Development in the erosion prone area, as shown on the SPP interactive mapping system, is therefore
subject to assessment against the assessment benchmarks – natural hazards, risk and resilience within the
SPP. The subject land is mapped as erosion prone area by the SPP interactive mapping system. An
assessment of the proposed development against the relevant assessment benchmarks of the SPP is
provided in Table 9 below.
Table 9: Assessment against SPP Assessment Benchmarks – Natural hazards, risk and resilience
Assessment Benchmark Applicant Response
Erosion prone areas within a coastal management district:
(1) Development does not occur in an erosion Not applicable. Whilst the subject land is mapped
prone area within a coastal management district as an erosion prone area, it is not mapped as a
unless the development cannot feasibly be located coastal management district.
elsewhere and is:
(a) coastal-dependent development; or
(b) temporary, readily relocatable or able to
be abandoned development; or
(c) essential community infrastructure; or
(d) minor redevelopment of an existing
permanent building or structure that
cannot be relocated or abandoned.
(2) Development permitted in (1) above, mitigates
the risks to people and property to an acceptable
or tolerable level.
Bushfire, flood, landslide, storm tide inundation, and erosion prone areas outside the coastal
management district:
(3) Development other than that assessed against The subject land is mapped as an erosion prone
(1) above, avoids natural hazard areas, or where it area. Notwithstanding, the design of the proposed
is not possible to avoid the natural hazard area, dwelling house is such that it avoids impacts to
development mitigates the risks to people and coastal processes and thereby avoids risks to
property to an acceptable or tolerable level. people and property.
All natural hazard areas:
(4) Development supports and does not hinder As above, the is appropriately and adequately
disaster management response or recovery setback from the seaward boundary of the site.
capacity and capabilities. The proposed development will therefore not
(5) Development directly, indirectly and impact on the ability for any disaster management
cumulatively avoids an increase in the severity of response or recovery requirements (if and when
the natural hazard and the potential for damage they are required in the future, nor will it adversely
on the site or to other properties. impact on natural / coastal processes.
(6) Risks to public safety and the environment from The proposed development is for a dwelling house
the location of hazardous materials and the only. Contaminants and / or hazardous materials
are therefore not anticipated.
Page 17 of 20
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
631_IPS Planning Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 552 KB (small file)
- File type
No other editions are linked here.