PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 11 FEBRUARY 2020
Performance Bond
8. Security in the form of a cash bond or trading bank guarantee to the sum of $15,000
must be submitted to Council, to secure performance of all conditions of this approval,
prior to the issue of a Development Permit for Operational Works. The cash bond or
trading bank guarantee will be returned on performance of the conditions of approval
less any costs incurred by Council in respect of enforcing performance of this permit.
Council reserves the right to call upon the bond or guaranteed sum to effect compliance
with conditions.
Building Appearance
9. The development (including the existing building) must be finished with subdued and
complimentary external building colours.
10. The northeast wall of the development must be finished with a minimum of two (2)
neutral colours to visually break up the wall and maintain an external building
appearance of two (2) storeys.
Landscaping
11. The development site must be landscaped. The works must be undertaken in
accordance with an Operational Works approval and the Noosa Plan for that specific
area and must include in particular:
a. Landscaped area as per the approved site plan;
b. The area between the PWD circulation space and front property boundary must
be landscaped; and
c. Provision of two (2) mature size street trees (100 litre pot size) within the road
reserve of the Jarrah Street frontage between the site driveways.
12. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
Fencing and Walls
13. A 2.0 metre high screen fence must be erected along the full length of the west
boundary of the site.
Waste Storage Areas
14. Waste storage areas must be screened by landscaping or fencing.
Street Identification
15. The street address of the development must be clearly visible and discernible from the
primary frontage of the site by the provision of a street number and, where appropriate,
the building name.
Water & Sewer Connections
16. An underground connection to reticulated water and sewerage must be provided to the
development site in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
17. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
(Unitywater) must be submitted to Council that certifies an underground connection to
reticulated water and sewerage has been provided to the development site.
Advertising Signage
18. Any advertising sign or device must comply with Council’s policies on advertising.
Page 40 of 119
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.