MCU22/0051 Application For Material Change Of Use Hardware & Trade Supplies At 178 Eumundi Noosa Road, Noosaville · Attachment 1 - MCU220051 – Proposed Conditions
40. Prior to the commencement of use, provide certification from a suitably qualified person that
all works have been undertaken in accordance with the Acid Sulfate Soil Management Plan.
Preparation of a Preliminary Construction Management Plan
41. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. Traffic management during all aspects of the construction phase including:
i. Traffic Management Control Plan in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction.
b. Maintenance of safe pedestrian access for the areas affected by the works during and
after daily construction has ceased.
c. Provision for worker car parking.
d. Maintenance and protection of water quality and existing drainage lines through the
construction site, through the implementation of appropriate erosion and sediment
control measures.
e. Works programme identifying key components of the works and their respective
durations.
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details.
g. Identification of complaint management procedures including:
i. Contact details for the on-site manager.
h. Dispute resolution procedures.
i. If the proposed earthworks exceed 1000m3, provide details on the location of external
fill sites/sources, the haulage route, type of vehicle to be utilised during filling
operations and frequency of usage. NB any damage to the existing road system as a
result of haulage operations shall be fully repaired at the applicant’s expense.
j. It is acknowledged that the preliminary Construction Management Plan will be a draft
document requiring finalisation upon appointment of the Principal Contractor employed
to construct the works and a final document will be required to be submitted at the Pre-
Start Meeting for the project.