29 August 2024
M3024E‐004



Chief Executive Officer
Noosa Council
PO Box 141
Tewantin QLD 4565

Attn: Daniel Epps
Re: Cambooya Pty Ltd
    36 & 38 Duke Street, Sunshine Beach
    Operational Works – Civil Engineering (Council Ref: OPW24/0103)




Dear Sir/Madam,

Reference is made to our IDAS Development Application for Civil Engineering Operational Works associated with the
above noted development.

We acknowledge receipt of Council’s information request dated 12 August 2024 and provide additional information
requested as follows:

INFORMATION REQUIRED

1. We have modelled the stormwater system to allow for a 20% increase in rainfall intensity by the year 2100 in
   accordance with Performance Outcome 2 of The Noosa Plan 2020 – Water Quality and Drainage Code. The detention
   requirement has been increased in volume and depth of water accordingly. The revised tank design now has
   adequate volume, and the additional 100‐year ARI scenario has been added to the amended SBSMP as a separate
   chapter (copy attached).


2. We provide further clarification to stormwater items on JFP Drainage Layout Plan (D02 Rev A) as follows:

      a. An amended detention tank detail and section has been provided detailing the inlet connection from structure
         1/A – refer to JFP Drawing M3024E D02 attached to this response;
      b. The 90o bend has been replaced by two 45o bends to provide better hydraulic performance and ease of
         maintenance – refer to JFP Drawing M3024E D02 attached to this response; and
      c. Catchment D3 (landscape area) is directed towards drainage structure 3/A via a piped drainage system
         constructed as part of the building works – refer building hydraulic drawings for details. Note 5 has been added
         to JFP Drawing M3024E D01 for further clarification maintenance – refer to JFP Drawing M3024E D01 attached
         to this response.
Log in to download the original file

JFP Covering Letter.pdf · 251 KB (small file)

Full text of the other 1 page

Page 2

The information provided above represents our response to all items contained in Council’s Request for Further
Information. We now request Council proceed with the assessment process and provide Operational Works Approval to
the application as submitted.


Please contact the undersigned if you wish to discuss any issues pertaining to this response.



Yours faithfully,



ANDREW FRASER (RPEQ 5691)
SENIOR ENGINEER
JFP URBAN CONSULTANTS

Encls: Amended JFP SBSMP
       Amended JFP OPW Drawings
       JFP Civil Drawing Transmittal
       Blackburne Jackson Landscape Drawings
       Blackburne Jackson Landscape Transmittal

cc:      David Dunworth – Cambooya Pty Ltd




JFP Ref: M3024E‐004                                                                                   Page 2

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.