6.      In accordance with condition 4 of the Material Change of Use approval, provide a
        landscape plan that details the location of all trees to be retained and all trees
        that are required to be removed within the development site. In particular, the
        retention of the large existing trees (Corymbia, Cupaniopsis & Mango) located in
        the north eastern corner of the site between the building and the front boundary

7.      Please detail in the Planting Schedule the species type of Syzygium located
        along the side property boundaries to reach a projected growth height of 4-5
        metres

8.      Demonstrate how the planting schedule achieves the natural character of the
        Sunshine Beach vegetation colony. All plant species are to be derived from the
        Landscaping Guidelines, Table 2.1 Coastal Beachfront Areas and the list
        provided for in Table 8.1 Coastal Beachfront Areas

9.      In accordance with condition 6 of MCU approval, please demonstrate that the
        basement is a minimum of 1.2 metres below natural and finished ground level.

Land Development

10.     Council has concerns that if the sewer manhole lid in driveway is not lowered
        then vehicles using the driveway may scrape the pavement. There is evidence of
        this occurring under existing conditions.

11.     The new 1.2 metre footpath should be shown on an alignment immediately
        behind the kerb and channel, which match the existing footpaths to the east and
        west of the development.

12.     The applicants should provide Geotechnical Engineers report indicating that the
        excavation proposed can be carried out on the site without detriment to the
        adjoining properties and Council’s sewer main.

13.     Please provide plans indicating the location of Rainwater storage tanks.
Please provide four (4) copies of all information that you are providing. In addition, it
would assist Council if you could also provide an electronic copy of your response.
Pursuant to the conditions of the Development Permit for a Material Change of Use
please note that all bonds and contributions are required to be paid prior to the issue of
the Operational Works approval.

Please be aware that under Section 3.2.12 of the Integrated Planning Act, the applicant
is to respond to any information request within 12 months of the request or otherwise,
the application lapses.
Under the provisions of the Integrated Planning Act 1997, you as the applicant, have
three options available in response to this Information Request. You may give the
assessment manager (in this instance Council) and each referral agency (if any):-

1.      all of the information requested; or




     Award Winner - Australian Clean Beach
       Challenge 2004 Litter Prevention

Used in these records

About this file

File size
11 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Request for Further Information - 010.2007.00000191.001 [As Published].pdf · 11 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.