06/1395 - Change to Development Approval [As Published] · 132006.1395.02

of 8

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

iP

ken hicks

27 June 2008
Our Ref: 070301T

Sunshine Coast Regional Council
Tewantin Office SCRC - Tewanitin
PO Box 141 Front Counter

TEWANTIN QLD 4565

 

ATTN: Kerri Coyle
Dear Kerri
REQUEST TO CHANGE AN EXISTING APPROVAL

142 NOOSA DRIVE, NOOSA HEADS
LOT 3 ON SP 126203

 

Please find enclosed IDAS Form 2 and owners consent in support of a request to change an existing
approval, being a change to conditions under section 3.5.33 of the Integrated Planning Act. We refer
to email advice from Councils Kerri Coyle of 30 May 2008 in relation to this matter, that the
application fee will be waived in this instance.

The request seeks Council’s approval for the following changes to the Negotiated Decision Notice of
16 May 2008.

Condition 13

Condition 13 requires an area of land located at the rear of the site be dedicated for environmental
protection purposes. As detailed under item 10 Further Development Permits Required, this action
will require a development permit for reconfiguring a lot. The last sentence of this condition states
“This area of land shall be dedicated to the crown prior to the sealing of the survey plan by Council”.
The requirement is somewhat contradictory, as dedication does not occur until registration of the
survey plan which occurs after the sealing of the survey plan by Council. To avoid any future
confusion and accord with the intent of this condition, it is requested the last sentence be amended to
This area of land shall be dedicated to the crown prior to the commencement of the use.

Condition 34

Condition 34 stipulates that the Development Permit lapses if the use has not happened by 24
January 2010, unless application to extend the currency period is approved by Council. This condition
essentially limits the currency period to a 2 year period from date of the original decision notice, which
was for a preliminary approval. We are not aware of any reason why this permit was limited to a 2
year period given Councils standard practice of approving 4 years currency periods. It is requested
that this condition be amended to reflect a time period of 16 May 2012 being 4 years from the date
of issue of the Negotiated Decision Notice and Development Permit.

Item 10 Further Development Permits Required

e Development Permit for Material Change of Use

As a result of the representation made, Council issued a Development Permit for Material Change of
Use with the Negotiated Decision Notice. This further permit is no longer required and should be
deleted from the Decision Notice.

 

TOWN PLANNERS | CONSULTING SURVEYORS | URBAN DESIGNERS | PROJECT MANAGERS
Ken Hicks & Associates Pty Ltd | [email protected] | A.C.N. 010278823 | A.B.N. 74 308 405 611
Suite 7 Dalton Centre, 1 Newspaper Place 18/42 King Street 61-73 Sturt Street
PO Box 6380, MAROOCHYDORE BC Qld 4558 PO Box 1712, CABOOLTURE, Qld 4510 PO Box 5027, TOWNSVILLE, Qld 4810
P 0754432844 «=F 07 5443 7146 P 0754955318 F 075495 5317 P 0747213066 F -07.4721 3088

Used in these records

About this file

File size
335 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

06_1395 - Change to Development Approval [As Published].pdf · 335 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.