CONCLUSION
This Stormwater Management Report has outlined how the stormwater run-off from the site is to be managed to
comply with the relevant requirements and minimise any adverse impacts to the downstream catchments.
• Surface run-off from the proposed development will largely maintain the existing discharge characteristics.
Peak flow rates in developed conditions will be attenuated to be no worse than existing peak flow rates, and
run-off will be discharged towards the downstream undeveloped bushland allotments as the lawful point of
discharge.
• Field inlet pits within the driveway will be capture surface run-off and provide house connections for roof
water drainage to be discharged.
• All run-off from the development will be attenuated using a 45.6m³ below ground attenuation tank with a
140mm low flow orifice and overflow weir that has been shown to not increase to existing peak flow
discharges from the site under developed conditions for all modelled storm events.
• During construction, erosion and sediment control measures are to be implemented to minimise potential
contaminants impacting the downstream receiving environment in line with the objectives of Appendix 2 of
the SPP. A site-specific erosion and sediment control plan has been developed using best practice
management principles to achieve these objectives.
• The proposed stormwater treatment train has been modelled in MUSIC and found to achieve the stormwater
improvement quality targets required to comply with the Noosa Plan 2020. The treatment train consists of
Ecosol litter baskets (200um mesh) or equivalent providing treatment to the driveway areas, and an end of
line bioretention garden to treat and infiltrate attenuated run-off from the development.
• Runoff from the development will be discharged via infiltration from the bioretention garden area into the
surrounding soils assisting with groundwater replenishment, with larger flow events able to overtop the
downstream lip of the bioretention area to discharge as sheet flows to minimise flow concentrations and
protect the downstream environment from erosion and scour.
• The proposed stormwater solution is considered to minimise any adverse impacts to the downstream
environment arising from the stormwater run-off while also meeting the stormwater quality and quantity
targets required for the development and is therefore a complying solution for the proposed development.
Project number 20220156
File RECOR Stormwater Management Report - 20220156.docx, 2022-08-08 Revision 0 Page 18 of 26
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.