Council archive · source document
07/2104 - Response to Information Request [As Published] · 142007.2104
John Devitt PO Box 966 Civic Square Canberra A.C.T. 2608 Australia Phn. 02 62480888 Fax. 02 62480658 Mob.041 7007773 Email. [email protected] Dear Tracy, . Here are copies of My letter of response to you plus Richard Leathers letter, and the Geotech report to be read in conjunction with the plans sent in a plan roll. I will also sent an electronic copy of the response as requested. If you require any further information please do not hesitate to contact me.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 11 pages
Page 2
i John Devitt 16A Truscott St Campbell ACT 2612 Tracy Arthur Noosa Council 9 Pelican St Tewantin QLD 4565 , Tuesday 27-11-07 Project -: Proposed Duplex Dwelling 29 Ventura St Sunrise Beach Lot 124 RP 132134 Dear Tracy The following is in reply to your letter dated 8th November 2007, regarding information requested subsequent to the Application for Operational Works for the above project. Land use 1. Provide an amended Landscaping Plan which addresses the following :- I referred these items back to Richard Leathers from Greenscapes Nursery & Design who has done the design and plan layout for us, his letter is appended. (I chose a local designer specifically for local knowledge of the design requirements peculiar to the Noosa Area.) I trust Richards Leathers’ explanation satisfies these queries. Items 2,3&4 are following. Land Development 3 5.1 Conditon No 20- requires the driveway to be a maximum of 4.5 metres across the Ventura St road reserve. Please amend all drawings to reflect this. Drawings have been amended.
Page 3
§.2 Condition No 33- Please provide a survey plan indicating the location and levels of Council's sewer line and stormwater lines. Appended Hydraulic Drawings amended to indicate IL’s of both sewer and stormwater which in turn satisfies 5.3 Condition 34. 5.4 Condition No 40 — Modications will be needed for the sewer manhole in the proposed driveway. Please supply the details of thes modifications. Engineers Drawing No17003-OW1 indicates height adjustment to be made including a “D3” type trafficable lid. 5.5 Condition No 48- Geotechnical Engineers report is required, demonstrating if the site is suitable for excavation works to be carried out without damage to adjoining properties. The report must also address the means of support for embankments during the construction of this development. Geotechnical Engineers report appended. Engineers Drawing No 17003-OW1 demonstrates the methods by which embankments will be supported during construction. Yours sincerely
Page 4
Greenscapes Nursery & Design Pty Ltd ABN: 13091293612 14/11/07 Tracy Arthur Noosa Council 9 Pelican St Tewantin. 4565. Dear Tracy, With regards to the Application for operational works at 29 Ventura St, Sunrise Beach. Lot 124 RP 132134 the following amendments have been addressed: Ll 14 1.5 1.6 Archontophoenix cunninghamia — We are trying to create clumps of palms for a tropical feel whilst providing height in the garden. The Archontophoenix cunninghamia has been selected as it is on the Noosa council plant list albeit not in that zone. We would like to try and keep these palms in clumps for the aesthetics. These are not being used as a screen This will be provided by the Acmena hemilempra, Acmena smithii, acmena smithii minor and the Alpinnea caerulea planted in front, underneath and behind the palms providing a solid screening of the building. The pot size of the Alectryon coreaceous is 100It and has been corrected on plant code. The Achronicia imperforata is a fantastic screening plant for coastal areas. We grow them in our nursery bushy all the way from the base up and have used them in many places as screening. We would like to keep these in if possible. If you would like to see examples, Noosa Council has used them in the remake of Peregian Beach shopping centre. The Callitris we would like to use along the boundary is Callitris collumnaris. This is also a great screen. The callistemon captain cook is to be planted in front and a secondary plant. The Callitris will offer a far better screen than Banksia integrifolia and will provide the affect we are trying to achieve. We have removed the street trees from the truncation of Ventura St and Orealla Crescent to improve sight lines as requested. The street trees have been moved | mt set back from the kerb to improve shading to the street as requested. Greenscapes Nursery & Design 468 Mckinnon Dve, Cooroibah. Qid. 4565. Telephone: 07 54556825 Fax: 07 54556841 Mobile: 0403709454
Page 5
If you would like to discuss any of these matters further, please contact me directly on 07 54556825. f will be happy to go through the design with you and discuss what we are trying to achieve. Yours Sincerely Richard Leathers Dip. Hort. Greenscapes Nursery. Greenscapes Nursery & Design 468 Mckinnon Dve, Cooroibah. Qld. 4565. Telephone: 07 54556825 Fax: 07 5455684 I Mobile: 0403709454
Page 6
: 14 November, 2007 ale RA tiad SCG Reference: 17003(S) John Devitt . C/- Space Structures Australia Pty Ltd PO Box 996, Civic Square Canberra Q 2608 SOIL TEST & FOOTING REPORT: Lot 29 Ventura Street, Sunrise Beach . 1.0 INTRODUCTION: This company has performed a site classification in accordance with AS 2870-1996 and made recommendations based upon the classification for a building to be constructed at the above site. This report does not include an assessment of Slope Stability, Landslide Risk, or specifications for damp proofing, termite ‘protection, moisture barriers, tie down, bracing or structural member sizing. . This report relates only to the above property and proposed construction as described below: Proposed Construction: Residential Units Timber / Block Timber Slab on Ground Timber / Concrete Cut Fill Pad Building Platform: This report must be read and considered as a whole. All of our recommendations, foundation sections and appendices must be read, considered and followed by all people involved in this project to ensure adequate long term performance of the footing system and the structure it supports. If you are unsure of any of the requirements herein, you must seek clarification from this office. 2.0 SITE CLASSIFICATION: After considering the results of our field investigation performed on 23/1/2007 we have classified this site as: Class P/S TOUTS f 07 5447 2634 @ [email protected] Prose MEM ecer ta eee CI Td 18 duke st sunshine beach q.4567 STRUCTURAL + CIVIL * GEOTECHNICAL CL LC Re eT cey
Page 7
The classification has been calculated from test work performed on the soil profile encountered on the day of our fieldwork and consideration of AS2870-1996. The 'P’ classification relates to the loose sands encountered in the upper profile of our test sites. “Any disturbance of the soil profile, may result in a change to the classification. The attached design, has allowed for the influence of the earthworks described in section 5.0 below. 3.0 SITE DESCRIPTION: The construction area has a gradient in the order of 7% has been cut and filled to form a level pad. Vegetation on the construction area (and nearby surrounds) consists of grasses and scattered trees. The existing surface drainage is good and sub-surface drainage is good. 4.0 FINDINGS: The soil profiles encountered are shown on the attached log sections. No water table was encountered during our testing program. The sandy soils encountered are susceptible to collapse when unconfined. This may effect excavations and result in additional earthworks and increased concrete volumes. For further information please refer to the attached critical line diagram. The samples classified on site were assessed as having low to negligible plasticity, therefore laboratory testing was considered unnecessary. We have assessed the expected differential movement of the soil profiles encountered to be the equivalent of a site with a Ys of less than 20mm. For buildings within the scope of AS 2870-1996, safe bearing is available at 300mm into the NATURAL MEDIUM DENSE SILTY SANDS. This strata is shown shaded on the attached logs. 5.0 SITE PREPARATION DETAILS: Where a retaining wall is required, a cut batter of 1 to 2 (vertical to horizontal) in the sand profile taken from the base of the proposed wall should be excavated. These earthworks must incorporate shallow surface spoon drains at the base and along the high side of the cut. Drains must have an efficient outflow down-slope and clear of the construction area. The exposed face should also be protected against the potential for stormwater erosion. Should these recommendations be un-achievable the builder should seek guidance from this office on temporary shoring, benching or other suitable techniques. Areas where existing structures or trees are removed shall be backfilled with engineer approved fill material compacted in accordance with AS2870-1996, or alternative measures to be provided by the engineer. Any loose or soft material uncovered in the site preparation shall be removed and replaced with approved fill material compacted in accordance with AS2870-1996, or alternative measures to be provided by the engineer. Site drainage during construction is important. Stormwater run-off should be diverted away. from any foundation excavations and not be able to pond within 5.0m of the building footprint. Temporary spoon drains or other practical methods should be used. We recommend using a footing system as per the attached plans and details on the prepared construction pad. For the design to be valid the cut/fill line must be in the position shown on our footing plan. Any variation must be brought to the attention of this office before continuing work. SCG CONSULTING ENGINEERS 2 SCG Ref: 17003(S)
Page 8
Where site drainage and landscaping does not conform to the specifications of AS 2870-1996 and CSIRO information Service Sheet BTF 18 (2003) significant damage to the building can be expected. A single copy of this document is issued with the original issue of this report. Please consult your builder or contact this office to obtain a copy. 6.0 FOOTING AND SLAB SPECIFICATIONS: Footing Details: All footings must be founded a minimum of 300mm into NATURAL MEDIUM DENSE SILTY SANDS _ . (shaded. on.the-attached log sections): Dimensions ‘and reinforcement fequiréménts are detailed in the following footing plan and cross-sections. Where the founding level is deep or is covered by the introduction of fill the footings are to be increased in depth to reach the level. Alternatively the footings can be supported on backhoe dug or drilled piers founded at or below the founding level. Refer to this office for details. Where unexcavatable rock is encountered at depths shallower than the founding level, the strip footing (non-retaining) depth may be reduced accordingly to a minimum of 150mm providing the footing is founded a minimum of 100mm into un-weathered or un-disturbed rock. Additional reinforcement shall be provided in the footing at the rock/soil interface, refer to attached details. Backhoe Piers Supporting the Footings: Where the NATURAL MEDIUM DENSE SILTY SANDS is deep or to be covered by fill the footings can be supported on backhoe piers founded at a minimum of 300mm into the NATURAL MEDIUM DENSE SILTY SANDS. These backhoe piers must be full trench width, 1000mm long and be at a maximum spacing of 3000mm center to center. Drilled Piers Supporting the Footings: Where the NATURAL MEDIUM DENSE SILTY SANDS is deep or to be covered by fill the footings can be supported on 350mm diameter drilled piers founded at a minimum of 300mm into the NATURAL MEDIUM DENSE SILTY SANDS. , Where drilling piers is not practical the footings can be supported on backhoe piers (see cross-section ). Where unexcavatable rock is encountered at depths shallower the founding level the piers shalt be augered a minimum of 100mm into un-weathered or un-disturbed rock. Drilled Pier Reinforcement: [Pier Depthmm | Perimeter Piers | Slab Piers | up to 1500 None required none required 1500-2500 2xN12bars none required 2500-4000 4xN142bars 2xN12bars 4000-6000 6xN12 bars 4xN12bars Floor Slab Details: We recommend reinforcing the floor slab as shown with SL82 slab fabric and the thickenings as specified. Where the foundation level of these thickenings is below prepared pad level, it may be advantageous to excavate them at the same time as the perimeter footing. Where the beams intersect the perimeter footing blockbase, their base must be graded down to the footing base level, 3 x N12 bars must be cogged into the footing, and lapped 500 with the beams trench mesh. Refer to the attached details. SCG CONSULTING ENGINEERS 3 SCG Ref: 17003(S)
Page 9
A levelling layer under the floor slab is to comprise of granular material compacted in 150mm layers. Either well graded sand or crusher dust can be used. An approved polyethylene damp proof membrane of 0.2mm (min.) thickness is to be placed over. the levelling layer. Laps are to be a minimum of 200mm and be taped. All service penetrations and punctures are to be fully taped. The membrane is to be extended down the inside face of the perimeter footings. Where rock is encountered within the slab area and encroaches within the slab depth it should be excavated to a level which enables placement of a 100mm (min.) layer of granular material under the slab. Notes: - -- es Alt building dimensions are to be obtained from the approved plans. The builder must ensure that the final pier placement meets all the requirements of this report (both written specifications and cross-sections). All excavations must be totally free of alt loose material and debris before pouring. They must be cleaned out so that the concrete is poured onto undisturbed ground. Tamping and/or watering loose material is not acceptable. We strongly recommend footing excavations be inspected by a qualified person with appropriate experience to confirm the founding material and level is as nominated herein. Similarly all preparations should be inspected prior to the pouring of concrete by a qualified person with appropriate experience to confirm that the workmanship and construction conforms with the details and recommendations contained herein. Tited Areas: In areas where ceramic floor tiles or brittle coverings alike are required we recommend increasing the size of the slab mesh by one grade. Use flexible adhesives when affixing tiles and delay the laying for as long as possible (at least 3 months, preferably 6 months) after the slab is poured. Reinforcement: Reinforcement is to comply with the following:- a) Concrete cover around the reinforcement must be 40mm to unprotected ground, 40mm to external exposure, 30mm to the membrane in contact with the ground, and 20mm to the internal surface. The slab fabric shall be placed towards the top of the slab within the zone defined by these limits. We recommend 30mm top cover. b) Slab fabric must be lapped by one full panel of fabric so that the two outermost transverse wires of one sheet overlap two outermost transverse wires of the sheet being lapped. Slab fabric is to be supported on bar chairs placed at 800mm ctrs. c) Trench mesh must have all cross wires cut flush with the outer main wires. Trench mesh in slab and edge beams must be overlapped by the width of the fabric at "T” & “L’ intersections. Trench mesh must be spliced, where necessary, by a lap of 500mm, d) Pre-Fabricated footing cages or reinforcing bars at “T” & “L” intersections are to have a Y12 corner lapping bar top and bottom and lapped 500mm with adjacent bars. e) The minimum tap length of reinforcing bar is to be 500mm or 25 bar diameters, whichever greater. SCG CONSULTING ENGINEERS 4 SCG Ref: 17003(S)
Page 10
7.0 LIMITATIONS: Field Testing Limitations The soil profiles reported in our Log Section should be representative of the soil conditions over this site. In some cases soil conditions may change dramatically over short distances, therefore exploration programs may not locate all variations. If site excavations reveal soil conditions that are different from those shown in the attached log sections we must be immediately notified. Changes to the site classification and/or footing design may be necessary. Previous Excavations The recommendations contained in this report have not taken into consideration the long term effects of any previous, current or potential subsurface excavation mining or potential slope instability problems. If a slope stability assessment is required for this allotment we can arrange for this to be done, but that type of report is beyond the scope of our commission and fees in this report... -.-- - Client Supplied Information In writing this report we have considered all the information supplied to us by the client. Should the client or his agent have omitted to supply us with relevant information our report may be irrelevant and / or inappropriate. We do not take responsibility for the consequences in such cases and we will make an additional charge if as a result, more testing or re-writing of the report is necessary. General Recommendations for Builders/Owners: Underground Services Where structures are built over uncontrolled fill, services will need to be supported so that settlement of this fill does not cause them damage or cause incorrect alignment. Plumbing Arrange plumbing fixtures so that the slab and beam penetrations are kept to a minimum and where necessary sleeved to allow for movement with 40mm thick closed cell polythene or similar material. Where the penetration is within 150mm of the base of a beam or footing, the depth of this footing element should be deepened by approximately twice the diameter of the penetration. All plumbing and drainage must comply with the requirements of the National Plumbing and Drainage Code. Drainage The ground surrounding the building site must be graded and drained so that water is shed away from the house area in all directions. Particular attention should be given to all drainage and plumbing trenches so that they do not introduce water to the foundation soil, and destabilise the footings. Correct drainage is an essential part of our recommendations and design. If the site is not prepared correctly, excessive soil moisture may accumulate in some areas, which may lead to wall and/or floor movements. Roof water should be diverted away for the building as soon as the roof is installed. Where building delays occur, temporary downpipes may be necessary. Bracing for Wind Forces Unless noted, we do not detail slab thickenings or pad footings to conform to wind bracing. Where a bracing wall is to be bolted to a slab, 40mm bottom concrete cover attained for a radius of 150mm is required around the bolts unless noted by other consultants. Inspections: We require 24 hours notice if you require engineers site inspections. Inspections can be booked between 8.30am and 4.30pm Monday to Friday by telephoning 07 5447 5544. Site Classification: The site classification is calculated in accordance with the "AS2870-1996 Residential slabs and footings-Construction” and relates to the estimation of Ys, “The characteristic surface movement’ within reactive soil profiles. The limits used for this classification are as follows; [Predicted Surface Movement _] Class | Ys = <=20mm $s Slight Ys = >20 - 40mm M Moderate Ys = >40 ~ 70mm H High Ys => 70mm E Extreme Problem sites Pp Problem Foundation Maintenance and Owners Responsibilities Trees and dense shrubs must be kept well away from the building. In all types of soil conditions, if an automatic watering system irrigates within 2.5 meters of a footing, instability problems may occur. Water should not be allowed to pond on the ground near the building. SCG CONSULTING ENGINEERS 5 SCG Ref: 17003(S)
Page 11
Definitions: Controlled Fill — Man placed soil which has sufficient bearing to support a structure according to AS 2870-1996. Fill certified at Level 1 according to AS 3798 is controlled fill. Partially Controlled — Man placed soil which appears to have been compacted under controlled conditions, but as the time of preparing this report, no compaction certificate suitable for compliance to Level 1 of AS 3798-1996 had been presented. Uncontrolled Fill — Man placed soil (overlying the natural soils) which is not adequate to support a normally loaded footing or floor stab. Unexcavatable Rock — Strong material including shaley material and strongly cemented sand or gravel + = =: --that-does not soften in water-or collapse under the ‘combination of loading and wetting: Material that cannot readily be excavated by a backhoe may be taken to be rock. Excavatable Rock — A rock-like material which does not shrink or swell with changes in soil moisture, but is readily excavatable with a conventional backhoe. . Load Bearing Wall - In our design work a load bearing wall is defined as any wall imposing on the footing a service load greater than 10kN/m. A load bearing wall will normally be supported by a slab thickening or footing in our slab designs. , Natural (Strata) - Refers to soil that is neither fill or imported material but one that is in its original undisturbed state and position. Gravel — Coarse soil particles, larger than sand size, but less than 60mm in diameter. Cobbles - Rocks greater than 60mm in diameter but less than 600mm in diameter. Boulders ~ Rocks larger than 600mm in diameter. NOTE : The information contained herein has been compiled following our field and laboratory testing, accepted engineering theory and discussions with, and information supplied by our client, whom is noted at the head of this report. We offer no warranty for the use of this report by other pgftles without prior written consent from this office. for and on behalf SCG CONSULTING ENGINEERS SCG CONSULTING ENGINEERS 6 SCG Ref: 17003(S)
Page 12
SCG CONSULTING ENGINEERS LOG SECTIONS Ref No.17003 Depth TEST SITE No 1 100 Silty Sand SM 200 Fine Grained , Pale Grey 300 Roots , Moist , Loose. 400 600 600 700 800 | __. SiltySand SM... . 900 Fine Grained , Pale Grey 1000 (White) , Moist , Loose. 1100 3. i 1200 |, , 1300 fe" a 1400 a 1500 ‘ % Sedans 1600 |& Hand:Auger..” 1700 1800 1900 2000 vU TEST SITE No 2 = a|-=/-/=|0 -a[olalo Se co| co] eo] of eo] oe] oo] ro] ry] Po Po| > mmr oe : eer eee Depth = mm below ground level. P = blows per 100mm penetration with an approved 9kg penetrometer. Notation such as (SP) refers to the soil description to Table A1 AS1726 ‘Guide to the description f identification and classification of soils’. Solid lines represent sharp interface between different soil types. Dotted lines represent gradation form one soil type to another. Abbreviations used UTP - unable to penetrate, Bec. ~ becoming, N.S.L. Natural Surface Level, Med. - medium, MW /j - Moderately weathered EW - extremely weathered, Plast. - Plasticity No recovery means unable to extract samples from the base of the bore hole because the soil will not bind in the auger head. The colour of the soil is often abbreviated, for example Gy = grey Or = orange. (Ls=?.?%) Indicates sample location and Linear Shrinkage result. The footings must be dug into or supported on piers dug into the shaded material. SCG CONSULTING ENGINEERS 7 SCG Ref: 17003(S) l
Used in these records
07/2104 - Response to Information Request [As Published]Related documentApplication case desk ↗
About this file
- File size
- 498 KB (small file)
- File type
No other editions are linked here.