Council archive · source document
Minor Change Existing Approval REC14/0005.05 {As Published}
(b) Modification of the existing pavement marking to extend the channelised right turn lane
(CHR).
(c) Extension of the existing yellow line marking “No Stopping” zone.
(d) Construction of a pedestrian footpath in accordance with the conditions of this Decision
Notice.
Condition 7 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Pedestrian and Bicycle Facilities
8. Pedestrian and bicycle facilities must be provided for the development. The works must be
undertaken in accordance with an Operational Works approval and must include in particular:
(a) A two metre wide concrete footpath within the road verge for the entire length of the
site’s frontage to Gateway Drive and connecting to the existing path fronting Lot 11
SP170295.
Condition 8 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Stormwater Drainage
9. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with an Operational Works
approval, AS3500.3 and the Queensland Urban Drainage Manual, and must include in
particular:
(a) Collection and discharge of stormwater to Council’s underground pipe network in
Gateway Drive
(b) Extension of the site stormwater system to accommodate stormwater from the external
catchment East of the site, including registration of drainage easements over the pipe
network within the subject site in favour of the upstream lot.
(c) The retention of the existing overland flowpath that conveys stormwater runoff from the
adjoining property (Lot 26 SP151406) through proposed Lot 103. The flows must be
contained and conveyed wholly within a 600mm dia. underground pipe at minimum 2%
grade, constructed along the southern boundary of proposed lot 103.
(d) Cut off drains along the Eastern site boundary to convey external catchment flows up
to the 1%AEP climate change event into the pipe network within the site.
9a. Carry out the development to ensure that adjoining properties, reserves and roads are
protected from ponding or nuisance from stormwater as a result of any works undertaken
Electricity and Telecommunication Services
10. Underground reticulated electricity and telecommunication services must be provided to
each lot in accordance with an approval for Operational Works and the standards and
requirements of the relevant service provider.
11. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
12. Certification must be submitted to Council from all relevant service providers which certifies
that the development has met the requirements of this Decision Notice and all applicable
legislation at the time of construction.
Easements
13. A drainage easement must be created within proposed Lot 103. The easement must be:
Page 3 of 8
Document Set ID: 23331643
Version: 4, Version Date: 04/11/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval REC14/0005.05 {As Published}Related documentApplication case desk ↗
About this file
- File size
- 199 KB (small file)
- File type
No other editions are linked here.