2024072 - NSC OPW Decision Notice with Conditions (Dated 20-06-2023) · MCU22/0199.01

of 7

Text shows just the words. Original shows the document exactly as it was published.

                      d.      where there is an existing pedestrian path, a matching crossfall must be provided for
                              the driveway on the alignment of the path, for the full width of the path;
                      e.      have a minimum clearance of 500mm from any Unitywater/Energex/Telstra asset,
                              unless a written approval is obtained from Unitywater/Energex/Telstra and submitted
                              to Council;
                      f.      any stormwater kerb outlet in close proximity to the edge of the new driveway must be
                              provided with an approved kerb adaptor; and
                      g.      any existing kerb sections requiring removal due to the works must be saw-cut and
                              removed to allow for a smooth and neat finish with the new driveway.
               20.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer.
                      Stormwater Drainage
               21.    The constructed driveway must not cause additional ponding on the road formation or the
                      road reserve.
                      Environment (Erosion and Sediment Control)
               22.    Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must
                      not be released from the site or to waters within the site, or be likely to be released should
                      rainfall occur, unless all reasonable and practicable measures are taken to prevent or
                      minimise the release and concentration of contamination.
               23.    The contractor must ensure non-essential exposure of soil is prevented by restricting the
                      extent of works and minimising the duration of soil exposure to adverse weather conditions.
                      Exposed areas must be suitably covered/stabilised/reinstated as soon as practicable and
                      prior to any predicted rainfall occurring.
               24.    Erosion and sediment control measures must be installed and maintained to minimise
                      erosion on the site and to minimise the export of sediment and associated pollutants from
                      the site. The erosion and sediment control measures must be designed, installed and
                      maintained in accordance with current best practice standards (refer to advisory notes).
               FOLLOWING CONSTRUCTION
               25.    A final inspection and approval of the new driveway and completed reinstatement works by
                      Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
                      inspection.
               26.    All works (including crossover, driveway, stormwater drainage and channel stabilisation
                      works), must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     As this driveway is a private structure, the owner bears full responsibly for the standard of its
                      construction, maintenance and any liabilities associated with its construction. It is
                      recommended that professional advice be sought for the construction of the driveway to
                      ensure that the driveway is constructed in accordance with standard drawing RS-056 and
                      any associated addendum.



                                                                                                         Page 4 of 7
Document Set ID: 22466445
Version: 4, Version Date: 20/06/2023

Used in these records

About this file

File size
148 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

2024072 - NSC OPW Decision Notice with Conditions (Dated 20-06-2023).pdf · 148 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.