ORDINARY MEETING MINUTES 4 JUNE 2015
c. details of the UPSS design and installation details (tank sizes, contents,
location of all relevant infrastructure)
d. list of industry standards complied with for the design, installation and
operation of the system
e. plans of the system and site
f. leak prevention measures
g. loss monitoring procedures
h. system maintenance procedures
i. emergency spillage response plan
j. loss investigation and notification procedures
k. record keeping
l. training requirements and records
m. information on ownership and occupation of both the site and the UPSS,
including specific contractual/franchise arrangements, defined
responsibilities and relevant contact details
n. procedures for the immediate rectification and remediation of any
detected contamination
The safety management plan must be fully documented and made
available onsite at the service station. The plan must be submitted to
council prior to use of the service station. All testing and monitoring
results must be documented accordingly and provided to Council upon
request.
69. An Emergency Spillage Response Plan for spilt fuels and other hazardous
materials must be developed as part of the Safety Management Plan and
implemented at the service station. The plan will establish procedures to
respond to identified hazards and to contain and dispose of spilt chemicals. All
spilt materials must be contained to prevent the spread of the material, the
affected area cleaned, and the material recycled, reused or disposed of in a
manner that prevents contamination or further contamination of the ground
surface, ground waters or soil. The plan must include but not be limited to the
following matters:
a. all actions to be taken by staff upon discovery of an incident
b. activation of emergency shut-off systems
c. use of spill clean-up kits
d. covering of drain entrances and bunding of impacted waterways
e. notification of emergency services where necessary
f. an accurate set of drainage plans which identify all containment and
treatment systems and all potential points of access to Council
stormwater infrastructure. Drainage plans must clearly trace the flow of
any potential spillage and shall identify the location of the outlet point (e.g.
creek, river, etc). A copy of the drainage plan must be placed in the two
(2) HAZMAT boxes for the use of emergency responders
g. a flow chart providing an overview of actions to be taken in the event of a
spill must be prepared and posted in a clearly visible location. It must
include a list of emergency telephone numbers
This is not an official copy of Council’s Minutes
Page 12 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.