Construction Phase
~
Objective The Contractor will install the Bioretention System in accordance with the Works
drawings.
Actions Bioretention systems to be constructed at the end of civil works for the
development.
Bioretention systems used for sediment basins during civil works construction
shall have sediments removed prior to layout of bioretention zone.
Construct Bioretention systems in accordance with steps as detailed in "Water by
Design Construction and Establishment Guidelines: Swales, Bioretention
-
Systems and Wetlands" Version 1 dated February 2009.
Contractor to conduct regular watering of all planted bioretention systems until
such time as plants are established.
Contractor to ensure bioretention systems are protected from sediment laden
stormwater runoff during construction period or only install once upstream
catchment is stabilised.
Monitoring The Contractor will carry out weekly inspections of the Bioretention system
(Including three monthly during the defects liability period). The following will be
examined at each inspection:
)> Sediment build up on the surface
)> Health of vegetation
)> Pondage during major storms not infiltrating into the sand
)> Erosion at the outlet
)> Pondage during minor storms
Reporting Contractor to maintain a log of inspections, watering and other actions.
Records are to be logged and kept for verification of compliance on a need basis.
Bio-retention designer I Engineer shall perform inspections during construction
stage and fill out Water by Design forms for compliance.
Incidents )> Bioretention systems not installed correctly
)> Sediment builds up on the surface of systems.
)> The vegetation dies off.
)> Pondage of water is in excess of one hour.
)> Erosion occurs.
)> Pondage of water occurs at every minor rainfall event.
)> Weed growth occurs.
Corrective Action Contractor to amend installation to ensure it complies with Works drawings.
The Contractor will check up stream sediment control and fix failures. The
sediment build up will be shovelled off the non-woven geotextile of the
Bioretention systems. The geotextile will be replaced at the beginning of the
defects liability period
Unsuccessful plantings will be replaced as required. A normal allowance of 10%
should be made for unsuccessful plantings. Ensure watering rates are adequate
and increase if necessary.
Replace geotextile where used, check and if necessary replace sand media with
coarser sand. Check that slottedpipe is not blocked and outlet free draining.
Replace and repair where necessary.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
REFERENCED DOCUMENT - MCU30/0030Related documentApplication case desk ↗
About this file
- File size
- 19.1 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.