Delegated Report - Code - Planning RAL26 0001 (As Published)
6. Certification must be submitted to Council from all relevant service providers (Energex, NBN)
which certifies that the development has met the requirements of this Decision Notice and
all applicable legislation at the time of construction.
7. Prior to Council signing the Plan of Survey, landscaping must be established along the full
eastern side of the access easement shown on the Approved Plans. The landscaping must
comprise Syzygium australe planted at 1.0 metre centres, with each plant being a minimum
1.0 metre in height and supplied in a minimum 200mm pot size at the time of planting. The
landscaping must be maintained in a healthy condition and any dead, damaged or diseased
plants must be replaced.
ENGINEERING
Property Access and Driveways
8. A residential driveway must be constructed to service Lots 1 and 2. The works must be
undertaken in accordance with an Operational Works approval and be generally in
accordance with Auxilium Consulting’s Operational Control Layout Plan (C902, Rev. B) dated
20 July 2026.
Stormwater Drainage
9. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with the Queensland Urban
Drainage Manual and be generally in accordance with Auxilium Consulting’s Stormwater
Management Report (Rev. 3) dated 21 July 2026.
10. Prior to Council signing the Plan of Survey, certification from a suitably qualified person
(RPEQ) must be provided to Council certifying that proposed Lots 1 and 2 have been
provided with a Lawful Point of Discharge pursuant to sections 3.6 and 3.9 of the Queensland
Urban Drainage Manual in a manner that does not substantially damaging a third-party
property.
Services
11. Reticulated electricity and telecommunication services must be provided to each lot in
accordance with the standards and requirements of the relevant service provider.
12. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
13. Certification must be submitted to Council from all relevant service providers (Energex, NBN
and Unitywater) which certifies that the development has met the requirements of this
Decision Notice and all applicable legislation at the time of construction.
Easements
14. A 4.5-metre-wide easement for the purpose of access and services must be registered
against the titles of the properties in favour of proposed Lot 2 over the proposed easement
identified on the Approved Plans.
15. Unless otherwise agreed in writing by the relevant service provider, any public or third-party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
16. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
17. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Page 8 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Delegated Report - Code - Planning RAL26 0001 (As Published).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.