Council archive · source document
Referral Agency Response - Planning RAP24 0009 · RAP24/0009
Officer: Samuel Osakwe
Direct Telephone: 07 53296316
Our Reference: RAP24/0009
Your Reference: 220293
24 July 2024
EarthCert Building Consultancy Pty Ltd
PO Box 432
POMONA QLD 4568
[email protected]
Dear Sir/Madam,
Referral Agency Response
Planning Act 2016
I refer to your application and advise that Council, as a referral agency for the application,
completed its assessment of the application on 22 July 2024. You are advised that Council
requires conditions to be attached to any development approval. The conditions are listed
below.
1. APPLICATION DETAILS
Application No: RAP24/0009
Street address: 35 The Peninsula Noosaville Qld 4566
Real property description: Lot 275 RP 856192
Planning Scheme: Noosa Plan 2020 (25 September 2020)
2. TYPE OF DEVELOPMENT
The applicant seeks the following type of referral agency response:
• Referral Agency Response for Alterations and Additions to Dwelling House (Structures
within 4.5m of Revetment Wall)
3. REFERRAL AGENCY CONDITIONS
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with
prior to the use commencing, and then compliance maintained at all times while the use
continues.
ABN 97.969.214.121 PO Box 141
noosa.qld.gov.au Tewantin QLD 4565
[email protected] 07 5329 6500
Page 1 of 5
Document Set ID: 23123077
Version: 2, Version Date: 24/07/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 4 pages
Page 2
Approved Plans
2. Development authorised by this approval must be undertaken generally in accordance
with the Approved Plans listed in the table below.
Plan No. Rev. Plan/Document Name Date
00.0 - Site Plan prepared by Paul Clout Design 29/02/2024
Performance Bond
3. A site compliance bond of $5,000 is to be submitted to Council prior to the
commencement of works. The commencement of works can only commence once
Council's Construction Engineering Officer has confirmation that the bond monies have
been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance
with these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
4. Bonds must:
a. meet the requirements of council’s relevant Planning Scheme Policy for
performance and uncompleted works;
b. be lodged with Council and accompanied by the Bond Administration Fee/s; and
c. be requested for release by writing to Council, when relevant approval
requirements have been met.
Earthworks
5. All earthworks and associated retaining structures/batters must be contained entirely
within the subject site unless written permission from the respective landowner(s) is
provided to Council. All earthworks must be undertaken in accordance with the
provisions of Australian Standard AS3798: Guidelines on Earthworks for Commercial
and Residential Developments.
6. Earthworks carried out on site must not affect the structural integrity of the revetment
wall, existing fences or other structures that border the subject site. Fences that are
affected must be replaced in a timely manner and in consultation and agreement of the
owners of the related properties.
Landscaping Works
7. A minimum of 20% of the site must be retained as soft landscaping.
8. The development site must be landscaped. The works must be undertaken in
accordance with the Noosa Plan for that specific area and must include the works shown
on the approved landscape plan.
9. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
10. Where excavations result in a cut face greater than 0.5m, suitable landscaping is to be
installed to soften the visual impacts of the excavations to the Noosa Waters’ Canal for
the full length of the cut face. Landscaping is to be of a suitable species and in
accordance with Noosa Plan 2020 Planning Scheme Policy PSP2 Landscaping.
Page 2 of 5
Document Set ID: 23123077
Version: 2, Version Date: 24/07/2024
Page 3
Revetment Wall / Flood Storage
11. All works within the 4.5m setback from the revetment wall must be carried out generally
in accordance with the plans Flood Storage Model Site Plan (22-1107-F1, Rev. B)
prepared by Lindsay Consulting and dated 8 July 2024.
12. All works for the purpose of increasing available flood storage must be located within
the 4.5m setback from the revetment wall.
13. Certification of the completed works within the 4.5m setback from the revetment wall
must be submitted to Council within 3 months of the completion of the works. The
certification must be prepared by a RPEQ (Registered Professional Engineer of
Queensland) and state that the works:
a. have not reduced the amount of available flood storage within the 4.5m setback
from the revetment wall;
b. have not negatively impacted the stability of the revetment wall or negatively
impacted the associated membrane;
c. have not reduced the available flood storage within the lot from the profile as
described in The Noosa Plan 2020 – Low Density Residential Zone Code; and
d. meet the relevant conditions of this approval
Damage to Services and Assets
14. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and
assets must first be referred to the relevant service authority for approval.
Environment
15. Sediment or any other material including building materials or waste products must not
be deposited or released into the road reserve, stormwater drain or adjacent properties.
4. REFERENCE DOCUMENTS
Plan No. Rev. Plan/Document Name Date
221107 - Flood Storage Calculations Prepared by 8 July 2024
Lindsay Consulting
22-1107- F1 B Flood Storage Model Site Plan Prepared 8 July 2024
by Lindsay Consulting
22-1107- F2 B Flood Storage Model Perspective View 8 July 2024
Prepared by Lindsay Consulting
5. REASONS FOR REFERRAL AGENCY’S DECISION
The proposal is subject to specific built form parameters outlined in The Noosa Plan (25
September 2020).
Page 3 of 5
Document Set ID: 23123077
Version: 2, Version Date: 24/07/2024
Page 4
6. TIME LIMIT FOR MAKING FURTHER APPLICATION
Pursuant to section 54(4) of the Planning Act 2016, you will not be required to refer your
building works application to council for a further Referral Agency Response if:
(a) You submit this Referral Agency Response in its entirety, including all referenced plans
and documents, when making the application to the Assessment Manager; and
(b) There are no changes to the proposal that was presented to council with this referral;
and
(c) The development application to the assessment manager is made within 12 months of
the date of this referral agency response.
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form
part of the referral agency conditions:
Infrastructure Charges
1. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges
Resolution” made pursuant to the planning legislation and regulations current at the time
of issue.
Sustainability
2. Council encourages sustainable and energy efficient building design for all development,
including the use of sustainable building materials, energy efficient fittings, solar hot
water, photovoltaic systems (including the use of inverter/charges), solar panels, water
saving devices and rainwater harvesting.
Equitable Access and Facilities
3. The plans for the proposed building work have NOT been assessed for compliance with
the requirements of the National Construction Code - Building Code of Australia (Volume
1) as they relate to people with disabilities. Your attention is also directed to the fact that
in addition to the requirements of the National Construction Code as they relate to people
with disabilities, one or more of the following may impact on the proposed building work:
a. the Disability Discrimination Act 1992 (Commonwealth);
b. the Anti-Discrimination Act 1991 (Queensland); and
c. the Disability (Access to Premises – Buildings) Standards.
Fires in Urban Areas
4. In urban areas fires are prohibited except where in an appliance is used for domestic
heating or cooking purposes, which must comply with particular standards. Any area
identified as a fire pit area on approved plans is to be in accordance with Local Law &
Subordinate Local Law No. 3, Schedule 3. Refer to the following link for details:
https://www.noosa.qld.gov.au/community/local-laws/local-laws-overview
Page 4 of 5
Document Set ID: 23123077
Version: 2, Version Date: 24/07/2024
Page 5
8. REPRESENTATIONS ABOUT REFERRAL AGENCY RESPONSE
The applicant may make representations to Council about this referral agency response at
any time before the application is decided pursuant to section 30 of the Development
Assessment Rules.
Yours faithfully,
Samuel Osakwe
Development Planner
Enc: Approved Plans/Documents
Page 5 of 5
Document Set ID: 23123077
Version: 2, Version Date: 24/07/2024
Used in these records
Referral Agency Response - Planning RAP24 0009Related documentApplication case desk ↗
About this file
- File size
- 113 KB (small file)
- File type
No other editions are linked here.