Decision Notice - Approved by Delegation of Authority MCU21 0191

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Officer: 	Lisa Pienaar
Direct Telephone: 	07 53296514
Our Reference:	MCU21/0191
Your Reference:	2021-23
17 August 2022
LR Shannon & AJ Casson
C/- Danya Cook Town Planning
PO Box 9410
PACIFIC PARADISE QLD 4564
[email protected]
Dear Sir/Madam,
Decision Notice
Planning Act 2016
I refer to your application and advise that on 15 August 2022, Council decided to approve the application, subject to conditions.
Details of the decision are as follows:
application details
Application No:	MCU21/0191
Street address:	Illawarra Court 17 Henderson St Sunshine Beach Qld 4567
Real property description:	BUP 3585, Lot 1 BUP 3585, Lot 2 BUP 3585, Lot 3 BUP 3585, Lot 4 BUP 3585
Planning Scheme:	Noosa Plan 2020 (25 September 2020)
Decision details
Council decided to issue the following type of approval:
Development Permit for Material Change of Use - Multiple dwelling (Additional Dwelling Unit)
CURRENCY PERIOD of approval
The currency period for this development approval is stated in the conditions below.
assessment manager conditions
PLANNING
When Conditions must be Complied With
Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues.
Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
1.2	E	Site Plan, prepared by M Design	11.08.2022
2.1	E	Level A – Proposed, prepared by M Design	11.08.2022
2.2	E	Level B – Proposed, prepared by M Design	11.08.2022
2.3	E	Level C – Proposed, prepared by M Design (as annotated by Council)	11.08.2022
2.4	D	Level D – Proposed, prepared by M Design	11.08.2022
2.5	E	Level E – Proposed, prepared by M Design	11.08.2022
2.6	E	Roof Plan – Proposed, prepared by M Design	11.08.2022
2.8	E	Gross Floor Area, prepared by M Design	11.08.2022
2.9	E	Landscape Plan, prepared by M Design	11.08.2022
4.1	E	Elevations, prepared by M Design	11.08.2022
4.2	E	Elevations, prepared by M Design	11.08.2022
4.3	E	Elevations, prepared by M Design	11.08.2022
4.4	E	Elevations, prepared by M Design	11.08.2022
5.1	E	Sections, prepared by M Design	11.08.2022
10.1	E	3D Views, prepared by M Design	11.08.2022
10.2	E	3D Views, prepared by M Design	11.08.2022
10.3	E	3D Views, prepared by M Design	11.08.2022
10.4	E	3D Views, prepared by M Design	11.08.2022
Nature and Extent of Approved Use
This approval relates to the provision of additional Unit 5.
Currency Period
This development approval lapses if the use has not happened by 15 August 2028, unless an application to extend the currency period is approved by Council.
Building Height
The maximum height of the development must not exceed 12 metres above the finished ground level and the natural ground level.
Certification must be submitted to Council from a Licensed Surveyor which certifies that the building does not exceed the maximum height requirement of this Decision Notice.
Performance Bond
Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must be submitted to Council, to secure performance of all conditions of this approval, prior to the issue of a Development Permit for Operational Works. The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions.
Building Appearance
All air conditioning units or other mechanical equipment must be located at ground level, or otherwise fully enclosed or screened such that they are not visible from the street frontages nor adjoining properties.
All deck and balcony areas above ground floor must not be enclosed by permanent fixtures such as shutters, louvres, glass panelling or the like, except where required to satisfy any privacy condition of this Decision Notice.
The upper level balcony located on Level E must include either balcony planter boxes, balustrading or fixed external screens, positioned in such a way to obscure direct views into the habitable room windows or private open space areas of the adjoining property.
Landscaping
A minimum of 20% of the site must be retained as soft landscaping.
Existing native vegetation on the site must be retained, particularly along the northern boundary except where required to be removed to accommodate the pool.
Existing vegetation in the road reserve must be retained, unless written authorisation from Council is granted for the clearing.
Landscaping works must be undertaken in accordance with an Operational Works approval and in accordance with Planning Scheme Policy PSP 2 – Landscaping and generally in accordance with Drawing no. 2.9 – Landscape Plan and include in particular:
Screening vegetation must be planted along the northern, southern and eastern boundary in accordance with the approved plan (exclusive of access and existing structures).  The planted vegetation must have a minimum pot size of 20 litres and consist of native, endemic species with a mature height of not less than 5 metres and approximate spacing of 1.5 metre centres.
Trees to be retained must be protected from construction activities by:
clearly marking vegetation to be retained with flagging tape
installing protective fencing around the drip line of the vegetation
restricting stockpiling, storage and vehicle parking to those areas which are already cleared
using low impact construction techniques around vegetation.
Damage to Services and Assets
Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times:
where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or
where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval.

ENGINEERING
Site Access and Driveways
The existing access driveway must be replaced with a new sealed access driveway extending from the road formation in Henderson Street to the parking and manoeuvring areas of the development. The works must be undertaken in accordance with an Operational Works approval and must include in particular a driveway crossover generally in accordance with Council’s Standard Drawing RS-051 together with any associated addendum
Car Parking
A minimum of 6 car (a minimum of 3 must be covered) and 2 motor cycle parking spaces must be provided and marked on the site and made available and accessible at all times. The works must be undertaken in accordance with an Operational Works approval and must include in particular:
a carparking layout generally in accordance with drawing number 2.1 revision E prepared by M design dated 11 August 2022, and
dimensions, crossfalls and gradients in accordance with Australian Standard AS/NZS2890.1:2004 - Parking Facilities.
All vehicles must enter and exit the site in a forward gear.
All car parking areas and access driveways must be maintained exclusively for vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
Stormwater Drainage
Stormwater runoff from the any new structures and the modified carparking area must be directed to the existing stormwater drainage system.
Services
Unless otherwise stipulated by telecommunications legislation at the time of construction, the development must be provided with all necessary conduits, pits and pipes to accommodate the future connection of optic fibre technology telecommunications.
Certification must be submitted to Council from all relevant service providers (Energex, NBN and Unitywater) which certifies that the development has met the requirements of this Decision Notice and all applicable legislation at the time of construction.
Geotechnical Stability
All development works must be carried out in accordance with a site specific Geotechnical Report (or part thereof) prepared by a qualified person* and endorsed through a Building Works approval.  *(Refer to advisory Note)
At the completion of the works certification must be submitted to Council from a qualified person* which certifies that the development has been constructed in accordance with the recommendations contained in the site specific geotechnical report and that the development has a minimum factor of safety against landslip of 1.5 in the long term.
*(Refer to advisory Note)
Earthworks and Retaining Walls
All earthworks associated retaining structures/batters, both above and below ground level, both temporary and permanent, must be contained entirely within the subject site unless written permission from the respective landowner(s) is provided to Council. All earthworks must be undertaken in accordance with the provisions of Australian Standard AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
referral agencies
Not applicable.
Advisory notes
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
Infrastructure Charges
All developments and/or changes to existing developments may require payment of “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution” made pursuant to the planning legislation and regulations current at the time of issue. For further information, please refer to https://www.noosa.qld.gov.au/planning-development/development-tools-guidelines/infrastructure-charges
Equitable Access and Facilities
The plans for the proposed building work have NOT been assessed for compliance with the requirements of the National Construction Code - Building Code of Australia (Volume 1) as they relate to people with disabilities.  Your attention is also directed to the fact that in addition to the requirements of the National Construction Code as they relate to people with disabilities, one or more of the following may impact on the proposed building work:
the Disability Discrimination Act 1992 (Commonwealth);
the Anti-Discrimination Act 1991 (Queensland); and
the Disability (Access to Premises – Buildings) Standards.
Building and Construction Industry (Portable Long Service Leave) Levy
The QLeave levy must be paid prior to the issue of a development permit where it is required. Council will not be able to issue a Decision Notice without receipt of details that the Levy has been paid.
Co-ordination of Operational Works Assessment
Additional application fees apply to Operational Work applications where the different aspects of the works are lodged separately. Significant savings in application fees will result if all works are lodged in a single application.
Qualified Person
For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability for the development, a qualified person is considered to be a person who:
is a Registered Professional Engineer of Queensland (RPEQ); and
has a degree in civil engineering or engineering geology; and
has a minimum of 5 years experience in the field of geotechnical engineering or engineering geology.
Preparation of a Preliminary Construction Management Plan
A preliminary Construction Management Plan must be submitted with the Operational Works application and must address the following:
appropriate traffic signage in accordance with the Manual of Uniform Traffic Control Devices (MUTCD)
provision for safe vehicle and pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased.
it is acknowledged that the preliminary Construction Management Plan will be a draft document requiring finalisation upon appointment of the Principal Contractor employed to construct the works and a final document will be required to be submitted at the Pre-Start Meeting for the project.
Private Infrastructure
All private infrastructure for the development must be designed to meet the planning scheme requirements unless otherwise agreed by the relevant authority
property notes
Not applicable.
VARIATION approval details
Not applicable.
further development permits required
Type of Development Permit Required	Subject of the required Development Permit
Development Permit for Operational Works	Access, Car parking, Landscaping
Development Permit for Building Works	All building work
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

Yours faithfully,

Lisa Pienaar
Development Planner

Enc:	Appeal Rights
Infrastructure Charge Notice
Approved Plans/Documents

	Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017

Chapter 6 Dispute resolution
Part 1 Appeal rights
229 Appeals to tribunal or P&E Court
(1)	Schedule 1 of the Planning Act 2016 states –
(a)	Matters that may be appealed to –
(i)	either a tribunal or the P&E Court; or
(ii)	only a tribunal; or
(iii)	only the P&E Court; and
(b)	The person-
(i)	who may appeal a matter (the appellant); and
(ii)	who is a respondent in an appeal of the matter; and
(iii)	who is a co-respondent in an appeal of the matter; and
(iv)	who may elect to be a co-respondent in an appeal of the matter.
(2)	An appellant may start an appeal within the appeal period.
(3)	The appeal period is –
(a)	for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or
(b)	for an appeal against a deemed refusal – at any time after the deemed refusal happens; or
(c)	for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or
(d)	for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or
(e)	for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or
(f)	for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person.
Note –
See the P&E Court Act for the court’s power to extend the appeal period.
(4)	Each respondent and co-respondent for an appeal may be heard in the appeal.
(5)	If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal.
(6)	To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about-
(a)	the adopted charge itself; or
(b)	for a decision about an offset or refund-
(i)	the establishment cost of trunk infrastructure identified in a LGIP; or
(ii)	the cost of infrastructure decided using the method included in the local government’s charges resolution.
230 Notice of appeal
(1)	An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that-
(a)	is in the approved form; and
(b)	succinctly states the grounds of the appeal.
(2)	The notice of appeal must be accompanied by the required fee.
(3)	The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to –
(a)	the respondent for the appeal; and
(b)	each co-respondent for the appeal; and
(c)	for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and
(d)	for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and
(e)	each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and
(f)	for an appeal to the P&E Court – the chief executive; and
(g)	for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate.
(4)	The service period is –
(a)	if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or
(b)	otherwise – 10 business days after the appeal is started.
(5)	A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6).
(6)	A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person.
231 Other appeals
(1)	Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable.
(2)	The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error.
(3)	A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter.
(4)	In this section –
decision includes-
(a)	conduct engaged in for the purpose of making a decision; and
(b)	other conduct that relates to the making of a decision; and
(c)	the making of a decision or failure to make a decision; and
(d)	a purported decision; and
(e)	a deemed refusal.
non-appealable, for a decision or matter, means the decision or matter-
(a)	is final and conclusive; and
(b)	may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and
(c)	is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground.
232 Rules of the P&E Court
(1)	A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal.
(2)	However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court

[word/footer1.xml]
Page 7 of 7

[word/footer2.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 7

[Attachment: image3.png (image text)]
ee) NOOSA COUNCIL
Log in to download the original file

Decision Notice - Approved by Delegation of Authority MCU21 0191.docx · 330 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.