SUPERSEDED - Amended - Minor Change Existing Approval - 51983 3225 22 (As Published) · 51983.3225.22

of 21

Text shows just the words. Original shows the document exactly as it was published.

               Additional Conditions specific for Lot 2 GTP 1154 – 19 May 2025
                      Performance Bond - Planning
               57.    Security in the form of a cash bond or trading bank guarantee to the sum of $5,000 must be
                      submitted to Council, to secure performance of all conditions of this approval, specifically for
                      Lot 2, prior to the issue of a Development Permit for Building Works. The cash bond or trading
                      bank guarantee will be returned on performance of the conditions of approval less any costs
                      incurred by Council in respect of enforcing performance of this permit. Council reserves the
                      right to call upon the bond or guaranteed sum to effect compliance with conditions.
               Partial Demolition of Existing Building
                      Codes of Development
               58.    Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
                      solutions as contained in the Waste Management Code and Water Quality and Drainage
                      Code of the Noosa Plan 2020.
                      Works
               59.    Demolition must be undertaken in a manner that causes no detrimental effect upon the
                      amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
                      hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
                      in accordance with the nuisance provisions of the Environmental Protection Act 1994.
                      Waste Management
               60.    Adequate area must be provided on-site for the collection and separate storage of recyclable,
                      non-recyclable, vegetative and hazardous materials in their specific waste streams during
                      removal or demolition works.
               61.    All waste materials must be removed from the site to avoid causing unhealthy conditions,
                      with the site left clean, tidy and free from any debris.
               62.    Where a development permit has not been issued for the future use of the site, hard surfaced
                      areas including concrete slabs must be removed and disturbed areas must be revegetated
                      in accordance with PSP2 Landscaping of the Noosa Plan 2020. Alternatively, the site must
                      be turfed within 20 business days of completing the removal or demolition work.
                      Water Quality and Drainage
               63.    Erosion and sediment control is to be undertaken in accordance with the requirements of the
                      Water Quality and Drainage Code of the Noosa Plan. Measures are to be installed and/or
                      maintained until soils are stabilised by vegetation or sealed.
                      NOTE: It is an offence under the Environmental Protection Act 1994 to deposit or potentially
                      allow litter, waste, soil, or other contaminants to enter a waterway or storm water drainage
                      system (e.g. roadside gutter).
                      Health and Safety
               64.    All building materials containing asbestos, including asbestos cement sheeting or roofing and
                      lagging, are removed from the building prior to demolition or relocation.
               65.    Removal of building materials containing asbestos must be undertaken by a licensed
                      asbestos removalist.
               66.    Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
                      requires a licensed asbestos removalist to give notice to Workplace Health and Safety
                      Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
                      commences. Notification must be made using Form 65: Notification of licensed asbestos
                      removal work, demolition work or emergency demolition.
               67.    All building materials containing asbestos products are wrapped and disposed of in
                      accordance with the Public Health Regulation 2006 and the Environmental Protection
                      Regulation 2008.


                                                                                                      Page 16 of 21
Document Set ID: 23828362
Version: 0, Version Date: 01/01/1900

Used in these records

About this file

File size
212 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED - Amended - Minor Change Existing Approval - 51983 3225 22 (As Published).pdf · 212 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.