22-0147 220228 NSC-RAF-DN Development Permit - Council Decision Notice
Attached to the e-mail Operational Works Application OPW 22/0124 - DA Form 1 - Plans -34 Peregian Esplanade Peregian Beach.
Noosa Council documents
One Household Only
8. The premises must be used in accordance with The Noosa Plan definitions for a
Detached House and must be for the exclusive use of one household only.
9. The premises must not be used as Multiple Housing and/or Visitor Accommodation or
any other residential use as defined by The Noosa Plan.
Landscaping
10. A minimum of 20% of the site must be retained as soft landscaping.
Relocation of Street Tree
11. The property driveway must be located to avoid the Pandanus tree in the street verge.
Alternatively, a request must be made to Council to relocate or replace the tree clear of
the driveway.
ENGINEERING
Site Access and Driveways
12. A sealed access driveway must be provided from the formation in Peregian Esplanade
to the garaging of the proposed development. The works must be undertaken in
accordance with an Operational Works approval and must include in particular:
a. a driveway crossover in generally in accordance with Council’s standard drawings
RS-049 and RS- 050 and any associated addendum
b. crossfalls and gradients in accordance with Australian Standard AS2890: Parking
Facilities
c. the earthworks within the road reserve must be kept to the minimum required for
the construction of the driveway
d. no permanent retaining structures are to be erected in the road reserve. The
surface of the road reserve adjacent to the proposed works must be shaped to
ensure that no trip hazards are created within the road reserve
e. the relocation or modification to any existing services in the road reserve (both
above ground and below ground level). If required written approval from the
relevant service authority must be submitted to Council as part of the operational
application
f. No trees in the road reserve are to be removed without prior written approval from
Council.
Stormwater Drainage
13. Stormwater runoff from the development must be disposed of on-site without causing
scour or damage to the subject site or any adjoining property.
14. A site specific Stormwater Management Plan must be submitted as part of the Building
approval.
Geotechnical Stability
15. All works must be carried out in accordance with the recommendations contained in a
site-specific geotechnical investigation and report for the proposed development. The
report must be submitted as part of the building approval
16. Certification must be submitted to Council from a qualified person* which certifies that
the completed development has been constructed in accordance with the
recommendations contained in site specific geotechnical report.
*(Refer to advisory Note)
Page 3 of 5
Document Set ID: 21104713
Version: 8, Version Date: 20/03/2020 Print Date: 20 March 2020, 3:40 PM