Skip to the record
NoosaWatch™: The source of truth.

Original source · versioned page text

Stormwater Management Plan

Attached to the e-mail Response to Info Request (Stormwater Managerment plan) - MCU18/0097.

of 40

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings: the text below has words only, no drawings.

Very large file (13.4 MB): may take a few minutes to open.

Log in to see the plans as drawn

Original PDF page 13, section 1. The text section number identifies this passage in the reader.

GOOD SHEPHERD LUTHERAN COLLEGE                                                                Odyssey Consulting Group
Lot 30 on SP170751                                                             Conceptual Stormwater Management Plan
115 Eumundi Noosa Road, Noosaville                                                                   Project No: K4277




         Figure 3:      Mitigated Post Development Catchment Q100 Flow Rates

         Catchment A will be collected by a detention tank to mitigate flows to less than that of the pre
         development scenario and will discharge to a LPOD on Eumundi Noosa Road. With reference to Figure
         3 the detention arrangement can be seen to effectively mitigate the post development flows in all
         storm events for the proposed site.
                                                                                                       3
         The hydraulic analysis using the DRAINS model has determined that a minimum of 126 m of storage
         is required for runoff attenuation and is to be provided in the form of a detention tank located within
         the open space area. Refer to Odyssey Consulting Group, Stormwater Management Plan (Ref:
         K4277/P007/D) and Odyssey Consulting Group, Stormwater Detention and Bio retention Details (Ref:
         K4277/P010/C) included as Appendix F, for details of the tank arrangement, indicative location and
         preliminary stormwater layout. The final location onsite and construction levels will be determined at
         detailed design stage.

         A copy of the DRAINS model used in this report can be made available to Council upon request.



5.0 WATER QUALITY ASSESSMENT
5.1      Background
         The development of land has the potential to increase the pollutant loads within stormwater runoff
         and downstream watercourses.

         During the construction phase of the development disturbance to the vegetation on the site has the
         potential to significantly increase sediment loads entering downstream watercourses. The operational
         phase of the development will increase the density of residential land use potentially increasing the
         amount of sediments and nutrients washing from the site.

         The following sections describe the predicted increase in pollutant loads generated by the proposed
         development and treatment devices to mitigate the potential increases. In accordance with industry
         guidelines suspended solids, nitrogen and phosphorus will be targeted for reduction during the
         operational phase of the development.




K4277-0002-C                                      05 November 2018                                         Page 9 of 16
Log in to download the original file

Stormwater Management Plan.pdf · 13.4 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.