UPDATED 16.5.23 - 20210153 Maple St SWMP
Original PDF page 39, section 1. The text section number identifies this passage in the reader.
FOOTPATH CENTRE LINE SETOUT TABLE
Pt Chainage Easting Northing Level Bearing Rad/Spiral A.Length D.Angle
IP1 0 1014.319 1045.799 120.547 205°11'04.01"
TC 31.788 1000.792 1017.033 122.099 205°11'04.01"
IP2 32.034 1000.687 1016.809 122.112 -2 0.492 14°06'31.80"
CT 32.28 1000.639 1016.567 122.127 191°04'32.22"
IP3 50.366 997.165 998.818 122.886 191°04'32.22"
DESIGN SURFACE
EXISTING SURFACE
DRIVEWAY
MATCH NEATLY TO
EXISTING FOOTPATH
DATUM R.L. 120.00
GRADE 0.50 % 5.00 % 5.70 % 4.66 % 5.19 % 5.20 % 6.16 % 1.97 %
LENGTH
HORIZONTAL ALIMNT R-2.0
ARC LENGTHS TAN 31.788 ARC 0.492 TAN 18.086
-0.022
-0.026
-0.077
-0.011
-0.008
0.000
0.010
0.082
0.050
0.035
0.055
0.059
0.066
0.194
0.240
0.027
CUT/FILL
120.547
120.556
120.665
120.842
120.970
120.986
121.487
121.818
122.006
122.099
122.112
122.127
122.603
122.719
122.879
122.886
DESIGN CENTRELINE
120.547
120.546
120.582
120.791
120.992
121.012
121.564
121.829
121.972
122.044
122.053
122.062
122.409
122.479
122.852
122.894
NATURAL SURFACE
10.000
10.344
20.000
26.378
30.000
31.788
32.032
32.280
40.000
41.893
50.000
50.366
0.000
1.976
4.144
7.244
CHAINAGE
1 0 1 2 3 4 5
SCALE (metres)
1 : 100 (FULL SIZE)
North Point Approved Project Address Title
BEN PARRY
RPEQ 28084 45 MAPLE ST, COOROY, QLD 4563 FOOTPATH CROSS SECTIONS
For and on behalf of RECOR Pty Ltd.
Scale ENGINEERING + PROJECT MANAGEMENT Client Details PROJECT NAME: Project Number Sheet Size
SUNSHINE COAST | BRISBANE | SYDNEY
B 28/04/23 RFI UPDATE QT BP www.recorconsulting.com | ABN 89 647 469 707 MARK MELVILLE COOROY NDIS RESIDENTIAL 20210153 A1
A 28/03/22 MCU ISSUE JAC BRP
AS SHOWN COPYRIGHT © This drawing is subject to copyright in accordance with the agreement between RECOR Pty Ltd and RECOR's client. This DEVELOPMENT Drawing Number Revision
047 B
drawing shall only be used for this specific project. This drawing shall not be used for construction until marked as 'Issued For Construction' in
Rev Date Revision Description Drawn Check DO NOT SCALE, IF IN DOUBT ASK the revision description.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (UPDATED 16.5.23 - 20210153 Maple St SWMP.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.