is no net loss of native vegetation in the covenant.
Monitoring and Review Annual inspection or assessed on an as needs basis.
Corrective Actions If monitoring indicates the removal of native vegetation the following corrective
actions will be triggered:
replacement planting with like for like species within 6 weeks of damage.
Responsibilities QIC Noosa Civic Pty Ltd will be responsible for the implementation of this
element.
3.3 Element 3 – Bushfire
Target No fires in the Covenant J area.
Actions / Tasks Exclude fire from Covenant J to facilitate transition to lower risk rainforest
vegetation.
Performance Indicators Operation is to be consistent with Bushfire Management Plan.
Monitoring and Review Prompted by unplanned fire events.
Corrective Actions Facilitate and monitor growth of vegetation following unplanned fires.
Responsibilities QIC Noosa Civic Pty Ltd will be responsible for the implementation of this
element.
QIC Noosa Civic Pty Ltd Version 1 9 December 2014
Covenant Interface Management Plan_V1.docx Commercial in Confidence Page 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.