Council archive · source document
2024072 - NSC OPW Decision Notice with Conditions (Dated 20-06-2023) · MCU22/0199.01
d. where there is an existing pedestrian path, a matching crossfall must be provided for
the driveway on the alignment of the path, for the full width of the path;
e. have a minimum clearance of 500mm from any Unitywater/Energex/Telstra asset,
unless a written approval is obtained from Unitywater/Energex/Telstra and submitted
to Council;
f. any stormwater kerb outlet in close proximity to the edge of the new driveway must be
provided with an approved kerb adaptor; and
g. any existing kerb sections requiring removal due to the works must be saw-cut and
removed to allow for a smooth and neat finish with the new driveway.
20. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain the
responsibility of the property owner/developer.
Stormwater Drainage
21. The constructed driveway must not cause additional ponding on the road formation or the
road reserve.
Environment (Erosion and Sediment Control)
22. Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must
not be released from the site or to waters within the site, or be likely to be released should
rainfall occur, unless all reasonable and practicable measures are taken to prevent or
minimise the release and concentration of contamination.
23. The contractor must ensure non-essential exposure of soil is prevented by restricting the
extent of works and minimising the duration of soil exposure to adverse weather conditions.
Exposed areas must be suitably covered/stabilised/reinstated as soon as practicable and
prior to any predicted rainfall occurring.
24. Erosion and sediment control measures must be installed and maintained to minimise
erosion on the site and to minimise the export of sediment and associated pollutants from
the site. The erosion and sediment control measures must be designed, installed and
maintained in accordance with current best practice standards (refer to advisory notes).
FOLLOWING CONSTRUCTION
25. A final inspection and approval of the new driveway and completed reinstatement works by
Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
inspection.
26. All works (including crossover, driveway, stormwater drainage and channel stabilisation
works), must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit.
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
General Advisory Notes
1. As this driveway is a private structure, the owner bears full responsibly for the standard of its
construction, maintenance and any liabilities associated with its construction. It is
recommended that professional advice be sought for the construction of the driveway to
ensure that the driveway is constructed in accordance with standard drawing RS-056 and
any associated addendum.
Page 4 of 7
Document Set ID: 22466445
Version: 4, Version Date: 20/06/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
2024072 - NSC OPW Decision Notice with Conditions (Dated 20-06-2023).pdfRelated documentApplication case desk ↗
Decision Notice - OPW23 0089 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 148 KB (small file)
- File type
No other editions are linked here.