Performance outcomes Acceptable outcomes
Buildings and structures are designed to minimise Buildings or structures that are visible from and accessible
opportunities for vandalism. from apublic street or laneway—
(a) avoid the use of solid fences and blank walls which
attractgraffiti. Where solid blank surfaces are
unavoidable, measures in the form of landscaping,
creepers, murals, Vandal resistant paint, etc. are
used;
(b) with windows at ground level use measures that
deterbreak and enters; and
(c) are constructed to be vandal and graffiti proof.
Earthworks and drainage Table 6.7.1.3 Criteria for assessment (Part)
Performance outcomes Acceptable outcomes
Earthworks and drainage
PO18 AO18 Not Applicable
Filling, excavation and retaining structures do not directly, Filling and excavation works are designed and constructed No filling or excavation works are required.
indirectlyor cumulatively cause adverse impacts external to to ensure overland flow and/or flooding is not worsened,
the development site by— impeded,or otherwise diverted to adversely affect other
(a) causing ponding of water on the site or nearby land; properties or downstream environments.
(b) increasing flooding, which adversely affects the
safety or use of any land upstream and
downstream; or adversely affecting the flow of water
in any overland flow path.
Environment and heritage Table 6.7.1.3 Criteria for assessment (Part)
Performance outcomes Acceptable outcomes
Environment, heritage and scenic amenity
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 2 - Code Responses.pdfRelated documentApplication case desk ↗
About this file
- File size
- 535 KB (small file)
- File type
No other editions are linked here.