                                      Form 6 - Decision Notice
                                      INTEGRATED PLANNING ACT 1997, S3.5.15, IDAS DEVELOPMENT APPLICATION


 File No:    2007/836                            Date of Decision:       6 August 2007

1.     APPLICANT DETAILS

 Name:               Ruben Uriarte

 Postal address:     PO Box 1364
                     NOOSA HEADS QLD 4567


 Phone no:                                    Fax no:

2.     PROPERTY DESCRIPTION

 Street address:     55 Elizabeth Street Noosaville

 Real property       Lot 1 RP 73068
 description:

3.     OWNER DETAILS

 Name:               Javaka Pty Ltd

 Postal address:     PO Box 1551
                     NOOSA HEADS QLD 4567

4.     REFERRAL AGENCIES

 Referral Agency            Address                                                   Basis
 Nil

5.     APPLICATION TYPE

 Development                      Development Details                        Preliminary        Development
                                                                              Approval             Permit
 Operational Works                Operational Works - Landscaping,               No                 Yes
                                  Car Parking & Access, Frontage
                                  Works,     Stormwater     Disposal,
                                  Sediment & Erosion Control & Filling

6.     DECISION DETAILS

Council decided to approve the application and grant a Development Permit, subject to conditions.

7.     APPLICABLE CODES

The developer must comply with the following codes for self-assessable development related to the development
approved under this Development Permit:-
Nil.

8.     SUBMISSIONS

Not Applicable.
Full text of the other 8 sections

Section 2

NOOSA COUNCIL IDAS Development Application Decision Notice                                              2 of 9

9.     CONDITIONS

The approval is subject to conditions. Noosa Council’s conditions are attached.

10.    FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit required                 Subject of the required Development Permit
 Nil

11.    RIGHTS OF APPEAL

Rights of appeal in relation to this application are attached.

12.    ASSESSMENT MANAGER

 Name:      Noosa Council                 Signature:                              Date:      7 August2007




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@54044421\@[email protected]

Section 3

NOOSA COUNCIL IDAS Development Application Decision Notice                                                  3 of 9




                                    Noosa Council Conditions
                                    INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION



Landscaping

1.    The site is to be landscaped in accordance with Council’s Policy on Landscaping Guidelines and the
      approved plan of Development. The approved plans and documentation titled Landscape Plan Drawing
      No. 070316-2 Issue B prepared by Greenscapes Nursery & Design dated 14/6/2007 and may be
      amended by these conditions.

2.    All manholes, inspection pits and grates are to be raised to finish surface level and kept free of cover and
      be visible at all times to ensure prompt access in case of emergency.

3.    The landscape construction is to be implemented in accordance with the amended landscape plan,
      planting schedule and horticultural industry best practices.

4.    Provide replacement species for the following plants:

           Location & Plant species to be Replaced                     Replacement Plant

           CYCAS revoluta, replace all apart from around       DORYANTHES excelsa
           the pool area


           ORPHIOPOGON japonica (mondo grass)                  DIANELLA caerulea

                                                               DIANELLA brevipendunculatum



           WOODYETIA bifurcata, frontage areas                 ARCHONTOPHOENIX cunninghamiana

              Refer to the amended landscape plan for details and location.

5.    All trees must be located a minimum of 1.0 metres from all services to prevent root/service conflict and to
      provide future ease of maintenance requirements.

6.    All native plant species located in group plantings shall not be subjected to any hedging maintenance
      regimes.

7.    All street trees (HARPULLIA pendula 100 litre) shall be established between the 1.5 m wide new concrete
      footpath and the back of kerb. Refer to the amended landscape plan for details and location. The trees
      shall be located 1m from the rear of the kerb.

8.    All street trees and internal trees 45 litre and greater must be securely staked and tied to assist their
      growth during the establishment period.

9.    The density of planting must achieve the set out requirements as detailed on the approved landscape
      plan. Refer to the amended landscape plan for details and locations.

10.   The applicant must ensure that all landscaping treatment does not unduly restrict/prevent access to
      service meters within the site.

11.   All palms shall be grouped in clumps to reflect their natural environment.

12.   Prior to commencement of any clearing or demolition works on site, all trees detailed for retention detailed
      on approved plan shall be provided with protective barricade fencing to prevent damage or subsequent
      loss. The tree protection methods shall remain in place until all building construction works on site have
      been completed.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@54044421\@[email protected]

Section 4

NOOSA COUNCIL IDAS Development Application Decision Notice                                                    4 of 9


13.   This Development Permit lapses if the development has not happened by 6 August 2009, unless
      application to extend the currency is approved by Council.

Land Development (frontage works, access, car parking, stormwater disposal, sediment and erosion controls)

14.   The development shall be carried out in accordance with Engineering drawings Nos.

             27973-TC1B dated 17/07/07                   by Rienmac Pty Ltd

             27973-C1C               dated 18/06/07             by Rienmac Pty Ltd

             1740-0-1A               dated 15/06/07             by Construction Hydraulic

             1740-0-2                dated 11/05/07             by Construction Hydraulic

             or as modified herein

15.   Roof and surface runoff connection to Council’s drainage system shall be generally as shown on drawing
      No. 1740-0-1A dated 15/06/07 by Construction Hydraulic. A manhole with a trafficable lid shall be
      constructed at the proposed junction with Council’s existing drainage system in Elizabeth Street. The
      construction of the manhole and reinstatement works to the road formation shall be undertaken in
      accordance with Council’s Planning Scheme Policy 5 – Engineering Design Standards – Roads, Drainage
      and Earthworks and the current standard drawings. In this regard a revised drainage plan indicating the
      abovementioned changes shall be submitted to Council for approval prior to the pre-start meeting.

16.   The two existing trees (Mango and Tuckeroo) located in the north-eastern corner of the site shall be
      retained and any works carried out on site shall not have an adverse impact upon these trees. The
      proposed stormwater drainage system and associated retaining structures shown on drawing No. 1740-0-
      1A dated 15/06/07 by Construction Hydraulic shall be relocated to ensure the preservation of these trees.
      In this regard a revised drainage plan indicating the abovementioned changes shall be submitted to
      Council for approval prior to works commencing.

17.   The edge of the access driveway shall be setback a minimum of 500mm from the adjacent property
      boundary.

18.   The proposed visitor carspace in the front setback from Elizabeth Street shall be constructed with a
      sealed surface with minimum dimensions of 2.5m wide and 5.4m deep clear of any obstructions.
      Stormwater runoff from the visitor carspace shall be directed to the stormwater drainage system.

19.   A bikeway/footpath 1.5 metres wide shall be constructed across the full frontage of the development. The
      footpath shall have a slip resistant surface. The alignment, of which, shall be determined on site with
      Council’s Construction Technical Officer. The expansion joints in any bikeway/footpath shall be “sawcut”
      not trowel jointed.

20.   Install suitable root barrier where proposed trees are adjacent to paths, pavement etc in accordance with
      Council’s Planning Scheme Policy PSP03 Landscaping Plants and Guidelines.

21.   Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily installed into the
      first existing external downstream stormwater structure.
      These devices are to be checked and cleaned on a regular basis and specifically after each rain event.
      These devices are to remain in place during the civil works and construction phases of the development.
      The location and type of device to be installed shall be established at the “pre start” meeting with
      Council’s Construction Technical Officer and shall be installed prior to the commencement of any works.
22.   Council’s Construction Technical Officer (ph 0410 512 505), shall be given seven (7) days’ notice of
      intention to commence works to arrange a “pre start” meeting regarding the civil works.

23.   The principal contractor must have all the appropriate insurance and public liability documentation to carry
      out the works. The principal contractor is also responsible to ensure that any sub contractors also have
      the appropriate insurance and public liability documentation.

24.   Prior to the “pre start” meeting, the principal contractor must be provided with a copy of Council’s
      signed approved drawings and conditions by the applicant.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@54044421\@[email protected]

Section 5

NOOSA COUNCIL IDAS Development Application Decision Notice                                                  5 of 9


25.   The Consulting Engineers for the project shall be currently Registered Professional Engineers of
      Queensland (RPEQ). The consulting engineers are responsible for arranging all inspections, with
      Council’s Construction Technical Officer or nominated staff.

26.   Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the project.
      (This person will be the contact for the project).

27.   Council standards shall apply to these works unless otherwise modified herein.

28.   The person acting on this permit shall ensure that its consultants and contractors take all reasonable care
      during the construction of the engineering works to ensure that Council property, road pavements or
      facilities (such as underground drainage, water supply, sewerage, footpaths, kerbing, landscaping, street
      furniture etc.) are protected against any damage or interference whatsoever.

      If any Council property or facilities should be damaged by the Applicant or any of its Consultants or
      Contractors through any cause whatsoever in the course of, directly or indirectly, carrying out the
      engineering works, the Applicant and/or its Contractors shall forthwith notify the Manager Land
      Development and shall forthwith rectify the damage to that property or facility at its cost and to the
      satisfaction of the Manager Land Development.

      All rectification works are to be completed prior to the commencement of the use or, alternatively, the
      Applicant may request the Council to carry out the rectification work at the Applicant’s cost, such cost
      being paid by the Applicant to the Council prior to the commencement of the use.

      In the case of any emergency the Council shall be entitled to rectify such damage at the cost of the
      Applicant, such cost being paid prior to the commencement of the use.

29.   The development of the site shall be carried out in such a manner as to prevent dust and/or sand
      nuisance to residents and/or tenants in the vicinity of the development.

30.   Construction work and other associated activities are permitted only during the hours of 7.00 am and 6.00
      pm Monday to Saturday. No work is permitted on Sundays or public holidays, except where extended
      hours are approved by the Manager-Land Development or his nominee.

31.   All signage, including that for safety during construction shall be in accordance with the Manual of Uniform
      Traffic Control Devices and Traffic Infrastructure (Roads) Act.

32.   Safe pedestrian access on Elizabeth Street shall be maintained at all times. Should footpath / road
      closures be necessary to carry out construction works, Council’s Construction Technical Officer (ph 0410
      512 505) must be notified prior to the proposed closure.

33.   Sediment and erosion control measures must be in place prior to works commencing. If such measures
      are not in place or are not satisfactory, “on the spot “fines may be issued. Such fines can be issued if
      sediments from the site are found to enter or have the potential to enter Council’s stormwater system or
      natural waterways. Although the sediment and erosion control measures have been approved on drawing
      No 1740-0-2 dated 11/05/07 by Construction Hydraulic, Council’s Manager – Land Development may
      request further controls to be installed should approved measures be inefficient.

34.   The owners of the subject property shall maintain the grease/oil arrestor pits/gross pollutant traps in
      accordance with the manufacturers specifications.

35.   The owners of the subject property shall inspect the grease/oil arrestor pits/gross pollutant traps on a
      weekly basis and after each storm event.

      The owners of the subject property shall enter into an ongoing maintenance contract with a Registered
      Contractor to clean and maintain the grease/oil arrestor pits/gross pollutant traps on a regular three
      monthly cycle and on a “On Call” basis in the case of an emergency.

      The management and maintenance of the grease/oil arrestor pits/gross pollutant traps shall be included in
      the Community Management Scheme for the completed development.

36.   All stormwater drainage lines including private drainage lines (also known as inter-allotment drainage
      lines) or as otherwise approved by Council’s Manager of Land Development shall be inspected by closed
      circuit television (CCTV) at the completion of all works and immediately prior to acceptance ‘On
      Maintenance’. Council’s Construction Technical Officer shall be advised of the timing of this inspection.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@54044421\@[email protected]

Section 6

NOOSA COUNCIL IDAS Development Application Decision Notice                                                   6 of 9


      A report of the CCTV inspection, including photographic records (which includes photos & video
      recordings burnt onto a CD) of the inspection shall be submitted to the Council for approval. Any defects
      or substandard works shall be recorded and accurately illustrated on the drainage plan showing the
      location of the defect(s).
      Substandard work will not be accepted ‘On Maintenance’ and must be rectified at the applicants expense
      with a further CCTV inspection arranged once the rectification works have been completed.
      To this extent all CCTV inspections, including any additional inspections necessary following defect
      identification and rectification, shall be entirely at the applicant’s expense. Any costs incurred by Council
      in reviewing the CCTV inspection results shall also be borne by the applicant.

37.   Certification of the completed works must be provided by the supervising engineer, together with
      certification from the Hydraulic Engineer that the completed works conform with all aspects of the
      drainage design for the development.

38.   Prior to acceptance of civil works to become Council assets "On Maintenance", the lodgement of
      satisfactory “As Constructed” records shall be submitted to Council.

      As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer (RPEQ) for
      design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and type of all
      services and structures. All of which shall be submitted to Council for checking and for Council’s records.
      The data must fully detail levels for all engineering works including but not limited to drainage structures,
      finished ground levels and pavement surface levels. The data shall be submitted in the Asset Design and
      As Constructed (ADAC) digital format.            (Guidelines on the use of ADAC are available at
      www.adac.com.au) and Council’s Planning Scheme Policy 5 – Engineering Design Standards – Roads,
      Drainage and Earthworks.

      Approval of works shall not be granted until all As Constructed information has been
      supplied and accepted by Council.

39.   A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will be imposed
      on construction works during the maintenance period, which is a minimum period of 12 months duration.
      Such bond must be lodged by, and shall only be accepted from the Developer for the works.

40.   The works to become Council assets will not be accepted "On Maintenance" until the landscaping is
      completed.

41.   These works are also to be in compliance with the relevant conditions of Development Permit No. 23737
      DA.

42.   Notwithstanding that Council has checked the plans with due care, where it is found during construction
      that variations from Council's standards exist, then Council standards shall apply.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@54044421\@[email protected]

Section 7

NOOSA COUNCIL IDAS Development Application Decision Notice                                              7 of 9



                                    Local Laws, Policies & State
                                    Regulation Requirements
                                    INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION


     THE FOLLOWING ADVICES ARE FOR INFORMATION PURPOSES ONLY AND DO NOT FORM
                             CONDITIONS OF APPROVAL

1.      Should any changes or modifications to the approved plans be required as a result of construction
        constraints, a Change to an Existing Approval Application under the Integrated Planning Act must be
        made. Amended plans clearly indicating the changes must be lodged with this application along with the
        appropriate fees.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@54044421\@[email protected]

Section 8

NOOSA COUNCIL IDAS Development Application Decision Notice                                                           8 of 9



                                                    Appeal Rights
                                                    INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION

   The following is an extract from the Integrated                           (6) If an application involves assessment against
   Planning Act (Chapter 4).                                              a concurrence agency code, appeal rights for
                                                                          submitters for the application are not available
   Division 8 - Appeals to                   court      relating     to
                                                                          against the part of the approval that represents the
   development applications
                                                                          concurrence agency’s response for the code.
   Appeals by applicants                                                  Appeals by advice agency submitters
   4.1.27.(1) An applicant for a development application                  4.1.29.(1) An advice agency may, within the limits of
   may appeal to the court against any of the following-                  its jurisdiction, appeal to the court about the giving of
   (a) the refusal, or the refusal                 in   part,   of   a    a development approval for a development
       development application;                                           application if-
   (b) a matter stated in a development approval,                         (a) the development application involves impact
       including any condition applying to the                                assessment; and
       development, and the identification of a code                      (b) the advice agency told the applicant and the
                            1
       under section 3.1.6;                                                   assessment manager to treat its response to the
   (c) the decision to give a preliminary approval when a                     application as a submission for an appeal.
       development permit was applied for;
                                                                             (2) The appeal must be started within 20 business
   (d) the length of a currency period;                                   days after the day the decision notice or negotiated
                                                                          decision notice is given to the advice agency as a
   (e) a deemed refusal.                                                  submitter.
      (2) An appeal under subsection (1)(a) to (d) must                   Appeals for matters arising after approval given
   be started within 20 business days (the “applicant’s                   (co-respondents)
   appeal period”) after the day the decision notice or
   negotiated decision notice is given to the applicant.                  4.1.30.(1) For a development approval given for a
                                                                          development application, a person to whom any of
       (3) An appeal under subsection (1)(e) may be                       the following notices have been given may appeal to
   started at any time after the last day a decision on the               the court against the decision in the notice-
   matter should have been made.
                                                                          (a) a notice giving a decision on a request for
   Appeals by submitters                                                      extension of the currency period for an approval;
   4.1.28.(1) A submitter for a development application                   (b) a notice giving a decision on a request to make a
   may appeal to the court about-                                             minor change to an approval.
   (a) the giving of a development approval, including                        (2) The appeal must be started within 20 business
       any conditions (or lack of conditions) or other                    days after the day the notice of the decision is given
       provisions of the approval; or                                     to the person.
   (b) the length of a currency period for the approval.                        (3) Subsection (1)(a) does not apply if the
       (2) The appeal must be started within 20 business                  approval resulted from a development application
                                                                          (superseded planning scheme) that was assessed as
   days (the “submitters appeal period”) after the day
                                                                          if it were an application under a superseded planning
   the decision notice or negotiated decision notice is
                                                                          scheme.
   given to the submitter.
                                                                             (4) Also, a person who has made a request
      (3) If a person withdraws a submission before the
                                                                          mentioned in subsection (1) may appeal to the court
   application is decided, the person may not appeal the
                                                                          against a deemed refusal of the request.
   decision.
                                                                              (5) An appeal under subsection (4) may be
      (4) If an application involves both impact
                                                                          started at any time after the last day the decision on
   assessment and code assessment, appeal rights for
                                                                          the matter should have been made.
   submitters are available only for the part of the
   application involving impact assessment.                               Division 9 - Appeals to court about other matters
       (5) If an application is processed under section                   Appeals for matters arising after approval given
   6.1.28(2), appeal rights for submitters for the                        (no co-respondents)
   application are available only for the aspects of the
   development that would have required public                            4.1.31.(1) A person to whom any of the following
   notification under the repealed Act.                                   notices have been given may appeal to the court
                                                                          against the decision in the notice-
                                                                          (a) a notice giving a decision on a request to change
                                                                              or cancel a condition of a development approval.
   1
        Section 3.1.6 (Preliminary approval may override local planning
       instrument)



AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@54044421\@[email protected]

Section 9

NOOSA COUNCIL IDAS Development Application Decision Notice                                       9 of 9

                                      2
(b) a notice under section 6.1.44 giving a decision to
    change or cancel a condition of a development
    approval.
    (2) The appeal must be started within 20 business
days after the day the notice of the decision is given
to the person.
   (3) Also, a person who has made a request
mentioned in subsection (1)(a) may appeal to the
court against a deemed refusal of the request.
    (4) An appeal under subsection (3) may be
started at any time after the last day the decision on
the matter should have been made.
Appeals against decisions to change approval
conditions under the repealed Act
4.1.33A.(1) A person who is dissatisfied with a
decision made on an application to change the
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act may
appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
    (2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of
the decision is to be given to the person.
    (3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on the
matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions
applied under a local law about the use of premises
or the erection of a building or other structure
permitted by the planning scheme may appeal to the
court against the decision or the conditions applied.
    (2) The appeal must be started within 20 business
days after the day notice of the decision is given to
the applicant.




2
     Section 6.1.44 (Conditions may be changed or cancelled by
    assessment manager or concurrence agency in certain
    circumstances)




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@54044421\@[email protected]

Used in these records

About this file

File size
42 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

0015A787.001.pdf · 42 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.