Section 4.4
4.4 Residual Risks
The LDMG recognises its treatment options will not always be adequate and residual risk will remain. Residual
risks are the risks which remain after the LDMG has applied the risk mitigation strategies within their capacity,
but those strategies have not sufficiently reduced or eliminated the risk.
The following is a list of identified risks identified using the QERMF methodology that are not within the
capacity of the LDMG to address and are therefore deemed to be Residual Risks to be escalated to the
DDMG.
Table 6: Summary of Residual Risks for Noosa Shire
Issue Current Capacity Residual Risk Can Council
assist?
Evacuation of entire Limited capacity exists to Request to District Limited
community evacuate the whole for assistance
community.
Multiple houses There is a risk that emergency Request to District Limited
damaged especially services response to any for assistance
those involving multi- disaster event will be severely
casualty scenarios compromised as a result of
insufficient response capacity.
Asbestos contamination The community has limited Request to District Limited
from damaged buildings personnel trained in or for assistance
equipped for asbestos
removal. External expertise will
be required.
Managing multiple Limited capacity exists to Request to District Limited
Evacuation Centre manage and staff evacuation for Assistance
Facilities centre facilities.
Various Public Health The community has a small Request to District Limited
Risks team of EHO’s. In a major for assistance
event, professional EHO
assistance will be required for
a range of public
health/environmental health
issues.
Significant Terrorist While Queensland Police Request to District Limited
Attack or other Attack on would escalate through their (and likely further
the State own channels, the requirement to the State) for
for community support and assistance
recovery resources could be
large.
Noosa Council 2025 | Local Disaster Management Plan Page 45 of 73
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.