    Specific Outcomes                  Probable Solutions            Compliance
Environmental values            No solution provided                O68 - Complies.
O68 The environmental values of                                     The environmental values of
land are protected from adverse                                     the subject site will not be
impacts as a consequence of                                         impacted from the proposed
development on or adjacent to                                       development as it will be
that land.                                                          located outside of
                                                                    environmentally sensitive areas
                                                                    (e.g. Remnant or Regrowth
                                                                    Vegetation) and will not require
                                                                    the removal of any vegetation.
                                                                    Therefore the proposal is
                                                                    consistent with O68.




10.3 - Compliance with Infrastructure Uses Code

        Specific Outcome              Probable Solution                      Compliance
14.39 Effects of use
Location and siting               S1.1 For Installations and        S1.1 - Complies.
O30 The location and siting of    Towers, where practicable,        The proposed site for the
Infrastructure Uses—              infrastructure is —               establishment of a
a) maximises accessibility for    a) co-located with existing       telecommunications facility (or
     maintenance purposes; and         Infrastructure Uses; or      ‘Tower’) is considered to be
b) does not disrupt access for    b) located on or within an        consistent with S1.1 as it will,
                                                                    although not directly co-located
     other purposes.                   existing building;
                                                                    within an existing infrastructure
                                                                    use, be located in an area which
                                  AND
                                                                    is characterised by similar such
                                  S1.2 Easements for access to
                                                                    uses including existing power
                                  Infrastructure Uses are granted
                                                                    stanchions and light poles.
                                  to the Council or the beneficiary
                                                                    O30 – Complies.
                                  of the easement to ensure
                                                                    The facility is also consistent
                                  suitable access can be gained,
                                                                    with O30 as it will be
                                  where practicable.
                                                                    intentionally located within
                                                                    private land for which there is
                                                                    existing access available. After
                                                                    the construction period, only
                                                                    infrequent access would be
                                                                    required during maintenance
                                                                    periods or outages. The existing
                                                                    access arrangements are
                                                                    considered appropriate and will
                                                                    not impact on any adjoining
                                                                    land uses.
Separation from incompatible      No solution provided.             O31 - Complies.
uses                                                                The subject site has been
O31 Sufficient separation                                           located an appropriate
distance is provided between                                        separation distance from
Infrastructure Uses and                                             sensitive locations and
incompatible uses on the same                                       dwellings.
site and neighbouring premises to


NBN-4BBZ-4GYM-5132-Schreibers                                                          Page 68
Log in to download the original file

Appendix 3 - Code Table Assessment.pdf · 291 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.