Minor Change Existing Approval OPW22/0273.02

of 7

Text shows just the words. Original shows the document exactly as it was published.

                      a.      the driveway surfacing must consist of either an approved hot mixed asphaltic concrete
                              or patterned/plain concrete.
                      b.      the driveway must be in accordance with the requirements of AS2890.1 Off-Street Car
                              Parking for longitudinal and crossfall gradients.
                      c.      the driveway must be constructed so as to not concentrate or direct stormwater runoff
                              onto neighbouring properties
                      d.      underground service conduits for water supply, electricity and any other services must
                              be provided as part of the access driveway
                      e.      have a minimum clearance of 500mm from any Unitywater/Energex/Telstra asset,
                              unless a written approval is obtained from Unitywater/Energex/Telstra and submitted
                              to Council.
                      f.      any stormwater kerb outlet in close proximity to the edge of the new driveway must be
                              provided with an approved kerb adaptor
                      g.      any existing kerb sections requiring removal due to the works must be saw-cut and
                              removed to allow for a smooth and neat finish with the new driveway
               24.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer.
                      Stormwater Drainage
               25.    The constructed driveway must not cause additional ponding on the road formation or the
                      road reserve.
                      Environment (Erosion and Sediment Control)
               26.    Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must
                      not be released from the site or to waters within the site, or be likely to be released should
                      rainfall occur, unless all reasonable and practicable measures are taken to prevent or
                      minimise the release and concentration of contamination.
               27.    The contractor must ensure non-essential exposure of soil is prevented by restricting the
                      extent of works and minimising the duration of soil exposure to adverse weather conditions.
                      Exposed areas must be suitably covered/stabilised/reinstated as soon as practicable and
                      prior to any predicted rainfall occurring.
               28.    Erosion and sediment control measures must be installed and maintained to minimise
                      erosion on the site and to minimise the export of sediment and associated pollutants from
                      the site. The erosion and sediment control measures must be designed, installed and
                      maintained in accordance with current best practice standards (refer to advisory notes).
               FOLLOWING CONSTRUCTION
               29.    A final inspection and approval of the new driveway and completed reinstatement works by
                      Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
                      inspection.
               30.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the requirements of this Operational Works
                      permit.
                      Bonds
               31.    Bonds must:
                      a.      meet the requirements of council’s relevant Planning Scheme Policy for performance
                              and uncompleted works.
                      b.      have approval of the bond calculations and amount from Council prior to lodgement
                      c.      be lodged with Council and accompanied by the Bond Administration Fee/s.


                                                                                                       Page 4 of 7
Document Set ID: 22624275
Version: 2, Version Date: 19/10/2023

Used in these records

About this file

File size
160 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval OPW22_0273.02.pdf · 160 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.