                The Clearing Contractor is responsible for conducting vegetation clearing in accordance
                with this management plan
                The Site Superintendent is responsible for dealing with Contractor compliance with what
                is required and reporting back to the Superintendent.
                The Fauna Spotter Catcher / Ecologist is responsible for
                      • Undertaking a pre-clearance survey, safely capturing fauna and releasing fauna
                          into suitable habitat and under suitable conditions.
                      • Maintaining detailed records of fauna interactions and fauna habitats cleared,
                          and preparing reports
                All personnel are responsible for upholding animal welfare by preventing and / or
                minimizing the risk of distress, injury, illness, orphanage, predation or death of fauna.
Reporting and   The Fauna Spotter Catcher / Ecologist is responsible for
Auditing             • Providing Stockwell Design and Construction with a pre-clearance survey
                         report, detailing how any additional habitat features will be managed
                     • Reporting on the number of hollows, hollow recruitment trees and arboreal
                         termitaries lost as a result of clearing works
                     • A post-clearance report is to be handed to the contractor on the clearing of any
                         native vegetation, including any fauna found and or relocated, and the details of
                         all habitat features removed during works
                     • Each day of native clearing vegetation is completed a log is to be completed by
                         the Contractor before or on the completion of the day. Audit of the key
                         requirements like the clearing within the limits, the presence of the fauna spotter
                         catcher, the absence of damage to vegetation in the surrounding area.
Corrective           • In the event where monitoring practice are inconsistent with the strategies for the
Action                   management plan the Contractor should take the corrective steps and write them
                         down in a monthly report to be looked at by the Site Superintendent.
Timing               • The duration of the construction period




FAUNA MANAGEMENT PLAN | Stockwell Design and Construction                                                11
Log in to download the original file

PR0587 Stockwell Medihub FMP 20230209 - signed.pdf · 2.1 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.