ADG Consulting Pty Ltd
5 Dewatering methodology
5.1 Basement excavation and shoring
Based on preliminary information provided by Seymour Group, existing ground levels within the
proposed basement footprint are approximately RL 2.4 m Australian Height Datum (AHD). Excavations to
facilitate the basement construction are proposed to extend to an approximate depth of 3.5 m below
existing ground level (bgl), corresponding to an approximate elevation of ‐1.1 mAHD. Localised deeper
excavations may also be required for other structural elements (i.e. lift pit and footings) across the site.
It is understood the excavation/basement perimeter will generally be stabilised using a contiguous secant
pile wall, except in proximity of the proposed pool on the northern side (facing the vacant parkland to
the north of the site) and as such will limit the potential for ground movement and instability of
surrounding lands, services and structures (refer to Appendix C).
Groundwater seepage was not encountered at the time of drilling to a depth of 4.5 mbgl during the
Geotechnical Investigations on the site in 205 (PTG Consulting, 2025). However, ADG notes that, typically,
the groundwater levels in the area are encountered at levels of approximately RL 0.5 m to RL 1.0 m.
Fluctuations of +/‐ 0.5 m are typically noted in the area. Groundwater levels are also likely to be subject
to fluctuations associated with the seasonal and climatic conditions, as well as tidal variations and
significant rainfall events.
It is expected that the development will include a ‘tanked’ basement to prevent the requirement for a
permanent dewatering facility at the site.
5.2 Groundwater extraction
Dewatering is anticipated to be undertaken using a series of 40 mm diameter PVC spears installed at
1.5 m intervals around the internal and external perimeter of the excavation. Alternatively, well point
dewatering may be appropriate within the internal face of the shoring wall. The final dewatering method
is subject to engagement of a shoring and dewatering contractor, as different contractors may specialise
in different methods of achieving the required dewatering drawdown. Preference should be given to
dewatering primarily on the internal face of the shoring wall, with preference for minimal dewatering
external to the shoring system to assist in minimising the extent of the cone of depression in the water
table (unless expressly required to limit hydrostatic force on the shoring system) and thereby limit
potential ground movement that may affect surrounding structures and services.
The basement excavation must be dewatered to a minimum of approximately 1.0 m below the deepest
point of excavation to allow construction to be undertaken in dry conditions. The water table (approx.
0.5 mAHD) is therefore expected to be lowered by at least 2.6 m in the locality of the basement
excavation footprint to a maximum of approximately ‐2.1 mAHD throughout the basement footprint.
Deeper localised dewatering may be required for the installation of a lift overrun pit and/or other
structural elements.
It is proposed that the development will include a ‘tanked’ basement to prevent the requirement for a
permanent dewatering facility at the site. Similarly, no permanent groundwater dewatering is proposed
or likely to occur as a result of the development, with all services and pipework proposed to be situated
above standing groundwater elevations (that is, at elevations above 0.5 mAHD) and subject to the
nominated hold points at Section 5.7. Where any deviation is proposed from this arrangement, all
pipework within the saturated zone, that outlets direct to waterways must be fitted with buried
headstocks at suitable intervals to prevent ongoing dewatering of groundwater along pipework bedding.
5.3 Extraction/discharge rates and volume
5.3.1 Dewatering extraction calculation based on subsurface soil profile
The dewatering extraction rate, area of influence and cone of depression has been estimated using the
Western Australian Department of Water and Environmental Regulation Cone of Depression Calculator.
ADG1777.25 Dewatering Management Plan_Rev0_01.05.25 Page 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix G - Dewatering Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 10.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.